SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

HIGH COURT (KUALA LUMPUR)
MARY LIM, J
Ranhill E & C Sdn Bhd – Appellant
Versus
Tioxide (M) Sdn Bhd and other – Respondent
ORIGINATING SUMMONS NOS 24C-9-04 OF 2015, 24C-15-04 OF 2015, 24C-11-04 OF 2015 AND 24C-16-05 OF 2015



Advocates:
John A Skelchy (Vishal V Kumar and Sean Denis with him) (James Monteiro) for the plaintiff.
Avinash Pradhan (Rubini Murugesan with him) (Christopher & Lee Ong) for the defendant.

Adjudication decisions under CIPAA 2012 are valid and enforceable unless substantial breaches of natural justice occur; interim resolutions are crucial for maintaining cash flow in construction disputes.

Headnote:(A) Construction Industry Payment and Adjudication Act 2012 - Section 28 - Enforcement of adjudication decisions under challenge due to alleged excess of jurisdiction and denial of natural justice - The adjudicator’s decisions upheld as valid, emphasizing the swift resolution of payment disputes - The contracts between parties and jurisdictional challenges examined under CIPAA's provisions prioritize interim decisions for cash flow in the construction industry. (Paragraphs 8, 9, 15, 24, 25, 81, 105)

(B) Jurisdictional Challenges in Adjudication - It was found that parties cannot derive a benefit from their own wrongs in arbitration agreement contexts - Adjudicators may assume jurisdiction when conditions, per CIPAA 2012, are fulfilled. (Paragraphs 27, 30, 81)

Facts of the case:
The disputes arise from two contracts between a construction firm and a private limited company, with Tioxide challenging adjudication decisions favoring Ranhill. The adjudication decisions addressed claims regarding non-payment of invoices and the validity of set-offs raised by Tioxide.

Findings of Court:
The court dismissed the challenges to adjudication decisions, emphasizing the importance of interim resolutions for payment disputes in construction.

Issues: Whether adjudication clauses in contracts were breached and if adjudicators exceeded jurisdiction.

Ratio Decidendi: The court affirmed that the nature of CIPAA 2012 allows multiple dispute resolution mechanisms, including adjudication for interim decisions, and that challenges based on natural justice must demonstrate material impact on outcomes.

Result: Applications to set aside dismissed; enforcement of adjudication decisions allowed.

Table of Content
1. case summary and introductory information (Para 1 , 2 , 3)
2. facts about the contractual relationship (Para 4 , 5 , 6 , 7)
3. adjudication process and claims (Para 8 , 9 , 10 , 11 , 12 , 13)
4. rulings on jurisdiction and claims (Para 18 , 21 , 22 , 29)
5. arguments regarding jurisdiction and natural justice (Para 24 , 30 , 31 , 46)
6. understanding of court's view on adjudication (Para 59 , 63 , 72)
7. final ruling and order (Para 105 , 106)

MARY LIM J

GROUNDS OF JUDGMENT

Introduction

[1]These four applications are heard together. Two of them, Originating Summons No: 24C-15-04/2015 and Originating Summons No. 24C-11-04/2015 concern an adjudication decision made by IR Leon Weng Seng on 6.4.2015. The other two Originating Summonses Nos. 24C-16-05/2015 and 24C-9-04/2015 concern an adjudication decision made by Murelidaran M Navaratnam on 30.3.2015.

[2]All four Originating Summons were heard together. It makes every good sense since these cases concern the same primary parties who had entered into two separate yet related contracts. The disputes that arose between them went to two separate adjudications, both of which are under challenge. Ranhill E&C Sdn Bhd [Ranhill], the successful party, is seeking to enforce both decisions under section 28Construction Industry Payment and Adjudication Act 2012

[3]There are many common grounds relied on both parties in respect of all four cases. All four cases were heard together with written and oral submissions made by all counsel. The parties are in agreement that Ranhill’s applications for enforcement follow consequently in the event Tioxide’s applications to set aside are dismissed.

The construction contracts

[4]These are the background facts. Tioxide is a private limited company incorporated under the laws of Malaysia and is part of the group of companies owned by the Huntsman Corporation (“Huntsman”). Huntsman is listed on the New York Stock Exchange. Tioxide Malaysia operates a pigment manufacturing plant also known as the Teluk Kalong Facility at Kawasan Perindustrian Teluk Kalong, Terengganu Darul Iman. It is responsible for managing a project known as “Sustainability Project Phase 1 – Copperas Extraction” (the “PSP1 Project”). Ranhill is in the business of construction and engineering contracting.

[5]Tioxide decided to expand the capacity of the Teluk Kalung Facility. It identified various sections of the Facility for upgrading, expansion and construction. One of those sections was Substation 5 and the MCC Building which housed the electricity facilities. It was decided that these two sections would be expanded. Tebodin (Malaysia) Sdn Bhd was engaged to oversee the construction works. Tebodin was the Project Manager.

[6]In June 2013, Ranhill and Tioxide entered into two agreements with respect to these upgrading, expansion and construction works of the PSP1 Project:

i.An agreement in writing entitled Contract for Civil Works dated 9.5.2013 (the “Civil Works Contract”) where Ranhill agreed to undertake the supply of civil works for the Production Sustainability Project Phase 1 – Cooperas Extraction – Building and Construction for RM7,025,530.78. The Civil Works Contract was amended on 23.12.2013.

ii.An agreement in writing entitled Contract for Mechanical & Piping Works dated 18.6.2013 (the “MPW Contract”) for an agreed price of RM8,550,000.00.

[7]Disagreements arose between the parties which were brought to adjudication by Ranhill.

The adjudication - the Civil Works Contract

[8]In relation to the Civil Works Contract, Ranhill’s claim was based on a failure to certify a total sum of RM224,304.85 as seen in Invoice and Interim Payment Certificate No. 13. Ranhill’s position was that Tebodin ought to have certified that amount as payable but had failed to do so. To this, Tioxide inter alia alleged that the contract was not based on measurement of works as submitted by Ranhill; that there were delays, third party involvement and failure to carry out contractual obligations; that Ranhill h

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top