2010 MarsdenLR 1603

HIGH COURT KOTA KINABALU
BESTEEL BERHAD – Appellant
Versus
PEMBANGUNAN LADANG HASSAN SDN BHD – Respondent
[Suit No. S22-02 Of 2003]



The court affirmed the right to terminate a contract based on substantial breaches by the employer, validating claims for retention sums in construction agreements.

Headnote:(A) Contract Act 1950 - Sections 40 and 56(1) - A declaration regarding lawful termination of a construction agreement - The plaintiff's unilateral termination was held valid due to the defendant's failure to fulfill contractual obligations, justifying the claims for retention sums. The court noted, 'the defendant's conducts amount to repudiatory breaches...go to the root of the contract.' (Paras 1, 2, 3, 4, 5, 6).

(B) Right to terminate - The court affirmed the contractor's right to terminate based on substantial breaches by the employer, ‘...the plaintiff's contention that the defendant did not perform its obligations...was justified.’ (Paras 1, 5).

Facts of the case:
The plaintiff was contracted to construct a palm oil mill for RM11,330,000 but claimed wrongful termination by the defendant and sought retention sums totaling RM1,073,017.80. The defendant counterclaimed, asserting the termination was invalid.

Findings of Court:
The court declared the prior contract termination lawful and awarded the plaintiff the retention sums plus interest, recognizing the defendant's failure to comply with contract terms.

Issues: Was the plaintiff justified in terminating the contract due to alleged breaches by the defendant?

Ratio Decidendi: The court found the defendant guilty of repudiatory breaches and ruled that the plaintiff's self-termination of the contract was valid as breaches affected core obligations.

Result: Judgment to the plaintiff for RM1,073,017.80 with interest; counterclaim dismissed.

Table of Content
1. overview of plaintiff's claims against the defendant. (Para 1 , 2 , 3 , 4 , 5)
JUDGMENT

Proceeding:

The plaintiff's claim against the defendant is in substance three folds which are:

1. A declaration that the Agreement dated 23.06.1998 between the plaintiff and the defendant (agreement) to construct for the defendant a palm oil mill for a total sum of RM11,330,000.00 had been lawfully terminated by the plaintiff,

2. For a sum of RM1,073,017.80 made up of:-

(a) RM961,509.30 [retention sum held by the defendant for the construction supply, fabrication, erection, installation of installation of a 45 tonnes palm oil mill]

(b) RM53,200.00 [retention sum held by the defendant for the supply of proprietary equipment]

(c) RM58,308.50 [amount for variation order for the piling works and load test for the boiler foundation.

3. The loss of profit on the value of the balance of the unfinished works.

The defendant denies the claim on the ground that the plaintiff had wrongly terminated the agreement and as a result had filed a counterclaim against the plaintiff.

In respect of the counterclaim, it had been agreed by counsel that the proof in respect of the quantum of damages suffered by the defendant will only be necessary if the court finds that the plaintiff's termination of the agreement to be wrongful.

Background facts:

The agreement which the plaintiff and the defendant entered into was to construct for the defendant and further to supply, fabricate, erect, install and commission a 45 tonnes FFB/HR palm oil mill (mill) including all ancillary works at Sg. Memanjang, Beluran (collectively referred to as the Works) for a total sum of RM11,330,000.00. This Mill is to be sited in the defendant's plantation known as Ladang Hassan.

Konsultant Proses Sdn Bhd (Konsultant Proses) on 2.9.1995 under a memorandum of agreement was appointed the engineer for the construction of the palm oil mill.

The plaintiff took possession of the site within fourteen (14) days from 19.05.1997 - 1 year before signing of the agreement dated 23.6.1998, and carried out the Works and submitted claims for payment progressively according to the stages of construction of the Works. Work on the site was put on hold as the defendant then had no technical person on site and work on the Mill restarted only in June 1998 when Liau Kim Tin (PW3), a professionally qualified engineer, was employed as the defendant's general manager who was tasked to be in charge of the mill project. On 13.12.1999 the plaintiff was informed by the defendant that the operation of the Mill should only start at the end of 2000 as there was a shortage of crop from its own estate.

For works executed by the plaintiff for the Mill and for proprietary equipments supplied, the plaintiff had submitted claims which were certified resulting payments made to the plaintiff leaving the following retention amounts of RM961,509.30 and RM53,200.00 respectively for the works executed for the mill and proprietary equipments supplied. These retention amounts are not disputed by the defendant except for the issue whether the plaintiff is entitled to them which will be dealt with later in my judgment.

The Issues:

Counsel at the end of the trial had agreed on the issues to be deliberated by me and they are these:

Issue No. 1:

Even if proven (which is denied), whether the purported grounds for the plaintiff's self-termination of the Contract vide their solicitors' letter dated 5.11.2002 are recognized under the Contract and if not, whether the said termination was wrongful.

The solicitor's letter sets out 5 grounds and they are these:

1. that the defendant had allegedly repeatedly and consistently failed to honour their contractual obligations by failing to extend to the plaintiff the design plan for the effluent treatment system;

2. that the defendant had allegedly failed to construct the water reservoir resulting in the plaintiff's inability to carry out piping works to and from the mill to the water reservoir;

3. that the d

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top