2012 MarsdenLR 1514

HUE SIEW KHENG
NR ENGINEERING & PRECISION SDN BHD – Appellant
Versus
PASHACORP SDN BHD – Respondent



Important Points

The court granted summary judgment, determining the defendant had no legitimate counterclaims regarding breach, coercion, or the plaintiff's capability after finding no formal contract was signed.

Subject

Contract Law - Summary Judgment

Act Referred

civil law: S.218

Headnote

(A) Contract Law - Summary judgment sought under the Letter of Award dated 3.12.2005 for a project with disputes over earnest money and breach allegations - Plaintiff paid RM 2 million against RM 5 million required, and claimed refund for project cancellation. (Paras 1-12)

(B) Allegations of threats and coercion by the plaintiff were found to lack merit, as refund actions predated any alleged threats. (Paras 6-9)

(C) Defenses regarding contractual breaches and the plaintiff's capacity were dismissed as baseless; the plaintiff's obligations arose only upon signing a formal agreement. (Paras 10-12)

Facts of the case:
The plaintiff sought RM 1.4 million as summary judgment asserting that the defendant did not demand unpaid earnest money and had indicated the project was called off. The defendant countered with allegations of breach and coercion.

Findings of Court:
The court found no legitimate defenses presented by the defendant and granted summary judgment in favor of the plaintiff.

Issues: The case revolved around whether the plaintiff breached the contract and if the defendant's allegations of coercion held any weight.

Ratio Decidendi: The court established that the timing of the refund and lack of demands undermined the defendant's position, affirming that without a formal contract, the obligations did not arise.

Result: Enclosure 7 was allowed with costs; plaintiff entitled to RM 1.4 million.
Table of Content
1. plaintiff seeks summary judgment based on letter of award. (Para 1 , 2)
2. dispute over earnest money payment and refund assertions. (Para 4 , 5 , 6)
3. court dismisses claims of threats and coercion as unsubstantiated. (Para 7 , 8 , 9)
4. defendant's claims of plaintiff's breach deemed baseless. (Para 10 , 11 , 12)
DECISION

(Enclosure 7)

1. By Enclosure 7 the plaintiff seeks to enter summary judgment against the defendant for the sum of RM 1.4 million and interest at 8% per annum from 11.5.2006 till payment.

2. The plaintiffs claim against the defendant is premised on a Letter of Award dated 3.12.2005 issued by the defendant to the plaintiff for a design and build turnkey contract in respect of a "Proposed Perlis Port Development Project". The plaintiff had paid RM 2 million as earnest money of which a sum of RM 600,000.00 had been repaid by the defendant.

The defendant raised the following issues:-

i) The plaintiff had failed to pay the balance sum of RM 3 million of the RM 5 million required to be paid as earnest money as provided for in clause 5 of the Letter of Award.

ii) The sum of RM 600,000.00 returned to the plaintiff was a result of threats and coercion by the plaintiff.

iii) The plaintiff had also breached other terms of the agreement in that no preparatory action was taken to draw up a formal contract within 3 months from the Letter of Award and that the plaintiff was not competent to carry out and complete the project and was not even a registered engineering company.

Failure to pay the balance earnest money.

3. Clause 5 of the Letter of Award is as follows:-

Earnest Money: On the issuance and acceptance of this Letter of Award, the Contractor shall pay the Employer an Earnest Money of RM 5.0 Million (Ringgit Malaysia: Five Million only).

The Earnest Money will be refunded 91 days from the date of acceptance of this Letter of Award, and upon successfully signing the Contract Agreement. This Letter of Award is considered null and void if the Earnest Money is not deposited with the Employer.

4. It is not disputed that the plaintiff only paid RM 2 million as earnest money. The plaintiff argues that even though clause 5 provided that the earnest money of RM 5 million was to be paid on 3.12.2005 ie, the date of issuance and acceptance of the Letter of Award, payment was effected only on 7.12.2005 and for a lesser sum of RM 2 million without any protest or objection from the defendant. Neither did the defendant at any time request or demand for the balance sum of RM 3 million.

5. On the contrary the plaintiff contends that there is clear and irrefutable evidence that the defendant had intended to refund the RM 2 million paid as earnest money as the project was called off. Accordingly, the defendant had issued a cheque for the sum of RM 2 million on 9.3.2006 to the plaintiff (see Exhibit NR-10 of Enclosure 10). The cheque was not banked in at the request of the defendant. The accompanying Payment Voucher stated the sum of RM 2 million to be "refund of Earnest Money for Design and Build Turnkey Contract on Proposed Perlis Port Development Project".

6. As such, the plaintiff contends that the defendants allegation of breach in respect of non payment of the balance sum of RM 3 million is baseless and without merit. I agree.

Alleged threats and coercion

7. The defendant has merely made bare averments of alleged threats and coercion to explain the refund of RM 600,000.00 made (the sum of RM 500,000.00 on 17.1.2006 and a subsequent sum of RM 100,000.00 on 9.5.2006) and the cheque issued for RM 2 million. Reference was also made to the s. 218 Notices issued, which the defendant claimed to be an abuse of the court process.

8. With respect, I do not see how it can be contended that the s. 218 Notices in any way induced the refund of the RM 600,000.00 nor the cheque being issued as the s. 218 Notices were only issued in 2008 and 2009 whereas the refund of RM 600,000.00 was in 2006, as was also the cheque. In fact t