SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 5992

COURT OF APPEAL (PUTRAJAYA)
ABDUL RAHMAN SEBLI,, MARY LIM THIAM SUAN, J, HASNAH MOHAMMED HASHIM, JJCA
KNM Process Systems Sdn Bhd – Appellant
Versus
Lukoil Uzbekistan Operating Company LLC – Respondent
CIVIL APPEAL NO W-02(C)(A)-1504-07/2018



Advocates:
Cyrus Das (Michael Chow and Wendy Yeong with him) (Michael Chow) for the appellant.
Jack Yeow (Daphne Koo, Kwong Chiew Ee and Melvin Ng with him) (Rahmat Lim & Partners) for the respondent.

Unconscionability serves as an independent ground for a restraining order against calls on guarantees, contingent on established strong evidence of bad faith or improper conduct by the beneficiary.

Headnote:(A) Arbitration Act 2005 - Sections 10 and 11 - Application for interim injunctive relief pending arbitration - High Court found no strong prima facie case of fraud or unconscionability and denied relief - Appellate court concluded the guarantees were not unconditional, leading to lack of objective entitlement to call - The simultaneous calls were unconscionably made without proper basis or notice of dissatisfaction. (Paras 30-86)

(B) Unconscionability as a ground for restraining calls on guarantees and bonds - The court recognizes unconscionability as a separate and independent ground to grant restraining orders, requiring strong evidence of bad faith or misconduct. (Paras 49-67)

(C) The Importance of Underlying Contractual Terms - Calls must comply with stipulated conditions; premature calls violate contract obligations. (Paras 62-64)

Facts of the case:
The plaintiff/appellant contested calls made on three guarantees from the defendant/respondent, alleging these calls were premature and unconscionable, arising from distinct contracts related to separate construction phases in Uzbekistan. The High Court initially dismissed the claims.

Findings of Court:
Appellate court found the calls invalid due to lack of clear contractual grounds and signs of good faith, allowing the appeal and affirming interim injunctions to prevent the defendant from acting on the guarantees.

Issues: Determination of adequacy of prima facie case, validity of simultaneous calls on distinct guarantees, and assessment of unconscionability in the context of contractual obligations.

Ratio Decidendi: Unconscionability as a legal doctrine is a basis for rescission of contract strength; the appellant’s claims of unavailability for calls, resulting from a breach of contract, establish a prima facie basis for equitable relief against such calls pending arbitration.

Result: Appeal allowed.

Table of Content
1. overview of the case and contractual background (Para 1 , 2 , 3 , 4 , 5 , 6 , 7)
2. respondent's counterarguments against unconscionability (Para 8 , 22 , 23)
3. arguments on injunction validity and abuse of process (Para 9)
4. high court’s findings and reasoning (Para 10 , 11)
5. appellant's complaints regarding contract terms (Para 12 , 13 , 14 , 15 , 16)
6. respondent's denial of obligations under contracts (Para 24 , 25)
7. sanctions and their relevance to the case (Para 27 , 28 , 29)
8. legal provisions regarding interim measures (Para 30 , 31 , 32)
9. tests for granting interim reliefs (Para 33 , 34)
10. court's perspective on arbitration and interim relief (Para 39 , 40 , 41)
11. establishing fraud and unconscionability (Para 46 , 47 , 48 , 49)
12. considerations for unconscionability claims (Para 50 , 51 , 52 , 53)
13. details and interpretations of guarantees (Para 60 , 61 , 62 , 63)
14. implications of bad faith in guarantee calls (Para 64 , 65)
15. importance of contractual terms in the analysis (Para 67 , 68)
16. assessing the validity of calls on guarantees (Para 69 , 70 , 71 , 72 , 73)
17. final observations on warranty guarantees (Para 74 , 75 , 76 , 77 , 78)
18. court's ruling on the appeal (Para 79 , 80 , 81)

Mary Lim Thiam Suan JCA:

JUDGMENT OF THE COURT

[1]The appellant was unsuccessful in its application made pursuant to section 11(1)(f)(h) Arbitration Act 2005 [Act 646]

The guarantees

[2]There are two underlying contracts between the parties:

i.Contract No. UZ-10-8009-0706 dated 3.12.2010 where the respondent appointed the appellant as a contractor to supply technical documentation and equipment for the construction of gas-condensate fields of Adamtash, Gumbulak and Djharkuduk-Yangi Kizilcha in the Republik of Uzbekistan [Gissar Main Contract];

ii.Contract No. UZ-11-8009-0649 dated 3.10.2011 where the respondent appointed the appellant for the development of detailed design and supply of equipment for the “Booster Compressor Station in Khauzak Site” in the Republik of Uzbekistan [Khauzak Main Contract];

[3]Both contracts contain provisions for guarantees of different total amounts as follows:

i.Gissar Main Contract [totaling USD37 million]: Performance Guarantee No: 5789031; and Guarantee for Refund of Advance Payment No: 5789175

ii.Khauzak Main Contract [USD3 million]: Warranty Guarantee No: 5842339

[collectively referred to as “the guarantees”]

[4]On 27.11.2017, the respondent issued simultaneous demands on all three guarantees. This caused the appellant to file Civil Suit No: 22C-110-12/2017 at the High Court at Kuala Lumpur against both the respondent and Malayan Banking Berhad, the issuing Bank, seeking in substance to restrain any payments being made out or received under the guarantees. The appellant claimed that the demands were fraudulent and unconscionable.

[5]On 6.12.2017, the High Court granted an ex parte injunction against both the respondent and the issuing Bank.

[6]The respondent approached the Court to stay the appellant’s claim relying on section 10Arbitration Act 2005

[7]The order of stay was granted by consent. We understand that the arbitration somewhat stalled, with the parties unresolved as to who exactly was responsible for initiating the arbitration, the respondent or the appellant, with both parties pointing to the other. The appellant has since initiated the arbitration.

[8]By agreement, the present Originating Summons was then filed to determine the matter of whether interim injunctive orders may be granted on the calls on the guarantees under section 11Arbitration Act 2005

i.the Guarantee for Refund of Advance Payment under the Gissar Main Contract was not an unconditional demand bond;

ii.the calls were not in compliance with the terms of the Gissar Main Contract;

iii.in any event, the call was only available upon termination and that did not arise in the instant case;

iv.contemporaneous evidence and conduct of the parties, especially the respondent show that there was no objective entitlement

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top