2005 MarsdenLR 1428

INDUSTRIAL COURT (KUALA LUMPUR)

AHMADI HAJI ASNAWI


LEE SENG CHONG
versus
TECKNODS SDN BHD

AWARD NO: 1969 OF 2005 (CASE NO: 19/4 - 267/05

Decided On : 10-13-05

Advocates:
Counsel for Claimant - In person
Counsel for the Company - R Harikannan,; T/n Rao Kamal (Kamaljit Kaur with him)

AWARD

BEFORE THE commencement of the hearing of this reference this morning (13th October 2005), both the learned counsel appearing for the Company and the Claimant who appeared in person informed the court that the parties have mutually resolved their dispute by consent on the following terms -

(i) That the Company shall, without any admission of liability, pay to the Claimant the sum of RM3,700.00 only as full and final settlement of the Claimant's claim in this reference.

(ii) That the said settlement sum shall be paid to the Claimant and that the said sum shall be made out under his own name, on or before the 27th day of October 2005.

(iii) That the said settlement sum shall constitute the full and final settlement of the Claimant's claim in this reference and with the payment of the said sum, the Claimant shall have no further/other claims hereinafter against the Company arising out of his employment with the Company.

UPON CONFIRMATION of the said terms by both the parties herein, the court accordingly handed down an award upon the terms as agreed to by consent indicated above.