2021 Supreme(SRI)(SC) 386
IN THE SUPREME COURT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA Sri Lanka Mahaweli Authority, No. 500, T.B. Jaya Mawatha, Colombo 10.
Plaintiff SC APPEAL NO: SC/APPEAL/101/2017 SC LA NO: SC/HCCA/LA/26/2017 HCCA ANURADHAPURA NO: NCP/HCCA/ARP/1076/2016 DC POLONNARUWA NO: 14798/M/12 Vs.
Dharshani Construction, No. 42, Pothgull Road, Polonnaruwa.
Under the sole ownership of Amarasiri Masakorala, No. 18, Habarana Road, Polonnaruwa.
Defendant AND BETWEEN Sri Lanka Mahaweli Authority, No. 500, T.B. Jaya Mawatha, Colombo 10.
Plaintiff-Appellant Vs.
Dharshani Construction No. 42, Pothgull Road, Polonnaruwa.
Under the sole ownership of Amarasiri Masakorala, No. 18, Habarana Road, Polonnaruwa.
Defendant-Respondent AND NOW BETWEEN Dharshani Construction, No. 42, Pothgull Road, Polonnaruwa.
Under the sole ownership of Amarasiri Masakorala, No. 18, Habarana Road, Polonnaruwa.
Defendant-Respondent-Appellant Vs.
Sri Lanka Mahaweli Authority, No. 500, T.B. Jaya Mawatha, Colombo 10.
Plaintiff-Appellant-Respondent Before: Murdu Fernando, P.C., J.
Achala Wengappuli, J.
Mahinda Samayawardhena, J.
Counsel: Senaka De Saram for the Defendant-Respondent-
Appellant.
Rajitha Perera, S.S.C., for the Plaintiff-Appellant-
Respondent.
Argued on : 05.07.2021 Written submissions:
by the Defendant-Respondent-Appellant on
14.07.2017.
by the Plaintiff-Appellant-Respondent on
16.08.2017.
Further written submissions:
by the Plaintiff-Appellant-Respondent on
14.07.2021.
Decided on: 15.10.2021 Mahinda Samayawardhena, J.
The plaintiff Mahaweli Authority and the defendant contractor entered into a written agreement marked P2 to make improvements to the spillway and tail canal of the Pimburattewa tank in the Polonnaruwa District. In terms of clause 59.2(a) of the agreement, the plaintiff terminated the agreement by letter dated 01.03.2006 marked P10 on the basis that the defendant had stopped work for more than 28 days without authorisation.
Clauses 59.1 and 59.2(a) of the agreement read as follows: 59.1 The employer or the contractor may terminate the services under the contract if the other party causes a fundamental breach of the contract.
59.2(a) Fundamental breach of contract shall include, but shall not be limited to, the contractor stops work for 28 days when no stoppage of work is shown on the current program and the stoppage has not been authorised by the engineer.
By letter P10 the plaintiff also informed the defendant that in terms of clause 60.1 of the agreement steps would be taken to decide on “the payment upon termination and completion of the balance work of the contract.” Clause 60.1 reads as follows:
If the services of the contractor under the contract is terminated because of a fundamental breach of contract by the contractor, the engineer shall issue a certificate for the value of the work done and materials ordered less advance payments remaining to be recovered at up to the date of the issue of the certificate and less the percentage to apply to the value of the work not completed. Additional liquidated damages shall not apply. If the total amount due to the employer exceeds any payment due to the contractor, the difference shall be a debt payable to the employer.
Clause 60.1 shall be read with “Contract Data” as agreed upon by the parties which states “The percentage to apply to the value of the work not completed, representing the employer’s [plaintiff’s]
additional cost for completing the works, is 25%.”
P10 further stated that the defendant would be informed of when he would be required to be present at the site for the final measurements in order to prepare the final payment bill subsequent to termination.
Notwithstanding the defendant was informed of the date, he was not present at the site inspection. The summary of the final payment prepared ex parte is marked P12, whereby it was calculated that the value of 25% of the incomplete work of the defendant in terms of clause 60.1 of the agreement is Rs.
2,150,000.
Thereafter by the letter of demand dated 26.04.2006 marked P