COURT OF APPEAL KOTA KINABALU
POTECK ENTERPRISE SDN BHD – Appellant
Versus
RICHALLENGE CORPORATION SDN BHD – Respondent
[Civil Appeal No: S-02(IM)(NCvC)-151-01-2022]
| Table of Content |
|---|
| 1. appeal on damage assessment after contract termination. (Para 1 , 2 , 3 , 4 , 5) |
| 2. background of the contractual relationship and disputes. (Para 6 , 7 , 8 , 9 , 10 , 11 , 12) |
| 3. standard for appellate review on damage assessment. (Para 14 , 15 , 16 , 17) |
| 4. reliability of expert testimony in damage valuation. (Para 19 , 20 , 21) |
| 5. burden of proof for claims of loss of profit. (Para 30 , 32 , 40) |
| 6. refund of performance bond due to contract termination. (Para 36 , 37 , 38) |
| 7. need for substantiating evidence in profit loss claims. (Para 39 , 41 , 44) |
| 8. final ruling on damages and costs awarded. (Para 46 , 47) |
Introduction
[1] This is an appeal on the assessment of damages pursuant to a terminated construction contract.
[2] The Appellant, who is the defendant in the High Court, is a private limited company.
[3] The Respondent, also a private limited company, is the plaintiff in the High Court.
[4] We heard the appeal on 14 March 2025 and subsequently adjourned the decision to allow time for deliberation on the arguments presented by the parties.
[5] Now having done so, we hereby give our decision below together with our supporting grounds.
Background
[6] The Appellant was awarded the main contract by the Ministry of Education of the Federal Government of Malaysia ("Employer") to construct a school named Sekolah Menengah Kebangsaan Tandek 2, located in Kuala Marudu, Sabah, with a contract value of RM42,750,000.00 ("Main Contract Sum").
[7] The Appellant thereafter sub-contracted the carrying out of the whole of the building works to the Respondent via a written sub-contract agreement dated 28 July 2009 ("Sub-Contract Agreement"). The sub-contract sum of the Respondent is determined at RM35,228,250.00 ("Sub-Contract Sum"), to wit, 85% of RM41,445,000.00 being the Main Contract Sum less contribution and levy charges of RM1,305,000.00. Thus, the balance of RM6,216,750.00, being 15% of the Main Contract Sum less contribution and levy charges is the Appellant's entitlement.
[8] During the course of construction of the school, there were disputes that arose that resulted in the Appellant, on 11 November 2014, terminating the Sub- Contract Agreement for the Respondent's failure to complete the construction of the school.
[9] Consequently, the Respondent commenced the action in the High Court ("Suit") and claimed damages against the Appellant for wrongful termination of the Sub-Contract Agreement. The Appellant counter-claimed damages against the Respondent, especially the extra costs incurred to complete the building works by Bangkit Energy & Pro Logistic (EM) Sdn Bhd ("Completion Contractor").
In The High Court
[10] After the trial of the Suit, the High Court on 15 November 2021, found in favour of the Appellant.
[11] On appeal by the Respondent, this Court in Civil Appeal No S-02(NCVC) (W)-2545-12/2017, reversed the High Court's decision on 21 March 2019 (see Richallenge Corporation Sdn Bhd v. Poteck Enterprise Sdn Bhd 2020 MarsdenLR 817 ; [2020] 3 MLJ 704 ; ; [2020] 4 AMR 865 ). The High Court was then ordered to assess the damages suffered by the Respondent due to the Appellant's unlawful termination of the Sub-Contract Agreement.
[12] Consequently, upon assessment, the High Court on 14 December 2021 allowed damages under the following headings:
Thus, the High Court ordered the Appellant to pay the total amount of RM8,999,897.27, with interest at the rate of 8% per annum from 29 September 2014 to the date of judgment and thereafter statutory interest on the said sum at the rate of 5% per annum from the date of judgment to the date of full payment and costs of RM10,000.00 subject to allocator.
[13] The Appellant is dissatisfied with the assessment made by the High Court and, therefore, filed an appeal with the Court of Appeal on 11 January 2022.
Findings Of This Court
[14] Although this is an appeal arising from the assessment of damages, our function here is no different from that of an appeal on liability after
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.