2011 MarsdenLR 4629 ; 2011 MarsdenLR 1

LAU BEE LAN
PATI SDN BHD – Appellant
Versus
HASRAT USAHA SDN BHD – Respondent



A sub-contractor can enforce completion claims against a main contractor despite claims of a back-to-back payment model; the burden of proof lies on the party alleging the arrangement when evidence contradicts it.

Headnote:(A) Sub-contract Law - Construction Contracts - Clauses governing payments and performance - The Plaintiff was permitted to claim RM729,780.36 as outstanding due after providing evidence of works completed under a project. The Defendant was entitled to a counterclaim of RM1,820,000 for liquidated damages due to delays in project completion. (Paras 2, 9, 10, 12, 14)

(B) Burden of Proof - Balance of probabilities - The Plaintiff must establish its claim on a balance of probabilities; the court should assume the evidence presented is correct when the opposing party fails to present any. (Paras 5, 10.2)

(C) Back-to-back payment agreements - A contractual arrangement must explicitly state conditions on payment to be enforceable; failure to do so means the Defendant must honor payments to the Plaintiff notwithstanding claims of prior settlements. (Paras 14, 15, 22)

PATI SDN BHD vs HASRAT USAHA SDN BHD - 2011 MarsdenLR 4629 ; 2011 MarsdenLR 1
Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top