2015 MarsdenLR 236
COURT OF APPEAL PUTRAJAYA
FAR EAST HOLDINGS BHD & ANOR – Appellant
Versus
MAJLIS UGAMA ISLAM DAN ADAT RESAM MELAYU PAHANG – Respondent
[Civil Appeal Nos: W-02(NCC)(A)-2672-12/2013 & W-02(NCC)(A)-2781-12/2013]
Important Points
Subject
Arbitration - Contractual Dispute
Act Referred
Headnote
| Table of Content |
|---|
| 1. introduction of parties involved in the appeals. (Para 1 , 2 , 3) |
| 2. overview of the appeals filed regarding arbitration awards. (Para 6 , 7 , 8) |
| 3. provision of essential background facts regarding stakeholders. (Para 10 , 14) |
| 4. summary of court findings on arbitrator's decisions. (Para 20 , 26) |
Introduction
[1] There are three related appeals involving three parties heard before us. It is appropriate that we begin by first setting out the particulars of the parties and the appeals.
The Parties
[2] Far East Holdings Bhd is a company wholly owned by the State Government of Pahang ("the State Government"). Kampong Aur Oil Palm (Co) Sdn Bhd is a wholly owned subsidiary of Far East Holdings Bhd.
[3] Majlis Ugama Islam Dan Adat Resam Melayu Pahang is a body corporate established under s 4 of the Administration of Islamic Law Enactment 1991 ("the Enactment").
[4] For ease of reference, we will refer to Far East Holdings Bhd as "FEH", Kampong Aur Oil Palm (Co) Sdn Bhd as "KAOP" and Majlis Ugama Islam Dan Adat Resam Melayu Pahang as "MUIP".
The Appeals
[5] FEH and KAOP are the appellants in Civil Appeal No W-02(NCC)(A)-2671-12/2013 and Civil Appeal No W-02(NCC)(A)-2672-12/2013. MUIP is the respondent in both the appeals. Conversely, in Civil Appeal No W-02(NCC)(A)-2781-12/2013 MUIP is the appellant and both FEH and KAOP are the respondents.
Civil Appeal No W-02(NCC)(A)-2671-12/2013
[6] Civil Appeal No W-02(NCC)(A)-2671-12/2013 (hereinafter referred to as "Appeal 2671") is an appeal by FEH and KAOP against the decision of the High Court allowing the application made by MUIP vide Originating Summons No 24NCC(ARB)-54-11/2012 ("OS54") under s 38 of the Arbitration Act 2005 ("the Act") to register a Final Award made in arbitration proceedings in which MUIP was the claimant and FEH and KAOP were the respondents.
Civil Appeal No W-02(NCC)(A)-2672-12/2013
[7] Civil Appeal No W-02(NCC)(A)-2672-12/2013 (hereinafter referred to as "Appeal 2672") is the appeal by FEH and KAOP against the decision of the High Court to dismiss their application made vide Originating Summons No 24NCC(ARB)-46-11/2012 ("OS46") pursuant to s 42(1) and (2) of the Act to determine questions of law arising out of the Final Award, and alternatively to set aside the Final Award pursuant to s 37(1)(a)(iv), (v) and (b)(ii) and s 37(2)(b) and ss 30(1) and (5) of the Act.
Civil Appeal No W-02(NCC)(A)-2781-12/2013
[8] Civil Appeal No W-02(NCC)(A)-2781-12/2013 (hereinafter referred to as "Appeal 2781") is the appeal by MUIP against the decision of the High Court to set aside the pre and post award interests awarded by the arbitrator to MUIP.
[9] At the commencement of the appeals, it was agreed that submissions will commence in respect of Appeal 2672, which is the main appeal, and the submissions made in respect of the main appeal will apply equally to the other two appeals.
Background Facts
[10] Before we delve into the appeals, we set out below the salient background facts:
(a) MUIP needed funds to carry out its functions and objectives under the Enactment. At the material time, the source of funds for MUIP was zakat collections and Baitulmal;
(b) MUIP then decided that it had to have sufficient and independent source of funds and not be dependent on the State Government for financial support;
(c) MUIP had requested the State Government to alienate a piece of land for the cultivation of commercial crops to generate revenue for MUIP;
(d) the State Government had approved the alienation of 11,073 acres of land ("the alienated land") to MUIP;
(e) however, MUIP did not have the experience or expertise to cultivate oil palm and needed to engage a third party with the financial capability and experience to develop the alienated land as oil palm estates ("the Project");
(f) MUIP then entered into a discussion with FEH which has expertise in oil palm cultivation;
(g) KAOP, the wholly owned subsidiary of FEH owns 5,000 acres of cultivated oil palm land which was already being