2025 MarsdenLR 2505

HIGH COURT MALAYA SHAH ALAM
CHU JIN HAU & ORS – Appellant
Versus
SIME DARBY BRUNSFIELD HOLDING SDN BHD & ORS – Respondent
[Civil Suit No: BA-22C-17-04-2022]



Important Points

Unit owners must act collectively in a representative action for claims impacting all owners, and time-bar considerations under applicable statutes apply to breach of statutory obligations.

Subject

Civil Law - Property and Contracts

Act Referred

Headnote

(A) Rules of Court 2012 - Order 14A and Order 18 r 19 - Summary disposal sought by both parties on multiple legal issues - The court addresses Plaintiffs' breach claims against Defendants regarding development project and management, focusing on locus standi and time-bar issues. (Paras 1-42)

(B) Locus Standi - On issues impacting collective interests of unit owners, a representative action is necessary for claims that affect all owners collectively. (Paras 36.1-36.5)

(C) Time-barred Claims - Claims arising from actions or non-actions should be assessed regarding limitations under relevant statutes, particularly on maintenance and statutory compliance claims. (Paras 37.1-37.4)

(D) Legal Obligations - Developer's responsibilities under Sale and Purchase Agreements regarding statutory compliance with building laws are confirmed through interpretations of related acts. (Paras 41.1-41.4) (E) Maintenance Charges - Discrepancies in charges due to failure to apply statutory provisions were emphasized, requiring recalibration of fees. (Paras 43.1-43.4)

Findings of Court:
Multiple applications were analyzed regarding the compliance of obligations, locus standi, and legal ramifications affecting plaintiffs and defendants alike. Clear guidelines established for future claims (Paras 45-51).

Issues: The court addressed several core issues including locus standi, time-barred claims, and breach of statutory obligations.

Ratio Decidendi: The court elucidated that unit owners must act collectively in representative actions and outlined the implications of limitation periods on legal recourse.

Result: Various claims were dismissed and recalibration of charges was mandated, with costs ordered against Plaintiffs.

Petitioner Advocates:Viola Lettice Decruz,Claudia Lynette Silva ,Respondent Advocate: Aqil Nasharuddin

Table of Content
1. court dismisses striking out application. (Para 1 , 2)
2. plaintiffs and defendants are identified. (Para 3 , 4 , 5 , 6 , 7 , 10)
3. sale and purchase agreements outlined. (Para 8 , 9 , 11)
4. plaintiffs seek various forms of damages. (Para 12)
5. plaintiffs file for summary disposal. (Para 14 , 15 , 16 , 17 , 18)
6. court's observations on fact disputes. (Para 19 , 20 , 21 , 22 , 23)
7. issues of locus standi and limitations. (Para 26 , 27 , 28 , 29 , 30)
8. court grants clarification on procedural applications. (Para 31 , 32 , 33 , 34)
9. declaratory reliefs and counterarguments discussed. (Para 35 , 36)
10. court issues conclusion and orders. (Para 39 , 40 , 41)
11. costs awarded and further instructions. (Para 46 , 47)
JUDGMENT

Sumathi Murugiah JC:

A. Introduction

[1] Previously, this suit was filed by the Plaintiffs against 15 Defendants; however, by way of a striking out application pursuant to O 18 r 19(1) of the Rules of Court 2012 (" ROC 2012"), the 4th to 15th Defendants have been struck out from this suit by this Court. Maintaining the remaining Defendants.

[2] This is the grounds of judgment written for the decisions which I had delivered on 13 February 2025 for both the Plaintiffs' and the 1st and 2nd Defendants' application via Enclosure Nos: 18 and 119 respectively for a summary disposal pursuant to O 14A ROC 2012. Also, for the decision delivered on 27 March 2025 for the application filed by the Plaintiffs against the 3rd Defendant via Enclosure No: 117 pursuant to O 14A 2012.

B. Brief Background

[3] The Plaintiffs are individuals and companies with the details as set out in Item B of Appendix A, as set out in the said Statement of Claim.

[4] The 1st Defendant is a company incorporated in Malaysia under the Companies Act 1965 and having its registered address at Level 10, Block G, No 2, Jalan PJU 1A/7A, Ara Damansara, PJU 1A, 47301 Petaling Jaya, Selangor Darul Ehsan, Malaysia, and is the Vendor/Developer of the development project known as OASIS ARA DAMANSARA (hereinafter referred to as the "said Project").

[5] The 2nd Defendant is a company incorporated in Malaysia under the Companies Act 1965 and having its registered address at Level 10, Block G, No 2, Jalan PJU 1A/7A, Ara Damansara, PJU 1A, 47301 Petaling Jaya, Selangor Darul Ehsan, Malaysia, and is the proprietor of the land on which the said Project was developed.

[6] Pursuant to the sale and purchase agreements entered into between the 4th, 5th, 7th, 8th, 10th (except Parcel No A-G 09), 11th, 13th, 14th, 16th and 19th Plaintiffs (hereinafter referred to as "the said Original Purchasers") respectively with the 1st Defendant and the 2nd Defendant, as specified in Item F in Appendix A of the said Statement of Claim (hereinafter referred to as "the Original Sale and Purchase Agreements), the said Original Purchasers purchased, and the 1st and 2nd Defendants sold, the parcels specified in Item C of Appendix A of the said Statement of Claim (hereinafter referred to as "the said Parcels") for the purchase prices as set forth in Item G of Appendix A of the said Statement of Claim (hereinafter referred to as the "said Original Purchasers' Purchase Prices") of the parcels in the said Project.

[7] The 1st, 2nd, 3rd, 6th, 9th, 10th (except for parcel A-G 09), 12th, 15th, 17th and 18th Plaintiffs are the sub-sale purchasers of the parcels specified in Item C in Appendix A of the said Statement of Claim (hereinafter referred to as "the said Parcels") and are bound by the terms of the Original Sale and Purchase Agreements between the Original Purchasers and the 1st and 2nd Defendants as successors-in-title and assignees of the rights and interests of the Original Purchasers.

[8] The said Project is developed on a piece of land identified as HS(D) 11[1073] PT 9 in the Mukim of Damansara, District of Petaling, State of Selangor, measuring 63,862 sq meters ("hereinafter referred to as "the said Land") and comprises:

a) Commercial shops and offices (Commercial Parcels) of