HIGH COURT MALAYA PENANG
PENANG DEVELOPMENT CORP – Appellant
Versus
TEOH ENG HUAT & ANOR – Respondent
[Civil Appeal No: 12-31-86]
[1] In the Sessions Court at Georgetown the respondents/purchasers had sued the appellant/ vendors, a statutory body set up by the Penang State Government pursuant to the Penang Development Corporation Enactment, 1971, (the Enactment), for the recovery of liquidated damages for breach of contract for late delivery of a dwelling house with interest thereon and costs. It will be more convenient if I referred to the appellants and the respondents as the defendants and the plaintiffs respectively.
[2] More particularly, by a sale and purchase agreement in writing dated 12 December 1979(the agreement) entered into by the plaintiffs as purchasers and the defendants as vendors, the plaintiff had agreed to purchase from the defendants, a dwelling house known as 14, Lorong Mahsuri 10, Bandar Bayan Baru, Penang (the dwelling house) at a price of RM82,364.
[3] The agreement by cl 11, provided that the dwelling house would have to be completed and vacant possession thereof given to the plaintiffs within 18 calendar months from the date of execution thereof.
[4] By cl 25(b), it was provided that in the event of non-compliance by the defendants with the requirements of cl 11, the defendants would indemnify the plaintiffs by the payment of interest on the purchase price at the rate of 11 per centum per annum calculated from day to day commencing immediately from the due date until the date of delivery of vacant possession of the dwelling house.
[5] It was common ground that although according to the terms of the agreement the defendants ought to have completed the dwelling house and delivered vacant possession thereof to the plaintiffs not later than 11 June 1981, the defendants did not do so until 12 August 1982 despite punctual payment in full of the purchase price by the plaintiffs. There was thus a delay of 427 days in respect of which the plaintiffs claimed liquidated damages amounting to RM10,599 and interest thereon at the rate of 11% per annum from 12 June 1981 until the date of realisation.
[6] In the Court below, the defence had been amended, re-amended and further re-amended. In the event, the argument there revolved around the following issues:
1(1) whether cl 11 was ultra vires the Enactment ?
(2) if any, whether cl 11 had been included in the agreement without the authority of the defendants and so was not binding on it?
(3) whether cl 11 was inserted by mistake and in ignorance of s 2(1) (b) of the Housing Developers (Control and Licensing) Act 1966, (the Act) and, if so, whether it was binding on the defendants?
(4) in any event, if the agreement were found to be binding on the defendants, whether the delay in the delivery of vacant possession of the dwelling house which had been caused by the contractor, who by Government policy was a bumiputra company, and who by the same policy, could not have its services terminated summarily, constituted circumstances, "beyond the control" of the defendants within the meaning of the proviso to cl 11 so as to exempt the defendants from liability?
[7] The learned President found each of these defences to be unsustainable and gave judgment for the plaintiffs as prayed for in the statement of claim and from that judgment the defendants have now appealed to this Court.
[8] Before me, it was contended by Counsel for the defendants that the learned President's interpretation of the relevant legislative provisions relating to authorised expenditure was incorrect and that, had it been correct, she ought to have found that cl 11, and consequently cl 25(b), were ultra vires the powers of the defendants. In particular, it was contended that cl 25(b) which provided for the payment of interest by way of indemnity for late delivery, was neither authorised nor sanctioned by the provisions of the Enactment.
[9] Alternatively, it was contended that if contrary to the defendants primary submission, the defendants had the power by statute, to pay such interest, upon the facts, the inclusion of
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.