1. Dispute over pipeline maintenance project — alleged breach of exclusivity in Master Agreement — application for interim injunction pending arbitration under Section 11, Arbitration Act 2005. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 )
2020 MarsdenLR 2798
HIGH COURT (BINTULU)
DUNCAN SIKODOL, JC
Expro Marine Sdn Bhd – Plaintiff
Versus
Amalgamated Plant Engineering Sdn Bhd – Defendant
ORIGINATING SUMMONS NO BTU-24-7/9 OF 2020 (HC)
Important Points
Subject
Commercial Law - Arbitration
Act Referred
Headnote
(B) An applicant for an interlocutory injunction must provide a valuable undertaking to pay damages and demonstrate the means to fulfill said undertaking, particularly when challenged by the opposing party (Paras 64, 66, 69).
(C) A matter is considered academic if there is no longer an actual controversy affecting the rights and interests of the parties (Para 45).
Facts of the case:
A service provider and a contractor entered into a master agreement for a pipeline maintenance project. A dispute arose when the service provider entered into agreements with third parties without the contractor's consent. The service provider sought injunctive relief to restrain the contractor from terminating the agreement and replacing them, pending the conclusion of arbitration. During the court proceedings, the contractor formally terminated the agreement.
Findings of Court:
The court found that there were bona fide issues to be tried and that damages would not be an adequate remedy. However, the prayers seeking to restrain termination and allow the execution of works became academic after the agreement was terminated. Crucially, the plaintiff failed to provide a valuable undertaking as to damages or prove the financial means to satisfy such an undertaking.
Issues: Whether there were bona fide issues to be tried in arbitration; whether the termination of the agreement rendered the injunctive reliefs academic; and whether a bare undertaking as to damages is sufficient to support an application for an injunction.
Ratio Decidendi: The failure of an applicant to provide a valuable undertaking as to damages and to demonstrate the means to fulfill that undertaking, especially when challenged, is fatal to an application for injunctive relief. Furthermore, prayers for injunctions to prevent an act that has already occurred, such as the termination of a contract, are academic.
Result: Application dismissed with costs.
Legal Category Hierarchy
- practice and procedure
- contract law
Shankar Ram (Thomas, Shankar Ram and Co Advocates) for the defendant.
Table of Contents
2. Plaintiff seeks injunctive relief to maintain status quo; Defendant argues the application is academic following termination and the undertaking as to damages is insufficient. (Para 13 , 14 , 15 )
3. The court found bona fide issues and inadequate damages but noted the termination rendered some prayers academic and the undertaking as to damages was unsupported. (Para 17 , 18 , 19 , 23 , 24 , 27 , 33 , 40 , 44 , 50 , 55 , 56 , 66 , 67 , 68 , 69 )
4. An applicant for an interlocutory injunction must provide a valuable undertaking to pay damages and demonstrate the financial means to fulfill that undertaking. (Para 64 , 66 , 69 )
5. Application for injunctive relief dismissed with costs. (Para 70 , 71 )
6. What is the requirement for an applicant seeking an interlocutory injunction regarding the undertaking as to damages?
The applicant must provide a valuable undertaking to pay damages and demonstrate they have the financial means to fulfill that undertaking, especially when challenged by the opposing party. (Para 64 , 66 , 67 , 68 , 69 )
7. When does an application for an injunction to restrain termination become academic?
An injunction to restrain termination becomes academic and redundant if the contract has already been terminated before the court grants the order, provided no ex-parte interim injunction was obtained. (Para 35 , 40 , 44 , 55 )
8. What are the general principles for granting an interim injunction pending arbitration?
The court considers whether there is a bona fide serious issue to be tried, where the justice of the case lies, and whether the status quo ought to be maintained. (Para 10 )
9. When are monetary damages considered inadequate for the purpose of granting an interlocutory injunction?
Damages are inadequate when the loss involves non-monetary factors such as loss of goodwill, trade reputation, or potential termination of a primary contract by a third party. (Para 22 , 23 , 24 )
Duncan Sikodol JC:
GROUNDS OF JUDGMENT
[1]Based on the Originating Summons (Encl.1) the Plaintiff had applied, inter-alia, for the following injunctive orders/reliefs: -
(1)An Order restraining the Defendant, whether by itself or through its directors, employees’, servants, representatives and/or agents or otherwise howsoever, from terminating and/or attempting to terminate the Master Agreement dated 23.9.2019 made between the Plaintiff and the Defendant (“the Master Agreement”) in relation to the maintenance of mechanical pipelines known as the Sabah-Sarawak Gas Pipeline or in short, SSGP (“the Project”) pending the full and final conclusion of the arbitration proceedings.
(2)An Order restraining the Defendant, whether by itself or through its directors, employees’, servants, representatives and/or agents or otherwise howsoever, from replacing the Plaintiff in the execution of the works for the Project contrary to the Master Agreement and/or executing the works for the Project without the involvement and consent of the Plaintiff and/or entering into any agreement with any 3rd party for the execution of the works for the Project contrary to the Master Agreement pending the full and final conclusion of the arbitration proceedings.
(3)An Order that the Defendant, whether acting by itself or by its directors, employees’, servants, representatives and/or agents or otherwise by any way whatsoever, within seven (7) days from the service of this Order, disclose to the Plaintiff by way of sworn affidavit the particulars of all contracts and/or agreements and/or consortiums, written or otherwise, entered into by the Defendant with any 3rd party other than the Plaintiff in relation to the Project and/or in relation to the financing of the Project; and
(4)An Order that the Plaintiff is expressly allowed to execute the works for the Project in accordance with the terms of the Master Agreement pending the full and final conclusion of the arbitration proceedings.
(5)Nothing in this Order shall prevent the Defendant from its normal business and operational obligations under the Letter of Award and/or the Master Agreement.
Brief Facts
[2]The material brief facts of this case are, inter-alia, as follows: -
(a)The Plaintiff is an integrated oil & gas and petrochemicals service provider who specializes in pipeline & integrated facilities maintenance, offshore and onshore facilities transportation and installation, underwater service (Diving & ROV), training, fabrications and engineering company.
(b)The Defendant is a company involved in general contract works and amongst others, possesses licenses and registrations required for pipeline maintenance works. Among the registration owned by the Defendant is the registration with the Department of Occupation Safety and Health (the “DOSH Registration”).
(c)The subject matter of the dispute in this case is related to a project awarded by Petronas to the Defendant via a Letter of Award dated 12/12/2019 under Tender No. DTC- BTU/PBF/2019/32 (the “Letter of Award”) for the maintenance of mechanical pipelines known as the Sabah- Sarawak Gas Pipeline Project, SSGP (“the Project”).
(d)That before bidding for the Project, the Plaintiff and the Defendant had jointly executed a Sub-Contracting Declaration stipulating certain understandings between the parties in the event the Defendant is successful in bidding for the Project (see exhibit A-1).
(e)Subsequently the Defendant received an invitation from PETRONAS to bid for the Project (the “Invitation Bid”) by way of open tender.
(f)The Plaintiff and the Defendant had jointly executed a Master Agreement dated 23/09/2020 (the “Master Agreement”) (see Exhibit A-2)
(g)Eventually, the Defendant succeeded in obtaining the bid and was thereafter awarded the works of the said Project via the Letter of Award (see Exhibit A-3)
(h)Thereafter, the Defendant executed a back-to-back Letter of Award dated 01/01/2020 assigning the works of the Project to the Plaintiff and further incorporated t