SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 5022

COURT OF APPEAL KOTA KINABALU
POTECK ENTERPRISE SDN BHD – Appellant
Versus
RICHALLENGE CORPORATION SDN BHD – Respondent
[Civil Appeal No: S-02(IM)(NCvC)-151-01/2022]



Petitioner Advocates:Marina Tiu,Joan Goh Pean Nee ,Respondent Advocate: Ronnie Cham Ngit Shin,Chleo Teo

The burden of proof lies on the claimant to substantiate claims for damages, with nominal damages awarded in the absence of sufficient evidence.

Headnote:(A) Construction Law - Assessment of Damages - The court reviewed the assessment of damages following the termination of a sub-contract for construction works, emphasizing the necessity for precise proof of damages and the reliance on expert testimony. (Paras 14, 17, 30, 40)

(B) Evidence - Burden of Proof - The court reiterated that the burden lies on the claimant to prove both the fact and amount of damages, with nominal damages awarded in absence of substantial proof. (Paras 32, 44)

(C) Appellate Review - The court clarified its role in reviewing the lower court's decision, applying the 'plainly wrong' test for findings of fact and emphasizing the need for judicial appreciation of evidence. (Paras 14, 15, 28)

Facts of the case:
The appellant terminated the sub-contract with the respondent for failure to complete construction; the respondent claimed damages for wrongful termination, leading to a complex assessment of damages by the High Court.

Findings of Court:
The court found that the damages awarded by the High Court were erroneous, substituting the amounts awarded for work done, variations, and loss of profit.

Issues: The main issues included the adequacy of proof for damages claimed, the appropriateness of evidence relied upon, and the correctness of the assessment process.

Ratio Decidendi: The court held that the respondent failed to provide sufficient proof for claims of loss and variations, justifying a reduction in awarded damages.

Result: Appeal allowed in part, with the total damages assessed at RM3,430,700.00.

JUDGMENT

Lim Chong Fong JCA:

Introduction

[1] This is an appeal on the assessment of damages pursuant to a terminated construction contract.

[2] The Appellant, who is the defendant in the High Court, is a private limited company.

[3] The Respondent, also a private limited company, is the plaintiff in the High Court.

[4] We heard the appeal on 14 March 2025 and subsequently adjourned the decision to allow time for deliberation on the arguments presented by the parties.

[5] Now having done so, we hereby give our decision below together with our supporting grounds.

Background

[6] The Appellant was awarded the main contract by the Ministry of Education of the Federal Government of Malaysia ("Employer") to construct a school named Sekolah Menengah Kebangsaan Tandek 2, located in Kuala Marudu, Sabah, with a contract value of RM42,750,000.00 ("Main Contract Sum").

[7] The Appellant thereafter sub-contracted the carrying of the whole of the building works to the Respondent via a written sub-contract agreement dated 28 July 2009 ("Sub-Contract Agreement"). The sub-contract sum of the Respondent is determined at RM35,228,250.00 ("Sub-Contract Sum"), to wit, 85% of RM41,445,000.00 being the Main Contract Sum less contribution and levy charges of RM1,305,000.00. Thus, the balance of RM6,216,750.00 being 15% of the Main Contract Sum less contribution and levy charges is the Appellant's entitlement.

[8] During the course of construction of the school, there were disputes that arose that resulted in the Appellant on 11 November 2014 terminating the Sub-Contract Agreement for the Respondent's failure to complete the construction of the school.

[9] Consequently, the Respondent commenced the action in the High Court ("Suit") and claimed damages against the Appellant for wrongful termination of the Sub-Contract Agreement. The Appellant counter-claimed damages against the Respondent especially the extra costs incurred to complete the building works by Bangkit Energy Pro Logistic (EM) Sdn Bhd ("Completion Contractor").

In The High Court

[10] After trial of the Suit, the High Court on 15 November 2021, found in favour of the Appellant.

[11] On appeal by the Respondent, this Court in Civil Appeal No S02(NCvC)(W)-2545-12/2017, reversed the High Court's decision on 21 March 2019 (see Richallenge Corporation Sdn Bhd v. Poteck Enterprise Sdn Bhd 2020 MarsdenLR 817 ; [2020] 3 MLJ 704; ; [2020] 4 AMR 865). The High Court was then ordered to assess the damages suffered by the Respondent due to the Appellant's unlawful termination of the Sub-Contract Agreement.

[12] Consequently, upon assessment, the High Court on 14 December 2021 allowed damages under the following headings:

Thus, the High Court ordered the Appellant to pay the total amount of RM8,999,897.27, with interest at the rate of 8% per annum from 29 September 2014 to the date of judgment and thereafter statutory interest on the said sum at the rate of 5% per annum from the date of judgment to the date of full payment and costs of RM10,000.00 subject to allocator.

[13] The Appellant is dissatisfied with the assessment made by the High Court and, therefore, filed an appeal with the Court of Appeal on 11 January 2022.

Findings Of This Court

[14] Although this is an appeal arising from the assessment of damages, our function here is no different from that of an appeal on liability after trial in the High Court.

[15] It is therefore a review of the High Court decision and we are guided by the case of Ng Hoo Kui & Anor v. Wendy Tan Lee Peng & Ors 2020 MarsdenLR 756 ; ; [2020] 10 CLJ 1 (FC) where Zaleha Yusof FCJ held as follows with emphasis added by us:

"[62] The Malaysian position has always been that, a decision that is arrived at, due to a lack of judicial appreciation of evidence is plainly wrong. The Federal case of Gan Yook Ching (P) & Anor v. Lee Ing Chin @ Lee Tuck Seng & Ors call considerations as to what constitutes as the 'plainly wrong' test.

[71] From the aforesaid authorities, there appears to be a differen

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top