SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2008 MarsdenLR 5156

COURT OF APPEAL PUTRAJAYA
WAN MUHAMAD IBRISAM WAN IBRAHIM & ORS – Appellant
Versus
OPAL PYRAMID SDN BHD – Respondent
[Civil Appeal No: W-03-107-07]



Petitioner Advocates:Adam Abdullah,S Maniarasan ,Respondent Advocate: JT Sambathan

JUDGMENT

Suriyadi Halim Omar JCA:

[1] The appeal before us was allowed with costs whereupon the High Court's decision was set aside. Pursuant to this order the senior assistant registrar's order allowing the first to the fourth defendants' (hereinafter merely referred to as the appellants) application for security for costs was reinstated. The only difference was that the sum of RM75,000 was varied to RM40,000.

[2] We now touch on the background of this appeal. The plaintiff (hereinafter referred to as the respondent) had sued Wan Muhamad Ibrisam bin Wan Ibrahim, Tuan Haji Mohd Salleh bin Zakaria, Said @ Shuaib bin Bakar, Salwan Corporation Berhad and Sateras Resources (Malaysia) Berhad (respectively the first until fifth defendants) for a breach of contract. On 24 August 2005, the four appellants with the exception of the fifth defendant (hereinafter referred to as Sateras), pending the main suit, filed a summons-in-chambers seeking security for cost for the sum of RM75,000 against the respondent. As said above, before the senior assistant registrar, the appellants succeeded and the full sum of RM75,000 sought for was granted as security for costs. Dissatisfied with that order, the respondent appealed to the judge-in-chambers and on 6 June 2007 successfully overturned the earlier order. It was then the turn of the appellants to appeal to the Court of Appeal hence our involvement.

[3] To appreciate the matter more comprehensively, a need arises for us to lay down the antecedents as well as the factual matrix of this case. Sateras was undergoing a restructuring scheme under s. 176 of the Companies Act 1965 . In a word it was classified as a PN4 company by Bursa Malaysia. Prior to this suit the fourth appellant had entered into a Definitive Agreement dated 9 May 2003, wherein on completion of the restructure of Sateras, it was supposed to be taken over by the fourth appellant. In anticipation of the take over exercise between the fourth appellant and Sateras, the respondent was established on 15 April 2003. As provided for in the agreement, Sateras would become the wholly owned company of the fourth appellant, thereafter followed up by a disposal of Sateras to the respondent for RM1. The respondent, which was a dormant company with a paid-up capital of RM2, thus was merely created as a Special Purpose Vehicle ("SPV") to facilitate the takeover exercise. From these facts so far adduced, without prejudging the matter conclusively, in the event the scheme of restructure were to fail the Definitive Agreement would be functionless and the respondent redundant. The learned judge had not missed this point regarding the function factor and the respondent's poverty when he said:

It is clear that all the defendants knew right from the start that the plaintiff was a company which was set up for a purpose of taking over the business of the 5th defendant in the event that the Section 176 scheme of arrangement was successful. A company of this nature is not expected to carry a large asset _ its principal objective being merely to take over the 5th defendant business.

1

[4] The following facts were not denied in that the restructure scheme failed when the Sateras' petition to have the scheme approved was dismissed by the High Court on 31 January 2005. The appeal to the Court of Appeal was also struck out on 15 June 2005. Leave was also applied for in order to appeal to the Federal Court but was unanimously dismissed on 26 September 2005. As a consequence of this failure to obtain the sanction by 31 March 2005, the appellants terminated the Definitive Agreement on 1 April 2005.

[5] This termination of the Definitive Agreement did not go down too well with Sateras, and it filed a suit ie, D6-22-465-2005 and ex parte interlocutory injunctions against the appellants, purposefully to restrain the termination of the Definitive Agreement. On 1 August 2005 the ex parte injunctions were dissolved and the inter partes applications were dismissed with costs. On

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top