SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 2987

HIGH COURT MALAYA SHAH ALAM
PUJIAN DEVELOPMENT SDN BHD – Appellant
Versus
THEAN JUN THYE & ORS – Respondent
[Originating Summons No: BA-24NCC-29-03/2023]



Petitioner Advocates:Ben Lee Kam Foo,Nur Amalin Shahida Sabidi ,Respondent Advocate: Harwinder Kaur Harbhajan Singh,Keshvinder Kaur Harvinder Singh,Dhanesh Subramaniam Nair

The existence of a bona fide dispute over claimed debts justifies granting a Fortuna Injunction to prevent potential irreparable harm to the plaintiff from a winding-up petition.

Headnote:(A) Companies Act 2016 - Sections 465(1)(e) and 466(1)(a) - Fortuna Injunction - Plaintiff seeks an injunction against winding up petition - Court assesses whether there exists an undisputed debt - Judgment sum of RM10,365,862.00 ordered for damages was claimed as being fully satisfied by a Consent Order but the claimed interest was disputed - Court finds prima facie a bona fide dispute exists over the claimed sum - Balance of interests necessitates granting a Fortuna Injunction. (Paras 17-20, 32, 46, 56, 58)

(B) Legal principles for granting Fortuna Injunction - An applicant must show that a winding-up petition would cause irreparable harm and must demonstrate that there is no reasonable prospect of success for the petition. (Paras 27-28, 30)

Facts of the case:
Plaintiff sought to restrain the Defendants from filing a winding-up petition related to disputes over debts totaling RM1,729,404.82. The main contention involved whether this claim constituted an undisputed debt based on various court orders and judgments concerning damages from abandoned construction of a commercial project. (Paras 1-14)

Findings of Court:
Court ruled that the compelling nature of the dispute on interest renders the claimed debt as bona fide disputed despite the existence of a judgment sum in favor of the Defendants. The Plaintiff's application for Fortuna Injunction is justified. (Paras 56, 58)

Issues: Whether the Plaintiff has an undisputed debt necessitating the winding-up petition. (Paras 4, 42)

Ratio Decidendi: Court finds that despite a judgment sum favoring the Defendants, the claims for extra interest are contested, warranting further judicial protection through the Fortuna Injunction to prevent irreparable harm. (Paras 56, 58)

Result: Plaintiff's application for Fortuna Injunction allowed with costs.

Table of Content
1. plaintiff seeks fortuna injunction against winding-up petition. (Para 1 , 2 , 3 , 4)
2. background and developments of the case's legal proceedings. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16)
3. plaintiff's arguments disputing defendants' claims. (Para 17 , 18 , 19 , 20)
4. defendants assert validity of their debt claims. (Para 21 , 22 , 23)
5. principles governing fortuna injunction established. (Para 25 , 26)
6. criteria for granting fortuna injunction explained. (Para 27 , 28 , 30)
7. court evaluates the plaintiff's contention of solvency. (Para 31 , 32 , 38 , 39)
8. court establishes disputed vs undisputed debt key issue. (Para 40 , 44 , 45 , 49 , 52 , 54 , 56)
9. court’s final ruling on the fortuna injunction application. (Para 58 , 59)
Choong Yeow Choy JC:

Introduction

[1] The Plaintiff in its Originating Summons sought a Fortuna Injunction to restrain the Defendants from presenting a winding up petition against it.

[2] This Court allowed the Plaintiff's application and the Defendants have filed an appeal against that decision.

The Pertinent Issues

[3] The principal issue for determination is whether the Plaintiff is entitled to the relief sought.

[4] Arising from the above dominant issue is the following subsidiary question, namely, whether there is an undisputed debt.

The Apposite Background Facts

[5] The origin of this case can be traced to as far back as 23 years ago.

[6] It involved claims initiated by the Defendants, who were purchasers of commercial properties in a development project developed by the Plaintiff.

[7] The Plaintiff had abandoned the construction of the development project and this resulted in the Defendants initiating proceedings vide Civil Suit MT-3-22-573-2003 against the Plaintiff. The Plaintiff had sought to terminate the Sale and Purchase Agreements and for damages to be assessed.

[8] On 3 December 2010, the High Court granted judgment in favour of the Defendants and ordered for damages to be assessed.

[9] That decision of the High Court was affirmed by the Court of Appeal on 3 October 2011.

[10] On 29 July 2011, the Defendants filed an application for assessment of damages.

[11] On 17 September 2019, the learned Senior Assistant ordered the Plaintiff to pay to the Defendants damages for (i) the out-of-pocket expenses; (ii) the total bank loan sum pursuant to the respective Loan Agreements; (iii) pre judgment interest at the rate of 10% per annum under s 11 of the Civil Law Act 1956 ; and (iv) post judgment interest of 5% per annum under O 42 r 12 of the Rules of Court 2012, calculated from 4 December 2010 until full settlement by the Plaintiff.

[12] As of the date of the Order made by the learned Senior Assistant Registrar, the total sums payable by the Plaintiff to the Defendants was RM10,365,862.00.

[13] It is crucial to note that the Plaintiff had appealed against the decision of the Senior Assistant Registrar's Order relating to the s 11 of the Civil Law Act 1956 and the O 42 r 12 of the Rules of Court 2012 interest claims to the High Court where the High Court allowed the Plaintiff's appeal on the s 11 of the interest claims but dismissed the Plaintiff's appeal on the O 42 r 12 of the Rules of Court 2012 interest claims Both the Plaintiff and Defendants appealed against the decision of the High Court and on 16 January 2023, the Court of Appeal reinstated the Senior Assistant Registrar's Order of 17 July 2019.

[14] It should also be noted that pending the disposal of the abovementioned appeals, the parties had also entered into a Consent Order for a conditional stay of the Senior Assistant Registrar's Order of 17 July 2019.

[15] One of the key terms of the Consent Order which was dated 19 February 2020 was that the judgment sum of RM10,365,862.00 be deposited into the fixed deposit joint interest-bearing solicitors' account to the Defendants.

[16] Upon all the appeals having been disposed off (by the Court of Appeal) on 16 January 2023, the parties agreed for the AmBank Berhad t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top