Important Points

A plaintiff's undertaking for damages in injunction cases is enforceable despite the absence of a finding that the injunctions were wrongfully granted, allowing assessment of damages following dismissal of appeals.

Subject

Civil Law - Injunctions

Act Referred

Headnote

The court considered the enforcement of a plaintiff's undertaking as to damages following the dismissal of its applications for injunctive relief. The plaintiff's appeal was unsuccessful in the lower courts, leading to the conclusion that the defendant was entitled to an assessment of damages for delays caused by the plaintiff's injunctions. Judicial precedents indicate no necessity for the court to find the injunctions were wrongfully granted to proceed with an assessment of damages. The final order included interest compensation at a rate determined by the court, alongside costs awarded to the defendant.
Table of Content
1. assessment of damages hinges on the validity of the undertaking. (Para 1 , 2 , 3)
2. undertaking must be honored by the plaintiff. (Para 8 , 12)
3. final ruling and costs outlined. (Para 30 , 43 , 72)
4. undertakings must be honored as agreed unless exceptional circumstances intervene. (Para 31 , 32 , 34 , 35)
5. judicial discretion on assessment of damages. (Para 39 , 46)
6. validity of bank guarantees during disputes. (Para 61 , 66 , 68)
7. importance of timely payments based on injunctions. (Para 78 , 81 , 86)
8. loss of interest due to delays from injunctions is compensable under the undertaking. (Para 87 , 88 , 89 , 91 , 92)

[1] The key issue in these two related applications by the defendants for assessment of damages arising out of an undertaking by the plaintiff to pay damages in the event the injunctions applied for are set aside is whether the undertaking applied when the interim injunctions and Erinford injunctions were granted by the courts though finally set aside and decisions of which were affirmed by the Federal Court in that leave to further appeal to it was dismissed.

[2] Related to that is whether the assessment of damages should wait until the outcome of the arbitration which had hardly started beyond a notice to arbitration issued by the plaintiff.

[3] The subsidiary issue is the rate at which the interest should be imposed for the period in which the Bank Guarantees sum could not be released by the banks as the injunctions were in place either as ad interim or Erinford injunctions depending on the point in time and period of time when either injunctions were operative.

[4] For ease of reference, the 1st defendant, Star Media Group Berhad, in both Originating Summons No: WA-24C(ARB)-11-02-2018 ("OS 11") and WA- 24C(ARB)-12-02-2018 ("OS 12") (collectively referred to as "OSs") will be referred to as "Star Media" or the "defendant". The 2nd defendant in OS 11 and OS 12 shall be referred to as AmBank and UOB respectively.

[5] The plaintiff, Jaks Island Circle Sdn Bhd ("Jaks") had opposed both the applications for assessment of damages by Star Media. The applications are in encl 62 for the AmBank Guarantee in OS 11 and encl 55 for the UOB Guarantee with respect to OS 12.

Previous Determinations

[6] The defining milestones in the chronology of events have been culled from the plaintiff's narration in its written submissions filed.

[7] On 23 February 2018, the plaintiff initiated proceedings herein to restrain Star Media from receiving the Bank Guarantees in the sum of RM 25,000,000.00 each from AmBank and UOB.

[8] It is admitted that the plaintiff had given its undertaking as to damages that Star Media may suffer arising out of the injunction applied for, in its affidavits-in-support of the injunction applications dated 23 February 2018.

[9] On 26 February 2018, the High Court granted the plaintiff an ad interim injunction ("ad interim HC injunction") pending disposal of the OSs.

[10] Learned counsel for the plaintiff said it is pertinent to note that Star Media did not file any application to set-aside the ad interim injunction in the OSs.

[11] On 12 July 2018, the plaintiff's OSs were dismissed with costs ("High Court Order").

[12] It was further highlighted that the High Court did not make any orders enforcing the plaintiff's undertaking as to damages.

[13] Dissatisfied with the decision of the High Court, the plaintiff on 13 July 2018 appealed against the High Court Order vide Court of Appeal Civil Appeal No: W-02(C)(A)-1477-07-2018 and Civil Appeal No: W-02(C)(A)-1478-07- 2018 (collectively referred to as "the Civil Appeals").

[14] Star Media also filed a cross-appeal on the ground that the High Court ought to have ordered the plaintiff to make good on its undertaking as to damages. The cross-appeal was subsequently withdrawn at the hearing of the appeal. Learned counsel for Star Media said the withdrawal was on the understanding given by the plaintiff that it may proceed with an application for assessment of

1