HIGH COURT (KUALA LUMPUR)
SAHERAN SUHENDRAN, JC
Pembinaan BY Sdn Bhd – Appellant
Versus
Minda Muhibah Sdn Bhd & Anor – Respondent
ORIGINATING SUMMONS NO WA-28JM-9-06 OF 2025
| Table of Content |
|---|
| 1. applications for judicial management. (Para 2 , 3 , 4) |
| 2. background facts regarding the contractual relationship. (Para 6 , 7 , 8) |
| 3. details on cipaa adjudication and contract terminations. (Para 9 , 10 , 11 , 12 , 13) |
| 4. subsequent settlement agreements. (Para 14 , 15 , 16 , 17 , 19) |
| 5. statutory notices and winding-up petition filings. (Para 20 , 21 , 22 , 23 , 24) |
| 6. details of the judicial management application. (Para 25 , 26 , 27) |
| 7. court's observations on the locus of creditors. (Para 31 , 32 , 33 , 34 , 35 , 36) |
| 8. judicial precedent and its implications. (Para 39 , 40 , 41 , 42) |
| 9. the assessment of the respondent's financial viability. (Para 86 , 87 , 88 , 89 , 90 , 91 , 92 , 93 , 94 , 95 , 96 , 97 , 98 , 99 , 100) |
| 10. conclusion regarding winding-up petitions. (Para 102 , 103 , 104) |
GROUNDS OF JUDGMENT
[1]These Grounds concern 2 applications filed herein, Encl 1 and Encl 10.
INTRODUCTION
[2]Encl 1 was filed by the Applicant, Pembinaan BY Sdn. Bhd. (“Applicant”) for orders, inter alia:
a.that Minda Muhibah Sdn. Bhd. (“the Respondent”) be placed under Judicial Management pursuant to s. 405Companies Act 2016CA 2016”);
b.that Mr. Andrew Heng and Mr. Kumarakuru Krishnan, be jointly and severally appointed as Judicial Managers of the Respondent;
[3]Encl 10 was filed by China State Construction Engineering (M) Sdn. Bhd. (“China State”), pursuant to, inter alia, O. 15 r. 6(2)(b), O. 18 r. 19(1)(b), (1)(c) and/or (1)(d) and O. 92 r. 4 of the Rules of Court 2012 , s. 410(c) CA 2016inter alia, the following Orders:
a.China State be granted leave to intervene and be added as the 2nd Respondent in these proceedings;
b.Encl 1 be struck out;
c.China State be granted leave to continue with the arbitration against the Respondent ‘In the Matter of the Arbitration Act 2005 (Amended 2011 & 2018) and In the Matter of an Arbitration between Minda Muhibah Sdn Bhd and China State Construction Engineering (M) Sdn Bhd’ (“Arbitration”);
d.China State be granted leave nunc pro tunc to continue with the winding up proceedings against the Respondent in KL HCt [OS No. WA-24NCC-339-06/2025] (“OS 339”) and KL H Ct [Companies Winding Up Petition No. WA- 28NCC-648-06/2024] (“Petition 648”);
[4]Save where the context otherwise provides, all references to sections are with reference to the sections of CA 2016.
[5]The contents of these Grounds are set out below.
| Contents | Para |
|---|---|
| INTRODUCTION | 2-5 |
| BACKGROUND FACTS | 6-8 |
| CIPAA 1 | 9-10 |
| Termination of Contract | 11-12 |
| Arbitration | 13 |
| Settlement Agreement 1 | 14 |
| CIPAA 2 | 15-16 |
| Settlement Agreement 2 | 17-19 |
| Statutory Notice of Demand | 20-21 |
| Respondent’s Fortuna Application (OS 300) | 22-24 |
| Winding-Up Petition against the Respondent (Petition 648) | 25-26 |
| China State’s Fortuna Application (OS 339) | 27 |
| Encl 1 – Judicial Management Application (“JMA”) | 28-30 |
| China State & the Locus of an Unsecured Creditor | 31-38 |
| An Unenviable Choice | 39-59 |
| Inconsistency | 60-69 |
| Encl. 10 & the Striking Out | 70-72 |
| Encl 1 & the Appointment of the JM | 73-86 |
| Respondent is Severely Insolvent | 87-89 |
| No Real Proof of Financing | 90-101 |
| Prayer 6 – Leave ‘Nunc Pro Tunc’ to Proceed with Petition 648 | 102-105 |
| CONCLUSION | 106-108 |
BACKGROUND FACTS
(see generally, Encl 11)
[6]The following background facts are adopted from the submissions of China State, for which I am grateful.
[7]The Respondent is the employer of a commercial development known as ‘Rencana Royale’ (“Project”).
[8]By a Letter of Award dated 12.11.2018, the Respondent appointed China State as the main contractor for the main building works under the Project (“Works”) for a total sum of RM160,627,298.81 (“Contract”).
CIPAA 1
[9]On 24.6.2022, China State commenced adjudication proceedings (Adjudication Reference No. AIAC/D/ADJ-4334- 2022) against the Respondent for unpaid certified sums due and owing under Interim Payment Certificates No. 18-32, 34 and 35 in respect of the work done (“CIPAA 1”).
[10]On 25.10.2022, China State obtained an adjudication decision against the Respondent for the sum of RM5,285,194.28 together with interest an
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.