PERBADANAN PEMBANGUNAN PULAU PINANG – Appellant
Versus
TRIKKON CONSTRUCTION SDN BHD – Respondent


Table of Content
1. interim award on preliminary issues discussed. (Para 1)

[1] The appellant and respondent are parties to an ongoing arbitration in Penang. The parties by agreement required the arbitrator to make an interim award on several preliminary issues which the parties wanted determined prior to the hearing of the arbitration proper. The learned arbitrator made the interim award dated 31st December 2009 (see p 562 of Bahagian Jilid 7).

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top