2025 MarsdenLR 4522

HIGH COURT MALAYA KUALA LUMPUR
BESTINET SDN BHD – Appellant
Versus
3B IDEA CREATION SDN BHD – Respondent
[Civil Appeal No: WA-12BC-20-12/2022]



Petitioner Advocates:Edmund Bon Tai Soon,V Jeya Kumar,Khor Xiaou Shan,Natalie Jong Ling Li ,Respondent Advocate: Tunku Ahmad Munawwir Tunku A Mustaffa

JUDGMENT

Nadzarin Wok Nordin J:

(Enclosure 1)

Introduction

[1] This is an appeal against the judgment of the Sessions Court given on 22 November 2022 dismissing the whole of Bestinet Sdn Bhd ("Appellant") claims and allowing 3B Idea Creation Sdn Bhd ("Respondent") counter claim with costs and against the order of the Sessions Court given on 29 November 2021 (29 November 2021 Judgment) in dismissing the Appellants application to Amend the Writ and Statement of Claim (29 November 2021 Order).

[2] In support of the Appellant's appeal, the Appellant had inter alia stated that

2.1 the learned Sessions Court Judge ("SCJ") had been confused about the nature of the contract entered into by the parties

Basic Background Facts

[3] Pursuant to a series of proposals and negotiations from on or about November 2017 until April 2018, Bestinet had agreed to appoint 3B to carry out works for the interior design and fit out at Bestinet's new Corporate Office which is an 8-storey building (including ground floor) situated at Block 5, Corporate Park, Star Central, Lingkaran Cyber Point Timur, Cyber 12 Cyberjaya 63000 Selangor ("the Premises").

[4] Bestinet and 3B had subsequently entered into a contract to execute the works under 3B's Quotation No 3B/BES-3-4- 2018/QUO/01/R1 dated 6 April 2018 and Bestinet's Purchase Order No BT-18-04-009-PO dated 13 April 2018 for a total value of RM1,890,090.00 ("the Contract"). It was a design and build contract where 3B was to design and carry out the construction works for the completion of the project.

[5] Bestinet contends that pursuant to the Contract, 3B had agreed to:

5.1 design the interior of the Premises and attend to the fit-out works;

5.2 advise Bestinet and provide the specifications required for the materials and various works in the Premises based upon 3B's approved design to enable Bestinet to invite for tenders from contractors and suppliers;

5.3 supervise all the works carried out both by 3B's own workers as well as any Nominated Sub Contractors ("NSC") appointed by Bestinet in respect of the fit-out works at the Premises to ensure that all said materials and works were of the standard and quality expected by Bestinet and in accordance with 3B's design and specifications;

5.4 hand over the Premises together with all approved drawings and plans upon due completion of the entire fit- out works and upon obtaining all requisite certifications and approvals from the relevant professionals and/or authorities on or before the scheduled completion.

[6] As part of Bestinet's overall renovation plans for the Premises, various subcontractors were appointed to carry out specific fit-out works for the Premises. Pursuant to this, 3B had also been appointed to carry out specific fit-out works amounting to RM3,510,329.90 as set out in the subsequent Quotations, Purchase Orders and Invoices issued between the parties.

[7] The total contract sum payable by Bestinet to 3B for the entire scope of works that 3B was required to carry out amounted to RM5,400,419.90.

[8] At all material times, Bestinet had dealt with 3B in good faith and had relied entirely on the representations by 3B or its officers that 3B would ensure that the renovation and fit-out works would be carried out in accordance with the levels of professionalism, quality and specifications expected by Bestinet in view that 3B is in the business of renovation works and interior design services.

[9] 3B commenced work at the Premises in April 2018. However, as of March 2019 the works were still not completed. Bestinet had to move in to occupy a few floors in the Premises on 22 March 2019 although the works on the Premises were still ongoing as it had already been forced to vacate other offices where Bestinet used to operate from as notice of termination of those tenancies had already been given in reliance of 3B's representations and assurances that the Premises would be ready for Bestinet's occupation by March 2019. 3B agreed at trial that the defect liability perio


1
2
3
4
5
6
7
8
9
10
11