IA(IBA)/87/KOB/2021
In
IBA/23/KOB/19
Page 1 of 7
THE NATIONAL COMPANY LAW TRIBUNAL
KOCHI BENCH, KOCHI
IA(IBA)/87/KOB/2021
In
IBA/23/KOB/19
(Under Section 33(1(a))of IBC, 2016)
Order delivered on 25.11.2021
Coram:
1. Hon’ble Shri Ashok Kumar Borah, Member (Judicial)
2. Hon’ble Shri Anil Kumar B., Member (Technical)
Applicants/Intervenors
Shri Vinod PadinhareVeetil,
Resolution Professional of
Dewa Projects Pvt Ltd
66-1058, First Floor,
Veekshanam Road,
Ernakulam 682 018.
Vs.
Impleaded Respondent (Vide order dated 27.10.2021)
Union Bank of India,
(Leader of the Consortium of lenders of Dewa Projects Pvt Ltd.),
Union Bank Bhawan,
Opposite Shenoys Theatre,
MG Road, Ernakulam 682 035
Represented by its Assistant General Manager Mr. Balakrishna A Bhat
In the matter of
Rita Venugopal & another ] Financial Creditor
Vs.
Dewa Projects Pvt ltd
] Corporate Debtor
Parties/Counsels Present:
For Applicant s
:RP Shri Vinod PV appeared in person
For Respondent
: Shri Nidhi Sam John, Advocate
IA(IBA)/87/KOB/2021
In
IBA/23/KOB/19
Page 2 of 7
Per: Ashok Kumar Borah, Member (J)
1. This order has arisen out of the IA filed under Section 33(1)(a) of IBC, 2016
by the Resolution Professional for liquidation of the Corporate Debtor Dewa
Projects Pvt Ltd.
2. This Tribunal vide order dated 13.09.2019 admitted the IBA/23/KOB/2019
filed under Section 7 of the Insolvency and Bankruptcy Code, 2016 and
appointed the Applicant as the Interim Resolution Professional and later the
Committee of Creditors confirmed the IRP as Resolution Professional (RP).
3. The Resolution Professional submitted that he invited expression of interest
on 21.12.2019 through advertisement, however there was no response to the
said advertisement. Accordingly, further revised Expression of Interest
through advertisement was given in newspapers. Further to the publication of
revised EOI, the Resolution Professional has contacted various real estate
developers, who were holding adjacent lands to the Project of the Corporate
Debtor. In response to the advertisement, Lulu Infra Build Pvt Ltd expressed
their interest to submit Resolution Plan on 12.2.2020. Accordingly, the
Resolution Professional has issued request for resolution plan to Lulu Infra
Build Pvt Ltd on 28.2.2020. Thereafter, M/s. Lulu Infrabuild Private Limited
submitted a Resolution Plan with a Resolution Amount of Rs.110 Crore which
was much below the liquidation value of Rs.140.25 Crore and the Resolution
Plan and that it was also complex as it was proposing a merger of the
IA(IBA)/87/KOB/2021
In
IBA/23/KOB/19
Page 3 of 7
Corporate Debtor with its subsidiary and extinguishment shares of the
subsidiary. The members of Committee of Creditors (CoC) sought time to take
their internal approvals as in view of lock down they were not in a position to
take immediate decision in the Plan and instructed the RP to seek the
indulgence of this Tribunal for extension of time.
4. Based on further negotiation done by the CoC, the Resolution Applicant M/s.
Lulu Infrabuild Private Limited enhanced the value by another 2.60 Crore,
however reserving their right to use Rs.2 Core to meet any contingency
expenses which arises during the implementation of the plan. The members
of the CoC discussed the Plan in various meetings, however they could not
reach a consensus on the approval of the Plan including distribution of money
among Financial Creditors and Home Buyers. On 17.03.2021, the Resolution
Applicant M/s. Lulu Infrabuild Private Limited again revised theResolution
Plan and enhanced the Resolution Amount from Rs.112.60 Crore to Rs.
113.35 Crore. This plan proposed 88 Crore to FC and principal dues to the
Home Buyers. In order to review of the Plan, the CoC instructed RP to seek
the indulgence of this Tr