SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 MarsdenLR 186

COURT OF APPEAL PUTRAJAYA
SAGUJUTA (SABAH) SDN BHD – Appellant
Versus
TRANE MALAYSIA SALES & SERVICES SDN BHD – Respondent
[Civil Appeal No: S-02-3268-12-2011]



The exercise of summary judgment under Order 14 requires an absence of triable issues; certification of claims must be honored unless proven otherwise by substantial evidence.

Headnote:(A) Rules of High Court 1980 - Order 14 - Application for summary judgment - Summary judgment granted for RM3,641,315.73 in favor of the respondent based on certified and unpaid works; appellant's claims of defects found unlikely to succeed as no triable issues raised - Importance of affidavit evidence in determining defenses - Certification confirmed by appellant's consultant and audit confirmation request admissible as evidence. (Paras 13, 14, 21, 24, 35)

(B) Summary Judgment - The court must assess whether there are triable issues sufficient to deny the application; reliance on documentary evidence is crucial - An unfettered right exists for defendants to apply for summary judgment on a counterclaim akin to a main claim. (Paras 11, 15)

Facts of the case:
The appellant, a developer, claimed damages of RM50 million citing defects in air-conditioning installation by the respondent, who counterclaimed for RM3,641,315.73 for unpaid certified services. The High Court ruled without trial, granting summary judgment to the respondent based on the lack of triable issues in the appellant's defense.

Findings of Court:
The court held that certification of payments stood validated and the respondent had legitimately completed its work as per contract requirements. The High Court's conclusion on the non-existence of triable issues was affirmed.

Issues: Core issues included the existence of triable defenses against the respondent's counterclaim and appropriateness of the summary judgment granted.

Ratio Decidendi: The court reasoned that the appellant presented no triable issues nor supported its claims against certification, and upheld that documentary evidence was pertinent in denying defenses to the summary judgment application.

Result: Appeal dismissed with costs awarded to the respondent.

Table of Content
1. background of the appeal and factual context. (Para 1 , 8 , 9 , 10)
2. factual background of the case. (Para 2 , 3 , 4 , 5 , 6 , 7)
3. high court's justification for summary judgment. (Para 11)
4. appellant's arguments presented. (Para 12)
5. explanation of order 14 rules. (Para 13 , 14 , 15)
6. evidence of certification and payments. (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23)
7. response to appellant's claims. (Para 24 , 25 , 26 , 27)
8. assessment of trial costs. (Para 28)

[1] This is an appeal by the appellant against the decision of the High Court allowing the respondent's application for summary judgment under O 14 of the RHC 1980 in respect of part of the respondent's counterclaim amounting to RM3,641,315.73 against the appellant.

Factual Background

[2] The appellant (which was the plaintiff at the Court below) at all material times was a developer of a mixed development project in Sabah and was undertaking a project known as the "1 Borneo Hypermall" in Kota Kinabalu.

[3] The respondent (which was the defendant at the Court below) was a company involved in a business of provision of customised system, services and solutions for heating, ventilation and air conditioning. The respondent used green building technology and can custom design building system that operate with maximum energy efficiency.

[4] By a letter of award dated 24 April 2006, the appellant commissioned the respondent to install air-conditioning and mechanical ventilation system and services in the 1 Borneo Hypermall complex. Works have been carried out by the respondent and as at 28 April 2010, a sum of RM3,641,315.73 had been certified completed by the appellant.

[5] The appellant claimed that there were defects and outstanding works not completed by the respondent and the respondent's representations regarding the suitability and fitness for the intended use of the air-conditioning system were false. The appellant further claimed that after the complex was completed, possession of retail units was handed over to respective owners and tenants. However, the appellant received numerous complaints from the owners and tenants about the lack or insufficiency of air-conditioning inside the premises. Consequently the appellant claimed to have suffered loss and damage, ie estimated costs to rectify the air-conditioning system and loss of business reputation for a sum of RM50 million.

[6] On 5 May 2011 the appellant filed a suit against the respondent for damages to be assessed, special damages of RM50 million and liquidated damages at the rate of RM10,000.00 per day to be calculated from 29 November 2007 to the date of the writ with interest and costs.

[7] On 29 June 2011, the respondent filed its statement of defence and at the same time counterclaimed against the appellant for the sum of RM3,641,315.73 for works done, certified and unpaid.

[8] Thereafter, by a Summons-in-Chambers dated 13 September 2011, the respondent applied for summary judgment under O 14 of the RHC 1980 , to be entered against the appellant in respect of the said sum of RM3,641,315.73 in its counterclaim against the appellant.

[9] On 16 December 2011, the High Court granted the respondent's aforesaid application and entered judgment against the appellant for the said sum together with interest at the rate of 4% per annum from 29 April 2010 till the date of judgment and costs of RM80,000.00, which sum is subject to review by the Court upon application by either party.

[10] Subsequently, on 31 January 2012, upon an application of the appellant pursuant to O 14 r 3(2) of the RHC 1980 , the High Court granted a stay of execution of the summary judgment until the trial of the appellant's claims against the respondent in the main suit or until further order. The respondent did not appeal against the stay order. The appellant's main suit has been set down for trial on 4-5 July 2013.

[11] In allowing the said summary judgment in favour of the respondent, the learned High Court Judge found

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top