JUDGMENT

Abdul Aziz Mohamad J:

This is the plaintiffs' appeal against the dismissal by the learned senior assistant registrar of their application for summary judgment against the second and third defendants ('the defendants').

The defendants have raised in this appeal several issues through the written submission of their solicitors.

Rate Of Interest

The plaintiffs' letter of offer specified, in respect of the trust receipt facility, a rate of interest of 2275% over their base lending rate of 10.75%. In para. 4 of the letter of offer, however, the plaintiffs reserved the right to vary the rate of interest. The plaintiffs seek final judgment in the sum of RM98,164.50 in respect of the trust receipt facility, with further interest at 3% above the base lending rate from 1 July 1991 until full settlement.

The defendants complain that the interest claimed is excessive and ambiguous and that the exact amount of it cannot be quantified.

I do not see that the interest is excessive.

For saying that the interest rate is ambiguous and that the amount of interest cannot be quantified, the defendants rely on Tuan Haji Ahmed Abdul Rahman v. Arab-Malaysian Finance Berhad[1995] 2 MLRA 155; [1996] 1 MLJ 30; [1996] 1 CLJ 241; [1996] 1 AMR 215. That was a case where the Federal Court held that the judgment was riddled with uncertainties serious enough to render it an irregular judgment. Here, however, there are no such uncertainties in the judgment sought in respect of the trust receipt facility. Moreover, the interest rate is not ambiguous and the interest can be quantified.

Limitation

The defendants raise s. 6(3) of the Limitation Act 1953 against the interest claimed by the plaintiffs, complaining that the plaintiffs have not stated "the period from which the rate of interest begins".

Section 6(3) does not apply in this case. It is about recovery of arrears of interest in respect of a judgment debt. The present case is not a case of recovery of interest in respect of a judgment debt. There is yet no judgment debt in respect of which one can think of recovering interest. The question under s. 6(3) will only arise in this case if, after obtaining judgment against the defendants, the plaintiffs should delay for the prescribed limitation period in taking action to recover the judgment sum and the interest on it.

Performance Bond

Part of the plaintiffs' claim against the defendants is a sum paid by the plaintiffs on a performance bond, which was one of the facilities provided by the plaintiffs to the first defendants, who were the nominated subcontractor for a certain project. By cl. (1) of the performance bond, the plaintiffs guaranteed to the main contractor the due performance by the first defendants of the subcontract, and by cl. (2) the plaintiffs agreed that upon default by the first defendants on the subcontract they would forthwith, on demand in writing, pay the main contractor the guaranteed sum.

The defendants contend that the plaintiffs should not have paid the guaranteed sum because there was no default on the part of the first defendants.

I agree with learned counsel for the plaintiffs that as the plaintiffs' obligation was to pay the main contractor on the performance bond on demand, the plaintiffs were not obliged to have the default established before their obligation to pay the main contractor could arise. It was sufficient that they be told by the main contractor when making the demand that the first defendants had defaulted. If, by the plaintiffs' paying under the performance guarantee the first defendants became indebted to the plaintiffs when in fact they had not defaulted, they could have recourse to the main contractor.

In para. 6 of their affidavit dated 27 August 1993, the defendants, as if to justify the contention they would be making and have now made that there had been no default on the part of the first defendants, pointed out that the main contractor themselves had admitted that the termination of th

1
2
3
4
5
6
7
8
9
10
11