FEDERAL COURT PUTRAJAYA
JOHOR COASTAL DEVELOPMENT SDN BHD – Appellant
Versus
CONSTRAJAYA SDN BHD – Respondent
Based on the provided legal document, here are the key points regarding the case of Johor Coastal Development Sdn Bhd v. Constrajaya Sdn Bhd:
Case Information and Parties - The case was heard by the Federal Court Putrajaya between the Appellant, Johor Coastal Development Sdn Bhd, and the Respondent, Constrajaya Sdn Bhd (!) . - The case was decided on 12-06-2009 under Civil Appeal No: 02-02-2007(J) (!) . - The Appellant appealed against the decision of the Court of Appeal, which had allowed part of the appeal (!) .
Background Facts - The parties entered into two sale and purchase agreements dated 13 March 1997 for Lots 7 and 14 of the Johor Bahru Waterfront City (!) . - The total purchase prices were RM4,590,000 and RM10,830,000 respectively, to be paid in six instalments (!) . - The Respondent paid the first three instalments totaling RM9,018,400, which included an initial payment of 12% (RM1,850,400) (!) . - The Respondent failed to pay the balance of the price, leading the Appellant to terminate the agreements and seek forfeiture of the sums paid (!) .
High Court and Court of Appeal Decisions - The High Court ordered the Appellant to refund all monies received, holding that the initial 12% was not a deposit but an instalment, and the Appellant failed to prove actual damage under s 75 of the Contracts Act 1950 (!) . - The Court of Appeal allowed the appeal in part, holding that the Appellant was entitled to forfeit the 12% as a "true deposit," but must refund the balance as no proof of damage was provided under s 75 (!) . - The Court of Appeal reasoned that the 12% functioned as a true deposit to secure future performance and was not a penalty, whereas the balance required proof of loss under s 75 (!) (!) .
Questions of Law Before the Federal Court - The Appellant raised two questions of law regarding the decision in Selva Kumar a/l Murugiah v. Thiagarajah a/l Retnasamy (!) . - Question (a) asked if the Selva Kumar principle obliging a party to prove losses despite s 75's wording is correct (!) . - Question (b) asked if parties can contract out of the provisions of s 75 of the Contracts Act 1950 (!) . - The Appellant argued that clause 16.2 of the agreements unconditionally and irrevocably acknowledged that stipulated sums constituted reasonable compensation, effectively contracting out of s 75 (!) .
Federal Court Findings on s 75 and Selva Kumar - The Federal Court held that Selva Kumar is still good law, establishing that in every case where a sum is named for breach, it is treated as a penalty, and the Court must determine reasonable compensation (!) (!) . - Despite the wording in s 75 ("whether or not actual damage or loss is proved"), the Court must still prove actual damages or reasonable compensation according to Hadley v. Baxendale principles (!) (!) . - The Court rejected the argument that Selva Kumar was incorrect based on the Indian case Oil & Natural Gas Corp Ltd v. Saw Pipes Ltd, noting that the latter dealt with loss incapable of assessment, whereas the present case could be assessed (!) (!) . - The Court answered Question (a) in the affirmative, meaning the requirement to prove loss remains (!) .
Interpretation of Contract Clauses - The Court examined Clause 8.2(b), which stated that all instalments paid, including the first payment, shall be forfeited absolutely upon termination, except for a specific 4-month period where only 10% is forfeited (!) . - The Court examined Clause 16.2, where parties acknowledged that stipulated sums would constitute reasonable compensation and waived objections regarding fairness (!) . - The Federal Court agreed with the Court of Appeal that Clause 16.2 does not exclude the application of s 75; rather, it was intended to prevent challenges to the forfeiture of the 12% deposit given the nature of the transaction (!) . - In case of ambiguity between Clause 8.2 and Clause 16.2, the Court applied the rule of contra proferentum, resolving the ambiguity against the Appellant (who relied on Clause 16.2) (!) .
Final Determination - The Federal Court held that the 12% paid was a "true deposit" and could be forfeited without proof of actual damage (!) (!) . - However, the Appellant could not retain the balance of the payments (the remaining instalments) without proving actual damage suffered under s 75 (!) . - Since the Appellant failed to adduce evidence of loss or damage, the Court could not determine reasonable compensation for the balance, and thus the balance must be refunded (!) (!) . - The appeal was dismissed with costs, upholding the Court of Appeal's decision that the 12% is forfeitable but the balance must be returned (!) .
Introduction
[1] The appellant in this case appealed against the decision of the Court of Appeal in allowing part of the appeal. It was held by the Court of Appeal that the appellant was entitled to forfeit 12% of the purchase price as a 'true deposit' paid under the agreements. However the balance of the monies must be refunded to the respondent as the appellant had failed to strictly prove damage under s 75 of the Contracts Act 1950 ('the Act').
[2] The appellant was granted leave to appeal on 9 January 2009 on the following two questions of law:
(a) Whether that part of the decision in Selva Kumar a/l Murugiah v. Thiagarajah a/l Retnasamy, [1995] 1 MLJ 817 which obliges a party having the benefit of a liquidated damages clause to prove its losses, notwithstanding the words in s 75 of the Contracts Act 1950 'whether or not actual damage or loss is proved to have been caused thereby', is correct; and
(b) Whether or not parties entering into a contract are entitled to contract out of the provisions of s 75 of the Contracts Act 1950.
Background Facts
[3] The appellant and the respondent entered into two sale and purchase agreements ('the agreements') both dated
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.