SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2010 MarsdenLR 1766

COURT OF APPEAL PUTRAJAYA
TASJA SDN BHD – Appellant
Versus
GOLDEN APPROACH SDN BHD – Respondent
[Civil Appeal No: W-02-800-2007]



Petitioner Advocates:Gobind Singh Deo,Marisa Regina ,Respondent Advocate: Wong Kian Kheong,Karen Lee

Claims arising from construction contracts must adhere to the limitation period established in the Limitation Act, and any new arguments not pleaded in the original statement of claim cannot be considered.

Headnote:(A) Limitation Act 1953 - Section 6(1)(a) - Rules of the High Court 1980 - Order 18 Rule 19 - Claim for outstanding payments after termination of construction contract - Court dismissed the appeal, ruling the claim was time-barred as it was filed beyond the limitation period from the issuance of interim valuation certificates, upholding the lower court's decision. (Paras 11, 14, 19, 24)

(B) Contract Law - Construction Contracts - The final account concerning payments must adhere to the terms of the signed construction contract, and raising new claims not pleaded in the statement of claim is impermissible. (Paras 18, 22)

Facts of the case:
The plaintiff, having been awarded a construction project by the defendant, alleged that the defendant failed to pay due amounts under interim valuation certificates and the contract's termination agreement. The plaintiff's claims for RM3,212,688.76 were filed after the limitation period expired.

Findings of Court:
The court found the claim time-barred under the Limitation Act and upheld the striking out of the plaintiff's statement of claim.

Issues: The primary issue was whether the plaintiff's claims were time-barred under the Limitation Act, specifically considering the termination agreement and timing of the filed claims.

Ratio Decidendi: The court ruled that the claim was based on the construction contract, not the termination agreement, emphasizing adherence to claims made in the statement and the relevance of the limitation period.

Result: Appeal dismissed.

Table of Content
1. contractual background and agreed terms (Para 2 , 3 , 4 , 5 , 6 , 8 , 9 , 10)
2. arguments on limitation and claims (Para 11 , 12 , 15 , 16 , 17)
3. court's final ruling on strike-out application (Para 13 , 14 , 19 , 20)
4. observations on the applicability of limitation law (Para 18 , 21 , 22 , 23)
Hasan Lah JCA:

[1] On 13 August 2009 we dismissed this appeal with costs. We now give the grounds for our decision.

[2] In this judgment the parties are referred to as "the plaintiff" and "the defendant" just as they were described in the writ of summons dated 22 June 2005.

[3] By a letter of acceptance dated 12 November 1996 the defendant awarded the construction works for a project known as "Proposed Construction And Completion Of Stage 2A Civil Infrastructural Works Including Earthworks, Roads, Drainage And Ancillary Works For Proposed Diamond Creeks Country Retreat On Lot 9887 & 9888, Mukim Of Ulu Bernam, Daerah Tanjong Malim, Perak (hereinafter referred to as "the project") at a price of RM14,925,754.15 with a completion period of 52 weeks to the plaintiff. It was provided in that letter of acceptance that pending the signing of a formal contract agreement, the letter of acceptance would constitute a legal and binding contract. It was also stated in the letter of acceptance that the plaintiff would take possession of the site on 18 November 1996 and the date for the completion of the whole works would be 18 November 1997.

[4] The defendant also had appointed Weathered & Howe (Malaysia) Sdn Bhd as its engineer ("the engineer") for the purposes of the contract who was responsible for the overall supervision and direction of the works for the project.

[5] On 6 February 1998 the plaintiff and the defendant signed the contract agreement ("the construction contract"). Clause 47 of the construction contract provided that upon the submission of claims by the contractor (the plaintiff) the engineer would make a fair valuation of the works properly executed by the contractor and within 14 days from the date of any such valuation the engineer would issue an interim valuation certificate stating the amount due to the contractor from the employer (the defendant). It was further provided that within 30 days of the issue of any such interim valuation certificate as aforesaid the employer would make a payment to the contractor of the amount certified as due to the contractor in the said certificate.

[6] The engineer issued five interim valuation certificates in relation to the works executed by the plaintiff and they are as follows:

(a) 20 March 1997 - Interim Valuation Certificate No. 1 for RM464,000;

(b) 29 April 1997 - Interim Valuation Certificate No. 2 for RM262,300;

(c) 10 September 1997 - Interim Valuation Certificate No. 3 for RM1,689,800;

(d) 6 November 1997 - Interim Valuation Certificate No. 4 for RM1,493,600;

(e) 12 February 1998 - Interim Valuation Certificate No. 5 for RM882,200

[7] In para. 7 of its statement of claim the plaintiff alleged that the defendant had not paid an amount of RM1,316,783.76 from the amount certified by the engineer in the interim valuation certificates and the claim is as follows:

[8] On 20 May 1998 the plaintiff and the defendant entered into an agreement for mutual termination of the construction contract ("the termination agreement"). Clause 2 of the termination agreement provided that all satisfactorily completed work would be inspected and valued by final measurement on site. Clause 3 provided that final account would be finalised and established within one month from completion of final site measurement and submission of full particulars/documents supporting the claims made. Clause 5 provided that mode of payment for all outstanding payments and monies due and owing to the plaintiff derived from the final account would be by monthly instalments of RM100,000 and would commence from 1 February 1998. Clause 18 provided that the plaintiff would contra bungalow lots in Phase 1, Diamond Creek Country

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top