2019 MarsdenLR 318
COURT OF APPEAL PUTRAJAYA
PORATHA CORPORATION SDN BHD – Appellant
Versus
TECHNOFIT SDN BHD – Respondent
[Civil Appeal No: W-02(C)-2122-10-2017]
Important Points
Subject
Contract Law - Construction Contracts
Headnote
| Table of Content |
|---|
| 1. claim for wrongful termination and financial losses. (Para 1 , 3 , 7 , 10) |
[1] This appeal by the appellant is against the decision of the Kuala Lumpur High Court which had allowed the appellant's claim in part for the sum of RM1,651,383.57 and ordered the sum of RM506,023.67 to be paid by the appellant to the respondent to complete the balance of works as well as the forfeiture of the retention sum of RM437,838.17 towards full settlement of the rectification works.
[2] For the purpose of this judgment, the parties will be referred to as they were in the High Court.
The Factual Background
[3] This appeal concerns a claim for premature and wrongful termination of the subcontract by the defendant and as a result the plaintiff suffered direct losses. The undisputed facts are as follows. The defendant entered into a contract with DAELIM (Malaysia) Sdn Bhd (DAELIM) for the construction of Mechanical Work Package 2 for Fast Track Project 3A in Manjung, Perak ('the Main Contract'). The defendant appointed the plaintiff as the subcontractor on 22 December 2015 to carry out the Mechanical Work Package 2-Piping Works in particular welding and installation of P92 pipe ("the subcontract works"). The value of the subcontract works is RM6,345,000.36.
[4] The parties had a number of meetings and it was agreed that the minutes of meetings were to be incorporated as part of the terms and conditions of the subcontract works agreement ('the Agreement'). The Agreement specified, amongst others, the Contractor's Scope of Works, Work Programme, HSE obligations for the defendant's contractor/subcontractor ('OFC'), Pricing Schedules and Bills of Quantities. Pursuant to cl 2 of the Agreement the plaintiff is required to implement the subcontract works in accordance with the Master Work Programme Schedule as well as the scope of work based on the RFQ Documents Attachment 2A-Addendum 1. The plaintiff's scopes of work covered 10 major areas as stated in the Addendum to the RFQ Documents.
[5] The agreed scopes of works of the plaintiff under the Agreement are as follows:
(a) Installation of pipe (fabrication and erection of pipe and its supports, receiving, launching, marking, fit-up, welding, reporting, testing and commissioning, final document submission);
(b) Supply of manpower for commissioning activities;
(c) Provide accommodation and food for workers; and
(d) Provide consumables and transport.
[6] The plaintiff immediately mobilised its workers on 17 October 2015. However, the piping works were delayed primarily due to the following reasons:
(i) delay in the supply of materials by the defendant;
(ii) the defendant failed to provide sufficient trailers and cranes to shift the materials; and
(iii) fabrication mistake in the spools received from DAELIM.
[7] It is the plaintiff's case that the defendant without providing any reason or giving any prior notice, terminated the Agreement prematurely even though the plaintiff completed a substantive portion of the subcontract works. The plaintiff carried out the subcontract works until 27 May 2016 and invoiced the defendant for the works done. The defendant, however, failed to pay the sum of RM2,027,955.34, that is, the balance sum as stipulated in the invoice for the works done.
[8] The subcontract works were scheduled to commence on 16 October 2015 and the scheduled completion was 15 September 2016. Prior to the commencement of the subcontract works, a number of meetings were held between the parties to discuss and determine the scopes of work and responsibilities of the respective parties. According to the Common Chronology, on 16 October 2015 the parties met to confirm amongst others, manpower mobilisation. On 17 October 2015 the plaintiff's manpower was mobilised on the work site. A kick-off meeting was held on 19 October 2015 for piping works mechanical Package 2-Manjung 5 to review the scopes of work, site arrangement/project master schedule/HSE/QA QC matters.
[9] According to the Common Chronology,