DHARSHANI CONSTRUCTION VS. SRI LANKA MAHAWELI AUTHORITY
2021 SLR 2 373
DHARSHANI CONSTRUCTION
Vs.
SRI LANKA MAHAWELI AUTHORITY
SUPREME COURT
FERNANDO, J.
WENGAPPULI, J.
SAMAYAWARDHENA, J.
SC/APPEAL/101/2017
SC/HCCA/LA/26/2017
NCP/HCCA/ARP/1076/2016
DC POLONNARUWA 14798/M/12
JULY 5, 2021
Contract-Violation and termination of the contract-Accrual of a cause of
action-Prescription Ordinance, section 6-When does prescription begin to run-
Technical cause of action and practical cause of action Liquidated damages
The plaintiff Mahaweli Authority and the defendant contractor entered into a written agreement to make improvements to a tank. In terms of clause 59.2(a) of the agreement, the plaintiff terminated the agreement by letter dated 01.03.2006 on the basis that the defendant had stopped work for more than 28 days without authorisation, which is a fundamental breach of the contract. By the same letter the plaintiff also informed the defendant that in terms of clause 60.1 of the agreement, steps would be taken to decide on payment upon termination and completion of the remaining work under the contract. The letter further states that the defendant would be informed of the date to be present at the site for the final measurements in order to prepare the final payment bill subsequent to termination. However the defendant was not present at the site inspection and the final bill was prepared ex parte. Thereafter by letter of demand dated 26.04.2006 the plaintiff demanded the sum as per the final bill from the defendant. The defendant failed to make payment and the plaintiff filed action against the defendant in the District Court on 24.04.2012 seeking to recover the said sum with legal interest. After trial, the District Court dismissed the plaintiff's action on the basis that the action was prescribed in terms of section 6 of the Prescription Ordinance, as it had not been instituted within six years of the date of termination of the agreement. The High Court of Civil Appeal set aside
the judgment of the District Court on the basis that the cause of action accrued
to the plaintiff against the defendant on the date the demand was made and, as
the action was filed within six years of the date of the demand, the action was
not prescribed in terms of section 6 of the Prescription Ordinance. The
defendant appealed to the Supreme Court.
Held:
1. What is prescribed after a lapse of six years in terms of section 6 of the
Prescription Ordinance is the cause of action. The cause of action that accrued
to the plaintiff is the recovery of the value of
25% of the incomplete work calculated in a sum of Rs. 2,150,000 in terms of
clause 60.1 of the agreement. This sum was not paid despite a demand made by the
letter dated 26.04.2006.
2. An agreement can give rise to several causes of action at different stages.
The termination of the agreement under clause 59 gave rise to a technical cause
of action but nothing flows from it. It is the next step set out in clause 60
that gives rise to a practical cause of action to either party. What is relevant
is the breach of the agreement giving rise to a cause of action contemplated by
section 6 of the Prescription Ordinance. The question at what point such a
breach takes place depends upon the facts of the particular case.
3. In order for clause 60.1 to apply, the engineer shall prepare the final bill
after the site inspection with the participation of the defendant. This is not
possible at the termination of the agreement in terms of clause 59.1 although
clause 59.1 is finked to clause 60.1.
4. The argument of the defendant would have succeeded if liquidated damages was
the remedy the parties agreed upon after the breach of the agreement leading to
its termination. n such an event, there is no further step to be taken to
calculate damages as the parties have already agreed on pre-determined damages
at the time of entering into the contract. Clause 60.1 expressly provides that
apart from the calculated