SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 1673

COURT OF APPEAL KOTA KINABALU
POTECK ENTERPRISE SDN BHD – Appellant
Versus
RICHALLENGE CORPORATION SDN BHD – Respondent
[Civil Appeal No: S-02(IM)(NCvC)-151-01-2022]



Petitioner Advocates:Marina Tiu,Joan Goh Pean Nee ,Respondent Advocate: Ronnie Cham Ngit Shin,Chleo Teo

A plaintiff must prove both the fact and amount of damages to recover; failure to do so may result in only nominal damages being awarded.

Headnote:(A) Contract Law - Assessment of Damages - Wrongful Termination of Sub-Contract Agreement - The Appellant terminated the Sub-Contract Agreement leading to a claim for damages by the Respondent. The High Court initially ruled in favor of the Appellant, but this was reversed on appeal, necessitating a damages assessment. The High Court awarded RM8,999,897.27 in damages, which included interest and costs. (Paras 12, 47)

(B) Burden of Proof - It is established that a plaintiff must prove both the fact and amount of damages to recover, failing which only nominal damages may be awarded. (Paras 32, 43)

(C) Appellate Intervention - The appellate court may intervene when a trial judge's decision is plainly wrong, which includes misapprehension of evidence or failure to consider relevant evidence. (Paras 14, 72)

(D) Valuation of Work Done - The court found that reliance on interim payment certificates was appropriate in the absence of joint measurement of work done, but erred in not using the most current valuation. (Paras 24, 27) (E) Nominal Damages - The Respondent was awarded nominal damages due to failure to substantiate claims for loss of profit. (Paras 44, 46)

Facts of the case:
The Appellant, a private limited company, terminated a sub-contract with the Respondent for failure to complete construction, leading to claims for damages. The High Court awarded damages which were disputed by the Appellant. (Paras 8, 12)

Findings of Court:
The court upheld parts of the damages assessment while correcting others, leading to a final award of RM3,430,780.00 with interest and costs. (Paras 47)

Issues: The primary issues included the proof of work done, the validity of claims for variations, and the substantiation of loss of profit. (Paras 30, 40)

Ratio Decidendi: The court emphasized the necessity for strict proof of damages and clarified the standards for appellate intervention when a trial court's findings are plainly wrong. (Paras 14, 43)

Result: The appeal was allowed in part, modifying the damages awarded by the High Court.

Table of Content
1. overview of appeal on damages assessment. (Para 1 , 2 , 3 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
2. guidelines for appellate review of damages. (Para 14 , 15 , 16 , 17 , 18)
3. dispute over valuation reliability. (Para 19 , 20 , 21)
4. court's acceptance of interim payment certificate. (Para 22 , 23 , 24 , 25 , 26 , 27 , 28)
5. failure to prove variation work. (Para 29 , 30 , 31 , 32 , 33 , 34)
6. concessions on advance payment and performance bond. (Para 35 , 36 , 37 , 38)
7. insufficient proof for loss of profit claim. (Para 39 , 40 , 41 , 42 , 43 , 44 , 45)
8. final decision on appeal outcomes. (Para 47)
Lim Chong Fong JCA:

Introduction

[1] This is an appeal on the assessment of damages pursuant to a terminated construction contract.

[2] The Appellant, who is the defendant in the High Court, is a private limited company.

[3] The Respondent, also a private limited company, is the plaintiff in the High Court.

[4] We heard the appeal on 14 March 2025 and subsequently adjourned the decision to allow time for deliberation on the arguments presented by the parties.

[5] Now having done so, we hereby give our decision below together with our supporting grounds.

Background

[6] The Appellant was awarded the main contract by the Ministry of Education of the Federal Government of Malaysia ("Employer") to construct a school named Sekolah Menengah Kebangsaan Tandek 2, located in Kuala Marudu, Sabah, with a contract value of RM42,750,000.00 ("Main Contract Sum").

[7] The Appellant thereafter sub-contracted the carrying out of the whole of the building works to the Respondent via a written sub-contract agreement dated 28 July 2009 ("Sub-Contract Agreement"). The sub-contract sum of the Respondent is determined at RM35,228,250.00 ("Sub-Contract Sum"), to wit, 85% of RM41,445,000.00 being the Main Contract Sum less contribution and levy charges of RM1,305,000.00. Thus, the balance of RM6,216,750.00, being 15% of the Main Contract Sum less contribution and levy charges is the Appellant's entitlement.

[8] During the course of construction of the school, there were disputes that arose that resulted in the Appellant, on 11 November 2014, terminating the Sub- Contract Agreement for the Respondent's failure to complete the construction of the school.

[9] Consequently, the Respondent commenced the action in the High Court ("Suit") and claimed damages against the Appellant for wrongful termination of the Sub-Contract Agreement. The Appellant counter-claimed damages against the Respondent, especially the extra costs incurred to complete the building works by Bangkit Energy & Pro Logistic (EM) Sdn Bhd ("Completion Contractor").

In The High Court

[10] After the trial of the Suit, the High Court on 15 November 2021, found in favour of the Appellant.

[11] On appeal by the Respondent, this Court in Civil Appeal No S-02(NCVC) (W)-2545-12/2017, reversed the High Court's decision on 21 March 2019 (see Richallenge Corporation Sdn Bhd v. Poteck Enterprise Sdn Bhd 2020 MarsdenLR 817 ; [2020] 3 MLJ 704 ; ; [2020] 4 AMR 865 ). The High Court was then ordered to assess the damages suffered by the Respondent due to the Appellant's unlawful termination of the Sub-Contract Agreement.

[12] Consequently, upon assessment, the High Court on 14 December 2021 allowed damages under the following headings:

Thus, the High Court ordered the Appellant to pay the total amount of RM8,999,897.27, with interest at the rate of 8% per annum from 29 September 2014 to the date of judgment and thereafter statutory interest on the said sum at the rate of 5% per annum from the date of judgment to the date of full payment and costs of RM10,000.00 subject to allocator.

[13] The Appellant is dissatisfied with the assessment made by the High Court and, therefore, filed an appeal with the Court of Appeal on 11 January 2022.

Findings Of This Court

[14] Although this is an appeal arising from the assessment of damages, our function here is no different from that of an appeal on liability after trial in

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top