FEDERAL COURT PUTRAJAYA
OBATA-AMBAK HOLDINGS SDN BHD – Appellant
Versus
PREMA BONANZA SDN BHD & OTHER APPEALS – Respondent
[Civil Appeal Nos: 02(i)-70-08-2022(W) 02(i)-71-08-2022(W) 02(i)-72-08- 2022(W) 02(i)-74-08-2022(W) & 01-(f)-1-01-2023(B)]



Petitioner Advocates:Low Joo Hean,Chan Kim Weng,Kuan Jia Yin ,Respondent Advocate: Lai Chee Hoe,Ooi Xin Yi,Angeline Ang Mei Fong

The court ruled that reg 11(3) of the HDR is ultra vires, invalidating extensions granted under it, and affirmed that claims for liquidated damages were time-barred.

Headnote:(A) Housing Development (Control and Licensing) Act 1966 - Housing Development (Control and Licensing) Regulations 1989 - Regulation 11(3) - Liquidated ascertained damages (LAD) - Appeals concerning the validity of extension of time for delivery of vacant possession - The court held that the extension granted under reg 11(3) is ultra vires and thus void. (Paras 2, 50, 61, 68)

(B) Limitation Act 1953 - The court found that the claims for LAD were time-barred, as the cause of action accrued at the execution of the Sale and Purchase Agreements (SPAs) and the suits were filed after the limitation period. (Paras 15, 18, 100)

(C) Second Actor Theory - The court applied this theory to determine that the reliance on the invalid extension by the developers was valid as it was granted before the execution of the SPAs. (Paras 104-135)

Facts of the case:
The appeals involved purchasers and developers disputing the validity of extensions of time for delivering vacant possession of condominium units, with the purchasers claiming liquidated damages based on a recent ruling declaring the extension provision ultra vires. (Paras 1-7)

Findings of Court:
The court affirmed the High court's decision that the extensions were invalid and that the claims were barred by limitation. (Paras 178)

Issues: The main issues were the validity of the extensions granted under reg 11(3) and the commencement of the limitation period for claims of LAD. (Paras 50, 100)

Ratio Decidendi: The court emphasized that the ultra vires declaration applies retrospectively, affecting all claims based on the invalid extensions. The reliance on the invalid regulation by developers was considered valid as it was in effect before the SPAs were executed. (Paras 50, 178)

Result: Appeals dismissed for Obata and allowed for Prema and Sri Damansara.

JUDGMENT

Hasnah Mohammed Hashim FCJ:

Introduction

[1] There are five appeals which were heard together, given the commonality of issues in the questions of law raised for our determination. One appeal was filed by the purchaser of the condominium units, The Sentral Residences. The other appeals are appeals filed by the developers of the projects, Prema Bonanza Sdn Bhd (Prema) and Sri Damansara Sdn Bhd (Sri Damansara). The appeals were heard together despite there being different parties involved. We heard oral submissions by all learned counsel representing the respective parties and at the end of those submissions, we indicated that we needed time to consider the respective submissions. We have now reached our decision and what follows below are our deliberations on the issues raised and our reasons as to why we have so decided.

[2] The central issue in all the appeals concerns the payment of Liquidated Ascertained Damages (LAD) as a result of this court's decision in Ang Ming Lee & Ors v. Menteri Kesejahteraan Bandar Perumahan Dan Kerajaan Tempatan & Anor And Other Appeals, [2020] 1 MLJ 281 (Ang Ming Lee) declaring that reg 11(3) of the Housing Development (Control and Licensing) Regulations 1989 (HDR) is ultra vires the parent Act.

Appeal No: 02(i)-70-08-2022(W) (Appeal No. 70) & 02(i)-71-08/2022(W) (Appeal No. 71)

Obata-Ambak Holdings Sdn Bhd (Obata) v. Prema Bonanza Sdn Bhd (Prema)

[3] Both appeals have identical issues, with similar facts, and arose from the same development project. Appeal No. 70 is an appeal by Obata against the decision of the court of Appeal dismissing the appeal by Obata against the High court's decision which allowed Prema's application under O 14A Rules of 2012 (ROC). Whereas Appeal No. 71 is an appeal by Obata against the court of Appeal's decision which dismissed Obata's application for Summary Judgment under O 14 ROC 2012.

[4] The Appellant, Obata, is the purchaser and owner of a condominium known as The Sentral Residences (the Project). The Respondent, Prema, is the developer of the Project. The Project comprises 2 towers of service apartments and was governed by the Housing Development (Control and Licensing) Act 1966 (HDA) and the HDR. Thus, the agreement was to be executed with potential purchasers as prescribed under Schedule H of the HDR, whereby the time for delivery of vacant possession and completion of common facilities is 36 months.

[5] However, due to the magnitude and the peculiarity of the bespoke design of the Project, Prema applied for modification of the prescribed agreement to vary the prescribed completion period for the Project from thirty-six (36) months to fifty-four (54) months pursuant to reg 11(3) HDR. The Extension of Time (EOT) was granted by the Controller of Housing (the Controller) on 16 December 2010, two (2) years before the execution of the SPA with the purchasers of the Project. Prema obtained the EOT to extend the time period for delivery of vacant possession and completion of common facilities from 36 months to 54 months. The amended approved provisions are as reflected in cls 25 and 27 of the Sale and Purchase Agreements (SPA). It was only after procuring the approval of the EOT and the amended clauses in the SPA that Prema executed the SPAs with its purchasers.

[6] Obata entered into the SPAs with the approved EOT on various dates which formed the subject matter before the court, namely:

(i) SPA dated 24 July 2012 (Suit 301);

(ii) SPA dated 28 October 2013 (Suit 303); and

(iii) SPA dated 11 July 2012 and 18 July 2012 (Suit 305) − the present appeals before us.

[7] After the Federal court's decision of Ang Ming Lee, Obata commenced proceedings against Prema for the following reliefs:

i. a declaration that any letters given for extension of time pursuant to reg 11(3) of the HDR to deliver vacant possession of the property to the plaintiff and the completion of the common facilities from 36 months to 54 months were inconsistent with the decision of Ang Ming Lee;

ii. a decl

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top