1. Subcontractor seeks direct payment from Principal under Section 30, CIPAA, following an Adjudication Decision against a Main Contractor currently undergoing winding up. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 11 , 12 , 13 , 39 , 53 , 55 )
2018 MarsdenLR 1914
HIGH COURT (KUALA LUMPUR)
LEE SWEE SENG, J
CT Indah Construction Sdn Bhd – Plaintiff
Versus
BHL Gemilang Sdn Bhd – Defendant
ORIGINATING SUMMONS NO WA-24C-7–01 OF 2017
Important Points
Subject
Construction Law - Adjudication and Insolvency
Act Referred
Companies Act 1965: S.218, S.176, S.219(2), S.223, S.224, S.293
Companies Act 2016: S.528
Bankruptcy Act 1967: S.52, S.53, S.53(1)
Employees Provident Fund Act 1991: S.65(1)
Interpretation Acts 1948 and 1967: S.18(2)
Companies Ordinance (Cap 32): S.182
Companies Act (Cap 50, 1988 Rev Ed): S.280(1), S.327(2)
Companies Act 1948: S.302
New Zealand companies legislation: S.292(1)
Headnote
(B) Insolvency Law - Prohibition of preferential payments - When a company is in liquidation, the principle of pari passu distribution among unsecured creditors prevails (Paras 66, 88, 110). Any payment made to a specific creditor that improves its position vis-à-vis other creditors after the commencement of winding-up proceedings is void as an undue preference (Paras 74, 87, 104).
(C) Enforcement of Adjudication Decisions - A party may exercise remedies under sections 28, 29, and 30 of the construction payment act concurrently (Para 35). However, the right to direct payment under section 30 is extinguished once a winding-up petition is presented against the contractor, as the debt becomes part of the company's assets for distribution among all creditors (Paras 109, 110).
Facts of the case:
A subcontractor obtained an adjudication decision against a main contractor. Following the main contractor's failure to pay the adjudicated sum, the subcontractor sought a declaration that the developer, acting as the principal, was liable to make direct payment of the amount under the relevant construction payment statute. The main contractor had been served with a statutory demand and was subject to winding-up proceedings at the time the application for direct payment was pursued.
Findings of Court:
The court found that the direct payment provision does not create a separate and independent obligation to pay that exists regardless of the contractor's insolvency. Because the payment would reduce the assets available for the general body of creditors, it would constitute an undue preference.
Issues: Whether the direct payment remedy under Section 30 of the Construction Industry Payment and Adjudication Act 2012 is subject to the prohibition of preferential payment under the Companies Act when the contractor is in liquidation.
Ratio Decidendi: The court ruled that the construction payment act does not contain express language or a non obstante clause to override the insolvency regime. The direct payment remedy is contingent upon money being due from the principal to the contractor; therefore, such sums are assets of the contractor. Upon the commencement of winding-up, the pari passu principle ensures that assets are distributed equally among unsecured creditors. Allowing direct payment to a subcontractor would bypass this legal requirement and constitute an undue preference under the Companies Act.
Result: Application dismissed with costs of RM10,000.00 awarded to the defendant.
Legal Category Hierarchy
- construction law
- company law
- practice and procedure
JL Foo (TW Teoh with him) (Gan Partnership) for the plaintiff.
Wong Rhen Yen (Siti Mardhiyyah with him) (Dennis Nik & Wong) for the defendant.
Table of Contents
2. Plaintiff contends Section 30 creates a mandatory statutory obligation; Defendant argues direct payment is prohibited as a preferential payment under insolvency laws. (Para 11 , 21 , 22 , 23 , 29 , 40 , 45 , 63 )
3. The court found Section 28 enforcement unnecessary for Section 30 but held that statutory direct payment cannot override the pari passu principle in insolvency. (Para 25 , 26 , 27 , 28 , 29 , 31 , 32 , 33 , 35 , 41 , 42 , 46 , 47 , 48 , 52 , 56 , 57 , 58 , 60 , 61 , 62 , 65 , 66 , 67 , 68 , 69 , 70 , 71 , 72 , 73 , 74 , 75 , 76 , 77 , 78 , 79 , 80 , 82 , 83 , 84 , 85 , 87 , 89 , 90 , 91 , 92 , 93 , 94 , 95 , 96 , 97 , 98 , 99 , 100 , 102 , 103 , 105 , 106 , 107 , 108 , 111 , 112 , 113 , 114 )
4. Direct payment under Section 30, CIPAA, cannot supersede insolvency laws prohibiting preferential payments unless an independent statutory or contractual obligation exists. (Para 41 , 47 , 65 , 66 , 81 , 86 , 88 , 104 )
5. Application for declaration of liability for direct payment dismissed with costs. (Para 115 , 116 , 117 )
6. Is a High Court enforcement order under Section 28 CIPAA required before seeking direct payment under Section 30?
No. The court held that Section 30 is a separate remedy for non-payment and does not require a prior application under Section 28 to enforce the adjudication decision as a judgment. (Para 29 , 31 , 32 , 33 , 35 )
7. Does the word shall in Section 30(2) and (3) of CIPAA create an absolute obligation for the Principal to pay?
No. The mandatory nature of shall is subject to Section 30(5), meaning money must be due from the principal to the contractor, and it is further subject to insolvency laws. (Para 26 , 27 , 28 )
8. Can the direct payment remedy under Section 30 CIPAA be invoked if the Main Contractor is in winding up?
Generally no, as it would constitute a preferential payment to an unsecured creditor, violating the pari passu principle of insolvency law, unless an independent obligation to pay exists. (Para 47 , 65 , 66 , 87 , 88 , 104 , 109 , 110 )
9. What constitutes an independent obligation that would allow direct payment despite insolvency?
An independent obligation arises from separate instruments, such as a guarantee, indemnity agreement, or a specific tripartite contract where the principal is liable as a principal debtor. (Para 82 , 83 , 84 , 85 , 94 , 95 )
Lee Swee Seng J:
THE JUDGMENT
[1]The primary question for determination in this application is whether the principal of a contractor against whom an Adjudication Decision has been made, is required to make payments direct to the Claimant under the direct payment remedy provision under the Construction Industry Payment and Adjudication Act 2012 (“CIPAA”) for a debt which the principal owes its contractor.
[2]The Plaintiff was the Subcontractor in a construction project known as “The Mark”. The Defendant as the Developer appointed BHL Builders Sdn Bhd (“BHL Builders”) as the Main Contractor for the Project.
[3]In the Letter of Award dated 28.4.2014 (“the LOA”), the Plaintiff was awarded by BHL Builders the subcontract work of RM43,144,275.98 for the supply, construction and completion of super structure work (“the Subcontract”) as follows:
“Cadangan Membina Pangsapuri Perkhidmatan yang mengandungi:
1.2 Blok Pangsapuri Perkhidmatan dan Kemudahan-kemudahan:
a)Blok A sebanyak 189 Unit Pangsapuri Perkhidmatan dan Kemudahan-kemudahan (21 Tingkat)
b)Blok B Sebanyak 278 Unit Pangsapuri Perkhidmatan dan Kemudahan-Kemudahan (23 Tingkat)
2.1 Blok Podium (8 Tingkat) yang Mengandungi:
a)18 Unit Ruang Retail (Di Sebahagian Aras 1-2)
b)36 Unit Ruang Pejabat (Di Sebahagian Aras 3-4)
c)1 Unit Perpustakaan MPAJ (Di Sebahagian Aras 2)
d)Tempat Letak kereta dan Tempat Letak Motorsikal (Di Sebahagian Aras 1-4 dan Di Aras 5-8)
e)Tempat Letak Kereta Separa Bawah Tanah (Aras Separa Bawah Tanah 1-2)
f)Tempat Letak kereta Bawah Tanah (Aras Bawah Tanah 1-2)
Di Atas Lot PT 12382 dan PT 6571, Taman Bukit Segar, Mukim Ampang, Daerah Hulu Langat, Selangor Darul Ehsan Untuk Tetuan BHL Gemilang Sdn Bhd (“the Project”)”.
[4]The Plaintiff had obtained an Adjudication Decision dated 13.10.2016 in its favour against the Respondent in an Adjudication under the CIPAA.
Problem
[5]As BHL Builders failed to make payment under the Adjudication Decision, the Plaintiff issued and served on 22.11.2016 a statutory demand under the then section 218Companies Act 1965
[6]On 19.12.2016, the Plaintiff served on BHL Builders a Winding Up Petition vide Kuala Lumpur High Court Winding Up Petition No. WA- 28NCC-1063-12/2016 (“the Winding Up Petition”).
[7]There was no application filed by BHL Builders to set aside the Adjudication Decision. BHL Builders has applied to restructure itself under section 176Companies Act 1965
[8]Pursuant to section 30CIPAA
[9]The Defendant did not issue a notice under section 30(2)CIPAAshow proof of payment” to the Plaintiff, or to “state that direct payment would be made after the expiry of ten working dates of the service of the notice”. This is a mandatory requirement under section 30(2)
[10]There was also no response from the Defendant to the Plaintiff.
Prayer
[11]The Plaintiff then filed this application on 17.1.2017 under section 30CIPAAinter alia, a declaration that the Defendant is liable as the principal of BHL Builders Sdn Bhd to pay to the Plaintiff the outstanding amount due under the Adjudication Decision dated 13.10.2016.
[12]The Adjudication Decision was for the principal sum of RM9,065,335.67 (“the Adjudicated Sum”) made in favour of the Plaintiff in addition to a further legal costs of RM20,000.00 and the adjudication costs of RM86,591.82 (“the Legal and Adjudication Cost”) together with interests at the rate of 5% per annum on the Adjudication Sum from 19.7.2016 to 13.10.2016 (“the Adjudicated Amount”).
[13]This was to be paid by 21.11.2016.
Principles
Whether the requirements of direct payment from the Principal to the Claimant under section 30CIPAAhave been met
[14] Section 30 of the CIPAA expressly allows the Plaintiff, as the successful party in the adjudication, to claim payment of the Adjudicated Amount directly from the Defendant as the principal, where BHL Builders, the Respondent in the Adjudication, has failed to make payment.
[15]It is provided under Part IV of the CIPAA under “Enforcement of Adjudication Decision”. The other section is section 28section