SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 MarsdenLR 2050

HIGH COURT MALAYA KUALA LUMPUR
CRCC MALAYSIA BERHAD – Appellant
Versus
DSG PROJECTS MALAYSIA SDN BHD – Respondent
[Originating Summons No: WA-24C(ARB)-7-02-2021]



Petitioner Advocates:Eunice Kwong ,Respondent Advocate: Lee Shih,Pang Huey Lynn

The court ruled that enforcement of interim measures ordered by an Arbitrator is incompatible with its powers under the Arbitration Act 2005 and is contrary to public policy.

Headnote:(A) Arbitration Act 2005 – Section 19H – Rules of Court 2012 – Order 23 r 1, 45 r 6 – Application by claimant to enforce interim measures ordered by Arbitrator – Plaintiff claimed RM250,000.00 as security for costs due to defendant's refusal to comply – The court found the enforcement incompatible with its powers and contrary to public policy. (Paras 25 - 54)

Facts of the case:

Plaintiff appointed the defendant as sub-contractor for a significant construction project – Allegations of delays led to claims for liquidated damages, resulting in arbitration proceedings.

Findings of Court:

The court explained that the enforcement of the interim measures lacked support from the power conferred under the applicable laws, and thus dismissed the application with costs.

Issues

: Whether the court could enforce the interim measures ordered by the Arbitrator and if it was within its powers to do so.

Ratio Decidendi:

The court determined that security for costs application does not traditionally arise from the claimant but is fundamentally a right of the defendant, making enforcement inappropriate in this instance.

Result:

Application dismissed.

JUDGMENT

Aliza Sulaiman J:

Introduction

[1] This is an application by the plaintiff pursuant to s 19H of the Arbitration Act 2005 (' AA 2005'); O 7, O 28, O 45 r 6 and O 92 r 4 of the Rules of 2012 ('ROC 2012') and/or the inherent jurisdiction of the Court for, inter alia, the following reliefs:

(a) that the decision by the learned Arbitrator, Mr Chong Thaw Sing ('Arbitrator') dated 14 December 2020, pursuant to the application for security for costs under s 19(2)(e) AA 2005 by the plaintiff as the claimant in the arbitration proceedings in ordering the defendant as the respondent in the said proceedings to deposit RM250,000.00 to be held jointly by the parties solicitors ('Interim Measures'), be enforced as if it is a judgment or Order of the High Court;

(b) that in the event the above prayer is allowed, the defendant shall pay security for costs of RM250,000.00 to the plaintiff's solicitors to be held as stakeholders within 14 days from the date of the Order; and

(c) that if the defendant fails to adhere to the Order, enforcement proceedings may be taken against the four directors of the defendant so as to compel them to adhere to the Order.

[2] The cause papers which were filed in this application are as follows:

(a) the plaintiff's Originating Summons ('OS') dated 10 February 2021 (encl 1);

(b) the Affidavit In Support affirmed by Tan Kean Cheong, the plaintiff's Manager on 10 February 2021 (encl 3);

(c) the Affidavit in Reply ('AIR') affirmed by Luke Furler, the defendant's Director on 1 March 2021 and 10 March 2021 (encls 4, 5 and 6);

(d) the plaintiff's AIR affirmed by the same deponent on 16 March 2021 (encl 7);

(e) the defendant's AIR No 2 affirmed by the same deponent on 25 March 2021 (encl 8); and

(f) the plaintiff's Supplementary Affidavit affirmed by the same deponent on 16 April 2021 (encl 18) setting out the chronology of events as agreed by the parties solicitors in "exh-1" and as directed by the Court on the hearing date.

[3] Having considered the cause papers and the parties written and oral submissions, I had dismissed the plaintiff's application with costs of RM4,000.00, subject to allocatur.

[4] The plaintiff has lodged an appeal against the decision of this Court and I now provide my full reasons.

Background Facts

[5] By a Letter of Award dated 15 June 2015 ('LOA'), the plaintiff has appointed the defendant as the nominated sub-contractor for "The Construction And Completion Of Interior Fitout Works For Retail" for the project known as "Cadangan Pindaan Kepada Pelan Bangunan (Rujukan BP T3 20072009) Bertarikh 28 Januari 2009 Kepada Cadangan Pembangunan Bercampur Yang Terdiri Dari 1 Blok Pangsapuri, Pangsapuri Servis Dan Hotel Tingkat 65 Tingkat Yang Mengandungi 3 Tingkat Basement Tempat Letak Kereta, 1 Tingkat Basement Ruang Niaga Dan Servis, 1 Tingkat Lobi Utama Dan Ruang Niaga, 6 Tingkat Podium Ruang Niaga, Tempat Letak Kereta Dan Kemudahan Hotel, 1 Tingkat Podium Kemudahan Rekreasi (Hotel, Pangsapuri Servis Dan Pangsapuri), 2 Tingkat Kemudahan Rekreasi Dan Ruang Mekanikal (Pangsapuri Dan Pangsapuri Servis), 10 Tingkat Hotel (190 Bilik), 16 Tingkat Pangsapuri Servis (160 Bilik) Dan 29 Tingkat Pangsapuri (128 Unit) Di Atas Lot 230 (Asal Lot 35), Seksyen 58, Jalan Lumba Kuda, Off Jalan Ampang Dalam Bandaraya Kuala Lumpur' for the lump sum price of RM15,988,000.00.

[6] On 15 January 2020, the plaintiff wrote to the defendant alleging that there was delay and/or slow progress in the completion of the defendant's work despite the numerous reminders to expedite the same. According to the plaintiff, there is a 569-day delay for the completion of the retail Mock-up and 227-day delay for the completion of Section 1 (Retail). The plaintiff claimed that pursuant to cl 13.0 of the LOA, the defendant was liable to pay liquidated damages ('LD') in the sum of RM2,845,000.00 for the retail Mock-up and RM11,350,000.00 for Section 1 (Retail).

[7] The defendant refused to pay the LD and subsequently filed an application for a Judicial

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top