SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2010 MarsdenLR 2350

COURT OF APPEAL PUTRAJAYA
HASRAT USAHA SDN BHD – Appellant
Versus
PATI SDN BHD – Respondent
[Civil Appeal No: W-03-242-2008]



Petitioner Advocates:C Soosay Nathan,Mohamad Fahzan Mohd Noor ,Respondent Advocate: Wong Suk May

An admission of debt must be clear and unequivocal for judgment to be granted under the Rules of the High Court 1980, emphasizing the distinction between an inquiry and an admission.

Headnote:(A) Rules of the High Court 1980 - Order 27 r 3 - Judgment on admission of fact - Defendant appealed against dismissal of its appeal to set aside judgment granted to plaintiff based on defendant’s admission of RM1,310,806.02 owed. Court addressed whether the defendant’s letter constituted an unequivocal admission of debt - Dispute arose over the amount claimed by plaintiff. (Paras 1-7, 10, 35)

(B) Legal principles regarding admissions of fact - For a judgment by admission to be granted, the admission must be clear and unequivocal. The court examined prior case law to distinguish between an admission and an inquiry about amounts owed. (Paras 9, 10, 36)

Facts of the case:
Defendant sub-contracted plaintiff for works valued at RM11,720,207.25; plaintiff claimed RM2,040,586.38 as owed, while defendant counterclaimed RM2,158,095.00 for delay and defective works. (Paras 2, 5, 19)

Findings of Court:
Defendant’s letter constituted a partial admission, obligating payment of RM1,310,806.02; however, no judgment was awarded for the full claimed amount, as the claim lacked clarity. (Paras 10, 39)

Issues: Whether the defendant’s letter represented an unequivocal admission of debt rather than an inquiry.

Ratio Decidendi: The court held that the inquiry nature of the defendant's letter did not amount to an admission of liability for the complete claimed amount, warranting the dismissal of the appeal. (Paras 10, 39)

Result: Appeal dismissed with costs.

Table of Content
1. facts of the case and background. (Para 1 , 2)
2. order 27 r 3 related to judgments on admissions. (Para 3 , 4)
3. defendant's claim of inquiry, not admission. (Para 5 , 6)
4. summary procedure for judgments based on admissions. (Para 7 , 8 , 9)
5. defendant's obligation to pay admitted balance. (Para 10)
6. claims and counterclaims of plaintiff and defendant. (Para 19 , 20)
7. assessment of whether admission is unequivocal. (Para 34 , 35 , 36)
8. confusion in claims necessitating trial. (Para 38 , 39)
Azhar Ma'ah JCA:

[1] This appeal is brought by the defendant against the decision of the High Court Judge, Kuala Lumpur, who, on 28 October 2008 dismissed its appeal to set aside the decision of the Senior Assistant Registrar allowing the plaintiff's application under O 27 r 3 of the Rules of the High 1980 (RHC 1980) to enter a judgment on an admission of fact by the defendant for the amount of RM1,310,806.02 and interest @ 8% per annum from the date of the summons until full settlement.

[2] The facts of the case as stated in the trial judge's grounds of judgment are these:

The defendant appointed the plaintiff as its sub-contractor (see Letter of Offer dated 18 October 2000 in encl 4 exhb. "RS-1"). The sub-contract sum was RM11,720,207.25. The plaintiff says that all works under the sub-contract had been completed on 1 August 2002. The plaintiff filed the present action seeking to enter judgment for RM2,040,586.38 which the plaintiff claims is the balance of the sub-contract monies owed to them by the defendant.

The defendant disputes the plaintiff's claim and says that the sub-contract works were to have been completed by 27 February 2001. Therefore, there was a delay of 520 days and the defendant counterclaims against the plaintiff for the sum of RM1,820,000.00. The defendant further claims the sum of RM338,095.70 being costs of rectification works which the defendant says the plaintiff has failed to carry out. Therefore, the defendant claims against the plaintiff a total sum of RM2,158,095.00.

Plaintiff's Case

The plaintiff avers that by an undated letter the defendant requested a confirmation from the plaintiff on the balance due to the plaintiff as at 31 December 2004. In the defendant's letter, the plaintiff was requested to advise the defendant's auditors "of the correctness of the balances as stated below" which according to the defendant's record, the balance due to the plaintiff as at 31 December 2004 is RM1,310,806.02 (see encl 4 exh. "RS-2"). The plaintiff replied that according to its records the correct amount is RM2,040,586.38.

[3]Order 27 r 3 of the Rules of the High 1980, reads as follows:

Where admissions of fact are made by a party to a cause or matter either by his pleadings or otherwise, any other party to the cause or matter may apply to the Court for such judgment or order as upon those admissions he may be entitled to, without waiting for the determination of any other question between the parties, and the Court may give such judgment, or make such order, on the application as it thinks just. An application for an order under this rule may be made by summons.

[4] It is in the light of the above provision that the plaintiff applied for judgment by admission, founded on a letter from the defendant seeking confirmation that a sum of RM1,310,806.02 was due to the plaintiff. For clarity we reproduce the letter in question which reads.

HASRAT USAHA SDN. BHD.

(Co. No 89823-V)

No 50-4-3A, Level 4, Wisma UOA Damansara,

No 50, Jalan Dungun, Bukit Damansara, 50490 Kuala Lumpur

Tel: 03-2715 1088 Fax: 03-2715 2088

PATI SDN. BHD.

17th Floor, Menara 2, Faber Towers

Jalan Desa Bahagia

Taman Desa

58100 Kuala Lumpur

Dear Sir,

Confirmation Request - PJR006 Project

For the purpose of the audit of our Company's financial statement, please advise our auditors of the correctness of the balances as stated below.

According to our records, the balance due to you is:

As at: 31 December 2004 Amount: RM1,310,806.02

Please sign on the space provi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top