SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1991 MarsdenLR 57

HIGH COURT MALAYA KUALA LUMPUR
ROYDEN (M) SDN BHD – Appellant
Versus
SYKT PEMBENAAN YEOH TIONG LAY SDN BHD – Respondent
[Suit No: S7-23-193-87]



Petitioner Advocates:Azhar Azizan ,Respondent Advocate: F Dorairaj

JUDGMENT

Lim Beng Choon J:

[1] The defendant was employed by Cosmopleks Sdn Bhd (the employer) as the main contractor for the construction of a project known as Raintree terrace 12 units luxury condominium apartments at Jalan Wickham, Kuala Lumpur (the project). By a sub-contract agreement dated 6 August 1984 (the 1st sub-contract) entered between the plaintiff and the defendant, the latter appointed the former as a sub-contractor to supply and instal air-conditioning and ventilation systems for the project. By another sub-contract agreement dated the same date (the 2nd sub-contract) entered into by the same parties the plaintiff was again appointed as a sub-contractor to supply and instal lift services for the project. The plaintiff alleged that the defendant had failed or refused to pay the plaintiff certain progressive payments notwithstanding that such payments were duly certified by the authorised architect of the project. Hence the plaintiff instituted this civil suit on 11 February 1987 against the defendant.

[2] In its writ endorsed with a statement of claim the plaintiff gave particulars of the progressive payments which had been duly certified by the architect which can be summarised as follows:

(a) 1st sub-contract:

architect's certificates of payment Nos 14, 18 & 20 totalling RM332,013.60.

(b) 2nd sub-contract:

architect's certificates of payment Nos 9, 10, 11, 13 & 20 totalling RM56,250.

[3] The plaintiff therefore claimed for an amount of RM388,263.60 with interest at the rate of 8% per annum from the date of judgment until the date of full settlement thereof and costs.

[4] After the defendant had entered appearance on 3 March 1987, the plaintiff made an application by way of summons-in-chambers dated 18 March 1987 for leave to enter final judgment for the aforesaid amount pursuant to O 14 of the Rules of the High 1980 (RHC). In the supporting affidavit affirmed by Kan Tong Seng (Kan) the accountant of the plaintiff it was asserted that the defendant was at the commencement of this action and still is justly and truly indebted to the plaintiff in the sum of RM388,263.60 in respect of work done and services rendered and performed by the plaintiff pursuant to the two sub-contract agreements dated 6 August 1984. The plaintiff then went on to state the manner in which the plaintiff was appointed as sub-contractor and gave the particulars of the outstanding certified amount of RM3 88,263.60 due and payable to the plaintiff by the defendant. The particulars given were the same as averred in the plaintiff's statement of claim.

[5] In response to the plaintiff's application for an O 14 judgment, the defendant applied by way of summons-in-chambers on 10 July 1987 for an order that all further proceedings in the civil suit be stayed pursuant to s 6 of the Arbitration Act 1952 as the plaintiff and the defendant by the sub-contracts agreed that matters in respect of which this action was brought be referred to arbitration. In the supporting affidavit affirmed by Gan Ching Lim (Gan) affirmed on 20 May 1987 (which must be read with the corrective and further affidavit of Gan affirmed on 6 August 1987 as in this affidavit Gan made some corrections to his earlier affidavit) it was asserted that cl 22 of the two sub-contracts provided:

That in the event of any dispute or difference between the contractor and sub-contractor whether arising during the execution or after the completion or abandonment of the sub-contract works or after the determination of the employment of the sub-contractor under this subcontract (whether by breach or in any other manner) in regard to any matter or thing of whatsoever nature arising out of this sub-contract or in connection therewith then either party shall give to the other notice in writing of such dispute or difference and such dispute or difference shall be and is hereby referred to arbitration...

[6] The defendant then went on to say that the matter in dispute was the precise amount of damages outstandin

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top