1974 MarsdenLR 125
FEDERAL COURT (KUCHING)
AZMI LP, J, LEE HUN HOE (BORNEO), CJ, GILL (MALAYA), CJ
ALLIANCE (MALAYA) ENGINEERING CO SDN BHD
versus
SAN DEVELOPMENT SDN BHD
CIVIL APPEAL NO. 146 OF 1973
Decided On : 05-31-74
For the appellants - S F Chong (Mrs Vohra with him); Chong Bros For the respondents - Patrick Tan; M/s. Yong & Co.
Gill (Malaya) CJ:
This is an appeal by the plaintiffs in the action against the dismissal by BTH Lee J of their application in the High Court at Kuching for summary judgment against the defendants under O. 14 of the Rules of the Supreme Court, 1957.
The application included a prayer in the alternative that the defendants' defence be struck out (a) under RSC O. 21, r. 1 as being a mere denial, or (b) under RSC O. 25, r. 4 on the ground that it disclosed no reasonable answer and was frivolous and vexatious, or (c) under RSC O. 19, r. 19 on the round that it was evasive and did not answer the point of substance, or (d) under RSC O. 19, r. 27 on the ground that it tended to prejudice, embarrass or delay the fair trial of the action, or (e) under the inherent jurisdiction of the Court on the ground that it disclosed no reasonable defence, that it was frivolous and vexatious and that it was an abuse of the process of the Court. The application under the prayers in the alternative was also dismissed.
The facts leading to the action out of which this appeal has arisen are as follows. By an agreement dated 27 January 1966 the defendants contracted to build for the Sarawak Government Phase I of a General Hospital in Kuching. By two agreements dated 21 March 1967 the plaintiffs became the nominated subcontractors of the defendants for the supply and installation of kitchen and medical equipment respectively for the proposed General Hospital Building. The value of the works for the supply and installation of the kitchen equipment was $287,058 and that of the medical equipment was $540,510, making a total of $827,568 under the two nominated sub-contracts.
Clause 6 of each of the sub-contracts provided for the nominated sub-contractor, after the signing of the sub-contract and within seven days of the receipt by him of a written notice from the contractor, to proceed with all reasonable despatch to execute and complete the nominated sub-contract works or the representative sections thereof within the period or respective periods specified in Part II of the Schedule to the sub-contract. There was a proviso to cl 6 of the agreement in the followings terms:
Provided that the nominated sub-contractor shall pay to the contractor as liquidated damages $5000 per week for loss suffered and incurred by the contractor due to the failure of the nominated sub-contractor to complete within the said period or respective periods. ... ."
Clause 7 of the agreement provided for the nominated sub-contractor, within a reasonable time after the receipt by him of the contractor's instructions, to make good all defects shrinkages or other faults in the nominated sub-contract works which the contractor (whether at his own costs or not) was liable to make good under the main contract. The proviso to this clause of the agreement was as follows:
Provided that where the contractor is liable to make good such defects shrinkages or other faults but not at his own costs then the contractor shall secure a similar benefit to the nominated sub-contractor for any money actually received by him in respect of the same."
Under clause 10 of the agreement the defendants as the main contractors agreed, subject to and in accordance with the main contract, from time to time to apply to the Director of Public Works for certificates of payments of the amount which at the date of the application fairly represented the value of the nominated sub-contract works, and within 14 days of the receipt by them of such certificates as aforesaid to pay to the nominated sub-contractors the amounts certified to be due in respect of the nominated subcontract works and any authorised variations thereof less the due proportion of retention money (10%) retained by the employer.
Clause 12 of each of the agreements provided for the contractor's right to deductions or set-off in the following words:
The contractor shall notwithstanding anything in this nominated sub-contract contained be