1998 MarsdenLR 989
HIGH COURT MALAYA MELAKA
USAHABINA – Appellant
Versus
ANUAR YAHYA – Respondent
[Civil Suit No: 22-28-97]
Augustine Paul JC:
On 27 February 1993 Anuar bin Yahya ('the defendant') and Usahabina ('the plaintiff') entered into an agreement ('the agreement') for the construction of a split-level house according to drawings and specifications prepared by Akitek Suria ('the architect') at a cost of RM1,226,177.40 ('the contract sum'). It was agreed by the parties that the date of commencement of construction work shall be 27 January 1993 and the date of completion shall be 26 October 1993. The contract sum was later reduced to RM989,200.31.
By his writ of summons dated 13 May 1997 the plaintiff commenced proceedings against the defendant for the recovery of a sum RM467,410.98 being amount due on the construction of the house. In para. 3 of the statement of claim the plaintiff alleged that the amount claimed is made up of RM292,554.02 in respect of Architect's Certificate No. 05 bearing serial no AS 9205 dated 15 November 1994 and a sum of RM174,856.96 in respect of Architect's Certificate No. 06 bearing Serial No AS 9205 dated 17 April 1996. On 13 June 1997 the writ of summons was served on the defendant who entered an unconditional appearance to it on 19 June 1997. The defendant did not file his defence within the time limited for doing so, that is to say, by 3 July 1997. The plaintiff allowed the defendant's request for an extension of one week to file the defence. As he failed to file the defence within the extended period the plaintiff entered judgment in default on 15 July 1997. By letter dated 25 July 1997 the solicitors for the defendant informed the solicitors for the plaintiff that:
2. Upon perusing documents in our clients' possession we came across the Contract Document between our mutual clients.Clause 34 of the Contract Document stipulates that a reference to Arbitration shall be made to resolve any dispute. A copy of the relevant Clause is attached herewith for your attention.
3. We believe Arbitration is the best avenue to settle this dispute speedily. Your clients' claims as per Statement of Claim could be assessed accordingly. Our client is alleging a breach of contract too.Particularly on poor workmanship, substandard material and unprofessional conduct.
4. As such we are instructed to give you notice that our client wishes for the disputes to be referred to an Arbitrator. Please nominate an Arbitrator for our clients' consideration. Pursuant thereto kindly confirm whether you are agreeable that the above suit be stayed and the matter be referred to arbitration.
Soon after that the defendant received a copy of the judgment on 31 July 1997. On 6 August 1997 he filed a summons-in-chambers praying for an order, inter alia, that
(a) the judgment in default be set aside,
(b) the matter be stayed and/or referred to an arbitrator,
(c) alternatively, he be allowed to bring in a third party to the proceedings,
(d) alternatively, he be allowed to file his defence and counterclaim.
In substance, therefore, the application of the defendant is to have the judgment set aside and for the case to be stayed pending reference to arbitration or, alternatively, for leave to be allowed to file his defence and other relevant documents.
In his submission before me learned counsel for the defendant contended that as there is a dispute between the parties the matter must be referred to arbitration pursuant to cl. 34 of the agreement and thus the judgment cannot stand. Particulars of the dispute are enumerated in the defendant's affidavit filed on 8 September 1997 where it is affirmed that the works carried out are not in accordance with the terms of the agreement as:
(a) plaintif gagal memasang cermin dengan sempurna pada satu bahagian dinding kolam renang yang turut menjadi dinding bilek besmen (basement),
(b) plaintif gagal menggunakan bahan-bahan binaan bermutu seperti yang sepatutnya,
(c) plaintif gagal memasang bahan-bahan binaan dengan sempurna,
(d) plaintif gagal membersihkan kawasan rumah setelah meninggalkan kerjakerja pembinaan.
(e) plaintif