2025 MarsdenLR 3730

HIGH COURT MALAYA SHAH ALAM
SINLEXON CONSTRUCTION & DECORATION SDN BHD – Appellant
Versus
MBO CINEMA SDN BHD – Respondent
[Civil Suit No: BA-22C-16-05/2024]



Petitioner Advocates:Queeny Ban Qiao Hui ,Respondent Advocate: Justin Lee Soong Jun

JUDGMENT

Sumathi Murugiah J:

A. Introduction

[1] This is the Plaintiffs Striking Out Application pursuant to O 18 r 19(1)(a), (b), (c), and/or (d) of the Rules of 2012 filed via Enclosure No 50 of this Writ Summons.

[2] Essentially, this suit has been filed by the Plaintiff for the sum of RM3,362,146.13 being the outstanding payments for work done by the Plaintiff against the Defendant pursuant to a Purchase Order and Letter of Award both dated 8 March 2022 and the Plaintiff's letter dated 10 March 2022 (collectively referred to as "the contract") entered into by the Plaintiff and the Defendant.

[3] The Defendant has via its Statement of Defence, filed a counterclaim against the Plaintiff for a sum of RM8,160,000.00 being the sum claimed to be Liquidated Ascertained Damages (LAD) owed to the Defendant for the alleged purported delay of 544 days.

[4] Via Enclosure No 5, the Plaintiff had filed for a Summary Judgment against the Defendant for the outstanding sum of RM3,362,146.13 which I had allowed with costs on 12 March 2025. Prior to allowing the Summary Judgment sought by the Plaintiff, I dismissed the Defendant's application to strike out the pleadings which was filed via Enclosure No 16 pursuant to O 18 r 19(1)(b), (c) and (d) of the Rules of 2012 on the same day.

[5] Via this application ie Enclosure No 50, the Plaintiff has filed an application to strike out the counterclaim filed by the Defendant pursuant to O 18 r 19(1)(a),(b),(c) and (d) of the Rules of 2012.

B. Brief Background

[6] The Defendant engaged the Plaintiff via the contract as a contractor for a project known as:

"Architerual And Interior Works For Proposed 8 Screen Multiplex Cinemas At Level 2 To Level 4 Of Gamuda Quayside Mall, 42500 Telok Panglima Garang For Mbo Cinema Sdn Bhd"

(hereinafter referred to as "the Project")

[7] The contract was awarded for a sum of RM5,846,240.00 ("original contract sum"), which was subsequently increased to RM6.047,102.31 ("new contract sum") inclusive of variation works in the sum of RM200,862.31.

[8] The project commenced on 4 March 2022 and contract period was to be for 19 months which ended on 15 July 2022. The Project Architect had on 28 June 2022 issued a letter to the Plaintiff issuing the Certificate of Practical Completion ("CPC") and confirming that the Defects Liability Period ("DLP") of 18 months was due to end on 27 December 2023. Through the same letter, the Project Architect also confirmed the following:

"The Works were completed to our satisfaction and taken into possession on: 28 June 2022"

[9] The Plaintiff, having discharged its duties and obligations under the contract in full, proceeded to issue Progress Claims Nos 1 to 5 for a total sum of RM6,047,102.31, all of which had been certified by the Project Architect. In this regard, the Plaintiff issued the following invoices for said sum of RM6.047,102.31 to the Defendant:

[10] The Defendant did not at any material time object to the Plaintiff's Progress Claims Nos 1 to 5, the Project Architect's certifications, and the Plaintiff's invoices for said Progress Claims Nos 1 to 5. In this regard, the Defendant is deemed to have admitted to owing the sum of RM6,047,102.31 to the Plaintiff.

[11] There is an instalment payment schedule dated 28 October 2022 ("instalment payment schedule") between the parties confirming the sum owed to be RM3,946,212.00, following which the Defendant had paid a sum of RM708,335.66 as part payment.

[12] The Defendant has undisputedly made part payments in the total sum of RM2,662,207.66 ("part payments"). Taking into consideration the part payments made by the Defendant together with the credit notes issued by the Plaintiff in the total sum of RM22.748.52, there is an undisputed sum of RM3,362,146.13 remaining due and payable by the Defendant to the Plaintiff.

[13] The breakdown of the sum owed to the Plaintiff by the Defendant is shown as follows:

[14] Although numerous reminders were sent to the Defendant for payments to be made for the outstandi