2014 MarsdenLR 750
HIGH COURT MALAYA KUALA LUMPUR
MALIM RESTU CONSTRUCTION SDN BHD – Appellant
Versus
PETRONAS DAGANGAN BHD – Respondent
[Civil Suit No: 22NCVC-225-03-2013]
Important Points
Subject
Contract Law - Construction Contracts
Headnote
(B) Onus to prove - Burden on defendant to demonstrate works were within scope - Defendant could not substantiate claim that all works were included in original contract. (Paras 10(e), 10(f))
| Table of Content |
|---|
| 1. claim for payment of variation order (Para 1 , 2 , 3 , 4 , 5) |
| 2. defendant's arguments against variation claim (Para 6 , 7) |
| 3. pertinent issues arising from the case (Para 8) |
| 4. court's finding on entitlement to payment (Para 9) |
[1] This is a claim by the plaintiff for payment of a variation order works amounting to a sum of RM813,441.35. The defendant disputed the plaintiff's claim.
[2] On 23 July 2007, the plaintiff submitted its tender for the construction and commissioning of a Petronas service station at Lot 273, Jalan Panglima Awang, Kawasan Bandar XXX111, Seksyen 33, Daerah Melaka Tengah, Melaka ("the project") for a sum of RM2,698,000.00.
[3] Based on the plaintiff's above mentioned tender, the defendant on 13 August 2007 appointed the plaintiff as the contractor for the project for the contract sum of RM2,698,000.00.
[4] On 13 March 2009, the plaintiff submitted its "Summary of Variation Order" dated 28 February 2009 for the alleged variation works in the sum of RM864,701.35. This was the first time the plaintiff forwarded a document, claiming the sum of RM864,701.35. This claim includes works in relation to the plaintiff's original scope of works namely the construction and completion of the deceleration and acceleration lanes, widening of the access road to which the plaintiff has been duly paid.
[5] On 16 June 2010, the defendant approved a portion of the plaintiff's said claim amounting to a sum RM51,260.00 which said payment was in relation to the construction of the MID structure and compressor which were the additional works requested by the defendant. However, the defendant rejected the plaintiff's balance of claim amounting to the sum of RM813,441.35 as the works carried out by the plaintiff, ie the construction and completion of the deceleration and acceleration lanes, widening of the access road pursuant to the requirements of Jabatan Kerja Raya ("JKR") are the within plaintiff's original scope of works, for which the plaintiff had been duly paid by the defendant.
The Plaintiff's Case
[6] [i] By a Letter of Award, the defendant awarded to the plaintiff, the project described as the Engineering, Procurement, Construction and Commissioning of Petronas Service Station on a piece of land described as Lot 273, Jalan Panglima Awang, Kawasan Bandar XXXIII, Seksyen 33, Daerah Melaka Tengah, Melaka to construct one Petronas service station for a total consideration sum of RM2,698,000.00.
[ii] Prior to the defendant awarding the project to the plaintiff, the plaintiff has tendered for the project based on the Conditions of Contract provided by the defendant.
[iii] Item 6 of the Conditions of Contract state as follows "Contractor to carry out the road widening and upgrading works as required to JKR's approval, with reference to letter JKR (M) 2177 PT 2588 and drawing HRC/RC/MLK/2005-12(CW01) inclusive of related works deem necessary by Local Authority".
[iv] Based on the specific requirements of Item 6 in the Conditions of Contract, ie the construction works must be in accordance with "JKR's approval, with reference to letter JKR (M) 2177 PT 2588 and drawing HRC/RC/MLK/2005-12(CW01)", the plaintiff submitted a quotation of RM2,698,000.00 which was accepted by the defendant.
[v] Prior to the plaintiff commencing construction works of the project, the plaintiff was informed and/or discovered that the original approved drawing plan for the project, furnished by the defendant, referred to in the Conditions of Contract has been rejected by JKR. Pursuant thereto the original drawing plan was subsequently amended and approved by JKR. In the said amended plan, additional works was required and upon the defendant's request, the plaintiff submitted the sum of RM864,701.35 as variation works for the defendant's consideration and approval [see the answer to Question 12 of WSPW-1 and at p 17 of Bundle C].
[vi] Even though at the material time the defendant has yet to confirm and accept the quotation by the plaintiff for the va