1. Subcontractor seeks direct payment from principal under Section 30, Construction Industry Payment and Adjudication Act 2012 — Dispute over whether retention sum is due or payable. (Para 1 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 )
2021 MarsdenLR 3685
HIGH COURT (KUALA LUMPUR)
ALIZA SULAIMAN, J
WTK Engineering Sdn Bhd – Plaintiff
Versus
Seriemas Development Sdn Bhd – Defendant
WA-24C-189-09 OF 2020
Important Points
Subject
Construction Law - Adjudication and Payment Disputes
Act Referred
Rules of Court 2012: O.69A, R.2
Income Tax Assessment Act 1936 (Cth): S.218, S.218(1)(i), S.204, S.205, S.206, S.207, S.208, S.170(2), S.170(3), S.170(4), S.170(6)
Corporations Act 2001 (Cth): S.95A
Income Tax Act 1967: S.23, S.24, S.28
Headnote
(B) Construction Law - Retention Sums - Where a construction contract stipulates a condition precedent for the release of the second moiety of a retention sum, such as the issuance of a Certificate of Making Good Defects, the sum is not "due or payable" until that condition is satisfied. (Paras 48, 52, 53)
Facts of the case:
A subcontractor sought to enforce an adjudication decision against a principal by requesting direct payment of an adjudicated amount, including the second moiety of a retention sum. The principal resisted the application, contending that the second moiety of the retention sum was not "due or payable" because the required Certificate of Making Good Defects and the subsequent Architect's certificate had not been issued under the terms of the governing construction contract.
Findings of Court:
The court found that under the relevant construction contract, the second moiety of the retention sum only becomes "due" upon the issuance of the Certificate of Making Good Defects and "payable" once the Architect's certificate is issued. Since neither certificate had been issued at the time the request for direct payment was received, the sum was not "due or payable" by the principal to the main contractor.
Issues: The main issues were the meaning of the phrase "due or payable" in sub-s 30(5) of the Construction Industry Payment and Adjudication Act 2012 and whether the second moiety of a retention sum is "due or payable" in the absence of a Certificate of Making Good Defects.
Ratio Decidendi: The court ruled that "due" and "payable" in s 30(5) of the Act are distinct, disjunctive terms. A sum is not "due or payable" if the contractual conditions precedent for its release have not been met. Consequently, retention money subject to the issuance of a certificate for making good defects cannot be claimed for direct payment until such certificate is issued.
Result: Application dismissed with costs.
Legal Category Hierarchy
-
construction law
- payment disputes
- contract law
Clarence Hing Ying Hui (Candice Shih Yuh Ru with her) (Jason Ng & Partners) for the applicant.
Idza bt Ahmad Idzam (Nan Muhammad Ridzan bin Rosnan and Mohammed Mifzal Mohd Murshid Kieron with her) (Zul Rafique & Partners) for the defendant.
Table of Contents
2. Whether the phrase due or payable in Section 30(5), CIPAA includes sums subject to contractual conditions precedent — Interpretation of retention sum payment triggers. (Para 20 , 21 , 22 , 23 , 24 , 25 , 42 )
3. Analysis of disjunctive term or in Section 30(5), CIPAA — Distinction between debt accrual and immediately enforceable payment obligations under construction contracts. (Para 18 , 19 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 41 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 )
4. Money is due or payable under Section 30(5), CIPAA only if it is owed as a debt or there is an immediately enforceable obligation to pay. (Para 40 , 52 )
5. Application for direct payment dismissed with costs. (Para 3 , 54 )
6. What is the interpretation of the phrase 'due or payable' under Section 30(5) of CIPAA?
The terms are read disjunctively. 'Due' signifies money owed as a debt, whereas 'payable' refers to money that has fallen due for payment, creating an immediately enforceable obligation to pay. (Para 37 , 40 )
7. Does a retention sum constitute money 'due or payable' for direct payment purposes if contractual conditions are unmet?
No. If the contract requires a condition precedent, such as the issuance of a Certificate of Making Good Defects, the retention sum is not due or payable until that condition is fulfilled. (Para 41 , 48 , 52 , 53 )
8. What is the legal distinction between a debt being 'due' and being 'payable'?
A debt is 'due' the instant it exists as a legal obligation to pay, but it may only become 'payable' at a future date specified by the contract or law. (Para 30 , 39 )
Aliza Sulaiman J:
GROUNDS OF JUDGMENT
Introduction
[1] In this application by the Applicant, WTK Engineering Sdn. Bhd. (‘WTK’) pursuant to s 30Construction Industry Payment and Adjudication Act 2012 [Act 746] (‘CIPAA’); O. 69A, r. 2 of the Rules of Court 2012 (‘RoC 2012’); and/ or the discretion of the Court, the issues which arose for consideration were -
(a)on the meaning of the phrase “due or payable” in sub-s 30(5)CIPAA
(b)whether the 2nd moiety of the retention sum is due or payable by the Respondent, Seriemas Development Sdn. Bhd. (‘Seriemas’) as the principal, to PA Builders Sdn. Bhd. (‘PAB’) at the time when Seriemas received the notice from WTK for the adjudicated amount in the Adjudication Decision dated 4.11.2019 (‘Said AD’) to be paid directly by Seriemas to WTK.
[2] The cause papers for this application are as follows:
(a)WTK’s Originating Summons (‘O.S.’) dated 18.9.2020 (encl. 1);
(b)WTK’s Affidavit In Support (‘AIS’) affirmed by its Director of Operations, Ng Nyok Kong on 18.9.2020 (encl. 2);
(c)Seriemas’s Affidavit In Reply (‘AIR’) affirmed by its Assistant Vice President, Saiful Bin Ibrahim on 15.10.2020 (encl. 4);
(d)WTK’s AIR affirmed on 28.10.2020 (encl. 5);
(e)Seriemas’s 2nd AIR affirmed on 10.11.2020 (encl. 6); and
(f)WTK’s AIR (2) affirmed on 26.11.2020 (encl. 7).
[3] Having read the above said cause papers and written submissions filed and upon hearing the oral submissions by Ms. Clarence who appeared for WTK and Ms. Idza Hajar representing Seriemas on 18.1.2021, the Court had dismissed WTK’s application with costs of RM4,000.00, subject to allocator.
[4] The main reason for the decision is basically that this Court is in agreement with Seriemas’s submission as to the interpretation of the words “due or payable” in sub-s 30(5)CIPAA
Background Facts
[5] PAB was awarded the contract for the construction and completion of the project known as “Cadangan Membuat 168 Unit Rumah Bandar (Town House), 1 Unit Pondok Pengawal, 1 Unit Pejabat Urusan Dan 1 Unit Pencawang Elektrik Double Chamber, Fasa 2 Di Atas Lot PT476 (PT13 Laman Cempaka) Kota Seriemas, Bandar Baru Kota Sri Mas, Daerah Seremban, Negeri Sembilan” (‘Project’) by Seriemas Development Sdn. Bhd. upon the terms and conditions as contained in the Letter of Award dated 12.1.2016.
[6] Seriemas and PAB had agreed to adopt the “Agreement And Conditions Of PAM Contract 2006 (Without Quantities)” (‘PAM Contract’) to govern their relationship in relation to the Project.
[7] By way of a “Sub-Contract Agreement for Sub-Labour And Materiaf dated 15.1.2016 (‘Sub-Contract’), PAB appointed WTK as its subcontractor to supply all labour and material to execute and complete all piling works for the Project for the sum of RM1,241,418.80 within two months from the commencement date of 15.2.2016. The Sub-Contract was signed by WTK’s Director on 13.7.2016.
[8] Subsequently, payment disputes between WTK and PAB in connection with the Sub-Contract resulted in the commencement of adjudication proceedings by WTK against PAB where WTK claimed that the total unpaid value of works done until the date of the Payment Claim of 4.7.2019 was RM393,036.28.
[9] On 4.11.2019, the learned Adjudicator, Ir. Ang Kok Keng delivered the Said AD whereby PAB was directed to pay WTK the following amounts on or before 18.11.2019:
(a)RM358,240.45, being the Adjudicated Amount;
(b)interest at the rate of 5% per annum on the Adjudicated Amount from 19.11.2019 until full payment;
(c)RM15,404.86 being the costs of the adjudication proceedings; and
(d)RM13,000.00, being the party to party cost.
[10] WTK had served the Said AD on PAB but no payments were made by PAB to WTK.
[11] On 3.6.2020, Seriemas received the notice to request for direct payment pursuant to s 30CIPAA(‘Request’).
[12] By way of letter dated 26.6.2020, Seriemas informed WTK that it was served with a notice from PAB on 22.6.2020 to stop Seriemas from making any payment directly to WTK without an order from the High Court under s 28CIPAA
[13] WTK replied to Seriema