SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 MarsdenLR 2317

HIGH COURT MALAYA IPOH
GUAN HENG CONSTRUCTION WORKS – Appellant
Versus
IMM WHITE BUTTON MUSHROOM (M) SDN BHD & ANOTHER CASE – Respondent
[Suits No: 22-302-2009 & 22NCVC-117-2011]



Petitioner Advocates:Joseph Ting,Tan Chun Ming ,Respondent Advocate: Terence Naidu,Syafiqah Khazariman

A contract signed for a larger amount, intended to deceive a financier, is deemed a sham; the lower contract governs both parties' obligations.

Headnote:(A) Contracts - General principles relating to validity and agreements - Evidence Act, 1950 - Contracts signed for construction work for different amounts, one sham only to satisfy financier - Parties' conduct suggests they intended to be bound only by the smaller contract. (Paras 12, 56, 68)

(B) Liability for damages - Contractor's obligation under contract to ensure proper workmanship and rectify defects - Parties found liable for the costs of rectification of defects. (Paras 44, 80)

(C) Estoppel - Party cannot assert claims contrary to confirmed payments to third party, reinforcing principle of good faith in commercial dealings. (Para 60)

(D) Counterclaim - Court allowed set-off for damages resulting from defective works, affirming contractor's liability. (Paras 68, 80)

Facts of the case:
The plaintiff, a local subcontractor, entered into a construction contract for a factory with the defendant based on two contracts: one for RM7,910,936.50 and a stamped contract for RM15,821,873.00. The project was mutually terminated at 92% completion due to issues with the factory floor sinking. The plaintiff sought payments according to the larger contract, while the defendant counterclaimed for damages for faulty works.

Findings of Court:
The court found the contract for the larger sum to be a sham contract for loan approval. The plaintiff was liable for the costs to rectify defects in the factory, resulting in a forfeiture of the defendant's retention sum.

Issues: The central issues were the validity of the larger contract and the liability of the plaintiff for rectification costs.

Ratio Decidendi: The court determined that the true agreement was for the lesser amount, viewing the larger sum as a facade meant to mislead the lender, reinforcing that good faith is crucial in contractual dealings.

Result: Judgment entered for the plaintiff for RM319,132.50; defendant's claim for retention sum allowed.

Table of Content
1. contractual terms and payment disputes. (Para 1 , 2 , 3)
2. claims and counterclaims for unpaid sums. (Para 10 , 11)
3. validity of contracts and their terms. (Para 12 , 14 , 15)
4. estoppel and sham contracts. (Para 56 , 57 , 68)
5. conclusion on claims and counterclaims. (Para 83 , 84)
Lee Swee Seng JC:

[1] The defendant wanted to build a factory for its new business. It was that of processing white button mushroom. It was also to serve as a fertiliser factory. It had a piece of land big enough for such an enterprise. The dimension of the factory was about 90 feet by 220 feet. It decided to award the contract for its construction to the plaintiff being a local subcontractor with some experience. It engaged Koh Perunding as its superintending officer and its civil and structural consultant upon the recommendation of the plaintiff. Malaysian Industrial Development Finance Berhad (MIDF) was the financier of part of the construction costs.

[2] There was a contract signed with a summary of the tender price or perhaps two contracts signed, according to the defendant. At any rate there were produced in court two contracts dated the same date, one for RM7,910,936.50 and the other for RM15,821,873.00 which of course is double the amount. The plaintiff started construction and the project was mutually terminated with completion at 92%. The floor sank and after rectification, it sank again! What was worse was that it sank unevenly. Tension was in the air!

[3] The plaintiff was not paid for what it claimed was the balance due under the consultant's certification. The defendant said what was due was just half of the amount certified as parties knew all along that the bigger contract was just to satisfy MIDF so that it could give a bigger loan. The actual contract which the defendant said is the one binding is for half the amount and that the parties had in their dealings with each other conducted themselves consistent with that knowledge and understanding.

[4] The plaintiff contended that it was the bigger contract that was stamped and so binding on the parties. The plaintiff sued based on the bigger sum contract and later proceeded to sue for a return of the bigger sum retention amount. The defendant cried foul! It depended on an oral agreement of a 50% discount! Alternatively it was the understanding of the parties that the true contract between them was the first contract for half the amount. The problem was further compounded by the factory floor that sank a second time after rectification. So the defendant put in a set-off and counterclaim for over RM900,000.00 to the plaintiff's first suit being the amount to rectify the sunken floor.

[5] The refrain must have reverberated through them as they ruminate on how to resist each other's claims:

"O what a tangled web we weave when we devise to deceive."

Personalities And Preliminaries

[6] The plaintiff called three witnesses:

1. PW1, Koh Liong Boon, the Proprietor of Koh Perunding who was the Consultant and Superintending Officer under the contract,

2. PW2, Tan Chong Kang, a partner of the plaintiff.

3. PW3, Tan Chong Meng, a partner of the plaintiff and PW1's brother.

[7] The defendant called DW1, Chin Ivan Oi Fook, the Managing Director of the defendant.

[8] The following documents were marked for each of reference:

Bundle Of Pleadings A

Common Bundle of Documents 1 B1

Common Bundle of Documents 2 B2

Common Bundle of Documents Supplemental C

[9] By consent parties agreed that all documents in Part A and Part B are automatically accepted as exhibits and evidence subject only to weight to be attached. They shall be referred to by page numbering and Bundle Alphabet. All documents in Part C are to be marked in accordance with the admission of documents under the Evidence Act 1950 .

Prayer

[10] There are two suits that were consolidated and heard together in this trial. One is Suit 22-302-2009 being the plaintiff's claim for the balance amount due under the Certification albeit based on the bigge

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top