2025 MarsdenLR 5514
HIGH COURT (KUALA LUMPUR)
ALIZA SULAIMAN J
ORIGINATING SUMMONS NOS WA-24C-25-02 OF 2024 AND WA-24C-29-03 OF 2024
24 January 2025
Reno Nga Chee Leang (with Ivan Tan) (Nga Chambers) in Originating Summons No WA-24C-25-02 of 2024 for the plaintiff.
Felicia Lai Wai Kim (Harold & Lam Partnership) in Originating Summons No WA-24C-29-03 of 2024 for the plaintiff.
Felicia Lai Wai Kim (Harold & Lam Partnership) in Originating Summons No WA-24C-29-03 of 2024 for the defendant
Reno Nga Chee Leang (with Ivan Tan) (Nga Chambers) in Originating Summons No WA-24C-29-03 of 2024 for the defendant.
Reno Nga Chee Leang (with Ivan Tan) (Nga Chambers) in Originating Summons No WA-24C-25-02 of 2024 for the plaintiff.
Felicia Lai Wai Kim (Harold & Lam Partnership) in Originating Summons No WA-24C-29-03 of 2024 for the plaintiff.
Felicia Lai Wai Kim (Harold & Lam Partnership) in Originating Summons No WA-24C-29-03 of 2024 for the defendant
Reno Nga Chee Leang (with Ivan Tan) (Nga Chambers) in Originating Summons No WA-24C-29-03 of 2024 for the defendant.
Aliza Sulaiman J:
GROUNDS OF JUDGMENT
Introduction
[1]These suits involve the application by –
(a)Quantum Hyrdromech Sdn Bhd (‘Quantum’) pursuant to ss 131516Construction Industry Payment and Adjudication Act 2012Act 746] (‘CIPAA’) in Originating Summons No. WA- 24C-25-02/2024 (‘O.S. No. 25’) to set aside the Adjudication Decision dated 19.1.2024 (‘AD’) by the learned Adjudicator, Low Pei Voon (‘Adjudicator’) and to stay the AD pending the disposal of application to set aside the AD (‘Setting Aside Application’); and
(b)Nine Hundred Builders Sdn Bhd (‘NHB’) pursuant to s 28CIPAAO.S. No. 29’) to enforce the AD (‘Enforcement Application’).
[2]By consent of the parties, the prayer for a stay of the AD pending the disposal of the Setting Aside Application was allowed on the date of the hearing.
[3]After having considered the affidavit evidence and the submissions of the parties, the Court had, on 15.8.2024, I had dismissed the Setting Aside Application and allowed the Enforcement Application.
[4]The full grounds for the decision are set out in the succeeding part of this judgment.
The Cause Papers
[5]The cause papers for each application are as follows:
Setting Aside Application:
(a)Quantum’s O.S. dated 26.2.2024 (encl. 1);
(b)Quantum’s Affidavit In Support (‘AIS’) affirmed by its Director, Chong Set Tat on 26.2.2024 (encl. 2);
(c)NHB’s Affidavit In Reply (‘AIR’) affirmed by its Director, Goo Kian Peng on 25.3.2024 (encl. 4); and
(d)Quantum’s AIR affirmed by the same deponent on 8.4.2024 (encl. 5).
Enforcement Application:
(a)NHB’s O.S. dated 4.3.2024 (encl. 1);
(b)NHB’s AIS affirmed by the same deponent on 4.3.2024 (encl. 2);
(c)Quantum’s AIR affirmed by the same deponent on 25.3.2024 (encl. 3);
(d)Quantum’s Notice of Intention to Use Affidavit in O.S. 25 (encl. 2) dated 25.3.2024 (encl. 4); and
(e)NHB’s Notice of Intention to Use Affidavit in O.S. 25 (encl. 4) dated 9.4.2024 (encl. 5).
Background Facts
[6]Quantum is a private limited company incorporated in Malaysia with an address at C-8-5, Plaza Mont Kiara, No. 2, Jalan Kiara, Mont Kiara, 50480 Kuala Lumpur.
[7]NHB is also a private limited company incorporated in Malaysia with an address at No. 144, Jalan PUJ 3/8, Taman Puncak Jalil, Bandar Putra Permai, 43300 Seri Kembangan, Selangor.
[8]By the Letter of Award dated 6.3.2019 (‘LOA’), Quantum appointed NHB as the sub-contractor for the project known as “Design, Submission, Obtaining Approval from Authorities and Subsequently Supply, Delivery, Installation, Construction, Testing and Commissioning, and Maintenance of Proposed Upgrading Existing Sewage Treatment Plant Module 2 (Phase A) to Cater for Additional 20,000 P.E for Cadangan Pembangunan Perumahan Dan Perniagaan Di Atas Lot 934, 982, 1246, 1286, 1851 Dan 3513, Mukim Rawang, Daerah Gombak, Selangor Darul Ehsan” for a contract sum of RM4,200,000.00 (‘Project’).
[9]On 28.7.2023, NHB issued the Payment Claim pursuant to s 5CIPAA
[10]NHB claimed that it has completed its scope of works for the Project on 16.12.2019 and all the rectification works within the Defects Liability Period (‘DLP’) of 12 months i.e. by 15.12.2020.
[11]On 26.3.2021, NHB submitted its Revised Final Claim for the value of permanent work done and materials on site, which included variation works, amounting to RM288,624.73.
[12]Subsequently, on 12.5.2021, NHB issued an invoice for the sum of RM393,624.73 consisting of the Final Claim and 2nd moiety of the retention sum (RM105,000.00).
[13]On 26.5.2023, Quantum issued the Sub-Contractor’s Work Done Certificate No. 12 (Final) (‘PC No. 12’) amounting to a negative sum of RM72,405.60 upon release of the 2nd moiety of the retention sum.
[14]NHB contended that Quantum had under-valued and under-certified or wrongly certified NHB’s value of work done in PC No. 12. NHB claimed for the sum of RM393,624.73.
[15]Quantum did not serve any Payment Response and is therefore deemed to have disputed the entire Payment Claim (see sub-s 6(4)CIPAA
[16]NHB, through its solicitors, served the Notice of Adjudi