SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2016 MarsdenLR 283

HIGH COURT MALAYA KUALA LUMPUR
DAYA CMT SDN BHD – Appellant
Versus
YUK TUNG CONSTRUCTION SDN BHD – Respondent
[Suit No: 22C-61-12-2015]



Important Points

The obligations and enforceability of an on-demand performance bond could be restrained only if unconscionability is convincingly established.

Subject

Contract Law - Construction Law

Headnote

The judgment involves a dispute between a main contractor and a principal subcontractor regarding the construction of a mixed development. The court found that the Bank Guarantee (BG) is an on-demand performance bond and issuance of the BG was not unconscionable. The plaintiff failed to prove unconscionable conduct by the defendant and therefore the injunction to restrain the call on the BG was dismissed. The injunction application was denied as the plaintiff did not demonstrate sufficient grounds to support the claim of unconscionability. Following the ruling, the injunction was lifted and costs were awarded to the defendant.
Table of Content
1. dispute context of a contracting relationship. (Para 1 , 2)
2. claims of unconscionable conduct need substantial proof. (Para 8 , 9 , 10)
3. legal basis for performance bonds and related obligations. (Para 21 , 22 , 23)
4. the final decision dismissing the injunction application. (Para 112 , 113)
Lee Swee Seng J:

[1] The dispute here between a main contractor and its principal subcontractor has a familiar story line. The subcontractor as the plaintiff here, had been engaged by the main contractor, the defendant here, with respect to the construction of a mixed development of three blocks of 28-storey buildings ("the project"). The defendant itself is being employed by the landowner/developer as the Main Contractor for all the works under the project for RM270 million ("Principal Subcontract Works"). The contract documents for the Principal Subcontract Works ("Principal Subcontract") between the plaintiff as Principal Subcontractor and the defendant as Main Contractor, consisted of a Letter of Award dated 2 May 2012 and the PWD 203 (Rev 10/83) together with amendments in Attachment A to the letter of award ("the conditions of contract"). The appendix to the conditions of Principal Subcontract is found in attachment B.

[2] It was a term of the conditions of contract that the plaintiff do furnish a Bank Guarantee ("BG") in favour of the defendant for RM13.5 million. It is common ground that the BG is an on-demand BG. By cl 37(c) of the conditions of contract, if the plaintiff commits any breach of its obligations under the conditions of contract, the defendant may utilise and make payments out of or deductions from the BG or any part thereof in accordance with the terms of the conditions of contract.

[3] The completion date of the project was 14 November 2014 ("original completion date") under cl 39. This was extended by 43 days under cl 43 to 27 December 2014 ("final completion date").

Problem

[4] What happened was that there was substantial delay in the project. As is not uncommon, each blamed the other for it. One thing was clear: by October 2014, there was no way the plaintiff could complete the Principal Subcontract Works by the original completion date. Parties then entered into a supplemental agreement dated 28 October 2014 to allow for sectional completion. Originally, the project consisted of Block A of 526 units SOHO (22 storeys and 10 units shop offices); Block B of 365 units of service apartments (21 storeys); Block C (168 units of service apartments (21 storeys)); including 7½ storey podium car park and two-storey basement car park. Under the sectional completion, completion of Block A was referred to as section 1 and that of Block B and C as section 2. The completion date of both sections 1 and 2 remained as 14 November 2014. There was one exception though: the liquidated and ascertained damages ("LAD") for section 1 is RM30,000.00 per day and that of section 2 is RM40,000.00 per day; down from RM70,000.00 per day under cl 40 of the conditions of contract.

[5] A certificate of non-completion ("CNC") was issued certifying that the plaintiff had failed to complete the Principal Subcontract Works by the final completion date. It was only on 22 November 2015 that the plaintiff completed section 1 which is Block A.

[6] According to the defendant, there were slippages in the completion of the Principal Subcontract Works after the Revised Work Programme was given by the plaintiff. There were work stoppages and strikes by the plaintiff's subcontractors and workmen. The defendant proceeded to give a notice under cl 51 of the conditions of contract requiring the plaintiff to remedy the defaults failing which the defendant would terminate the Principal Subcontract. The work stoppages and strikes continued unabated and the site memo, dated 14 December 2015 exhibited by the defendant in exh D 25 in the defendant's first affidavit, set out the number of strikes and work stoppages. The defendant terminated the Principal Su

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top