SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 MarsdenLR 97561 ; 2026 MarsdenLR 98136

HIGH COURT MALAYA MELAKA
RAJA SEGARAN S KRISHNAN, JC
FIRST RELIANCE TARGET SDN BHD – Appellant
Versus
PLANETARIUM MELAKA SDN BHD – Respondent
[Originating Summons No: MA-24NCvC-399-09/2025]



Petitioner Advocates:Joshua Kevin Sathiaseelan,Intan Maisarah Mohd Khir ,Respondent Advocate: Lim Tse Hwei,Jacelyn Heng Yi Zo

A binding agreement requires absolute and unqualified acceptance; silence alone is insufficient. When a contract provides specific machinery for termination and financial consequences, parties cannot circumvent these terms by invoking general restitutionary principles or non-contractual doctrines like frustration without satisfying the requisite foundational elements.

Headnote:(A) Contracts Act 1950 - Section 7 - Acceptance of a proposal must be absolute and unqualified - Acceptance coupled with condition does not amount to a valid contract. (Paras 22, 23, 31)

(B) Contracts Act 1950 - Section 6(b) - Revocation of proposal occurs by lapse of stated time for acceptance or a reasonable time. (Para 24)

(C) Contracts Act 1950 - Section 57(2) - Doctrine of frustration - Requires event not provided for in the contract, absence of responsibility, and fundamental change in performance - Commercial difficulty or delay does not constitute frustration. (Paras 68-71)

(D) Civil Procedure - Originating Summons - Order 5 Rule 4(1)(b) - Requires absence of substantial factual dispute - Inappropriate for complex contractual claims involving contested breaches and evidentiary proofs. (Paras 15, 17, 20)

Facts of the case:
The parties entered into a privatization agreement regarding site rehabilitation and operations. Disputes arose over project delays, regulatory approvals, and land premiums. One party proposed a mutual termination through correspondence, enclosing a draft agreement subject to revisions. The other party did not respond, and subsequently initiated legal proceedings via originating summons seeking declarations of valid termination and monetary relief for alleged expenditures.

Findings of Court:
The court found that the correspondence regarding termination lacked the finality required for a binding agreement as it explicitly remained subject to further amendments. The doctrine of frustration was inapplicable as the project challenges fell within the scope of contractual risks and responsibilities. The originating summons was considered an inappropriate mode for resolving complex factual disputes regarding breach and restitutionary claims.

Issues: Whether the correspondence constituted a binding mutual termination; whether the contract was frustrated; whether the monetary claims were sustainable on the current record; and whether contractual dispute resolution mechanisms were a mandatory bar to litigation.

Ratio Decidendi: A binding contract or termination requires absolute and unqualified acceptance; silence does not constitute acceptance unless accompanied by conduct clearly referable to agreement. Furthermore, contractual mechanisms for termination and compensation cannot be circumvented by invoking general restitutionary principles when the factual and legal basis for termination has not been established.

Result: Originating summons dismissed.

JUDGMENT

Raja Segaran S Krishnan JC:

A. Introduction

[1] This is the Court 's judgment in respect of the Originating Summons in Enclosure 1 filed by First Reliance Target Sdn Bhd against Planetarium Melaka Sdn Bhd The application arises out of a Privatization Cum Concession Agreement dated 13 September 2019 concerning the rehabilitation, management and operation of the Melaka Planetarium Adventure Science Centre.

[2] The immediate controversy is not whether the project encountered difficulties. That much is common ground. The real controversy is whether those difficulties culminated in a legally effective termination in the manner alleged by the plaintiff, and whether the Plaintiff is thereby entitled, by originating summons, to declaratory relief together with monetary relief for RM1,000,000.00 and RM3,560,845.82.

[3] The Plaintiff's case is built principally on the defendant's solicitors' letter dated 30 September 2024 and on the plaintiff's silence thereafter. The Plaintiff says that the letter, read together with the prior dealings between the parties, brought about a valid mutual termination and rendered the draft Mutual Termination Agreement effective. The Defendant denies that any concluded mutual termination agreement ever came into existence and maintains that the draft remained unsigned and subject to revision.

[4] The Defendant also raises threshold objections. It says the present action is premature by reason of cl 16 of the Privatization Cum Concession Agreement and that, in any event, the reliefs sought are inconsistent with the contractual regime governing termination and its consequences.

[5] In my judgment, the dispositive issue is narrower than the breadth of the parties' affidavits might suggest. The central question is whether, on the true construction of the contractual documents and correspondence relied upon, the Plaintiff has established a legally binding mutual termination or other legally effective termination entitling it to the declarations and monetary relief sought.

B. Material Facts And Procedural History

[6] By the Privatization Cum Concession Agreement dated 13 September 2019, the Defendant granted the plaintiff rights in relation to the proposed privatization of the Planetarium. The agreement contemplated that the Plaintiff would redesign, renovate, construct, execute and do all other things necessary for completion of the privatization, while the Defendant undertook, among other things, to assist with approvals, facilitate occupancy arrangements for a Tourism One Stop Centre, and hand over vacant possession subject to the agreement. The agreement also contained provisions on termination, consequences of termination, dispute resolution, waiver and time of essence.

[7] On 24 September 2019, a Revocable Power of Attorney was executed by the defendant in favour of the plaintiff.

[8] The documentary record shows that, by late 2019 and throughout 2020 to 2022, issues arose in relation to governmental space requirements for the proposed Tourism One Stop Centre, the proposed Snow World component, and the alienation premium for the land. The Plaintiff requested assistance on agency requirements. The Defendant's materials show that requirements from agencies were forwarded and that letters were subsequently issued concerning the land premium and payment schedule. The Plaintiff, for its part, maintained that construction could not proceed because of Snow World occupation, absence of confirmations from agencies, and non-reduction of land premium.

[9] By letter dated 29 July 2022, the Plaintiff asserted that it had undertaken preparatory works, listed various categories of expenditure, stated that the project could not continue, and demanded return of RM1,000,000.00 together with reimbursement of RM3,560,845.82 within 14 days. The letter attributed the inability to proceed to three matters, namely Snow World occupation, non-confirmation by government agencies for the Tourism One Stop Centre, and non-reduction of lan

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top