COLOMBO HOTELS CO. LTD. v. MOOTOOMULL
NLR21V385
[PRIVY COUNCIL]
Present: Earl Loreburn, Lord Atkinson, Lord Scott Dickson,
and
Sir Arthur Channell.
COLOMBO HOTELS CO., LTD. v. MOOTOOMULL et al.
Agreement to enter into a lease when new buildings are completed- Outside
evidence led to show what was meant by nets buildings- Evidence Ordinance, s.
92.
The plaintiffs entered into an agreement with the defendants by which the
defendants agreed to accept a lease of a shop. The period of lease was to
commence " from the date when the new buildings are completed and the shop is
occupied." The plaintiffs resolved to rebuild the hotel in three sections, and
the shop in question was in section No. 2. The defendants entered into
occupation of the shop some time after it was completed, but thereafter the
plaintiffs intimated that they had definitely abandoned the erection of section
No. 3. The defendants when called upon to enter into the lease refused to do so
as the new buildings had not been completed.
The plaintiffs sued for damages. The Court allowed evidence to be led to explain
what was meant by " new buildings, " and on the evidence it was held that the
words " new buildings " meant the entire buildings, and not only section No. 2.
THE
facts appear from the judgment.
June 10, 1918. Delivered by LORD SCOTT DICKSON: -
The plaintiffs (respondents) in this case are the owners of the Grand Oriental
Hotel, Colombo. The defendants (appellants) are shopkeepers in Colombo, who for
many years before the present dispute arose occupied as tenants business
premises in the said hotel.
In 1910 the respondents resolved to rebuild their whole hotel, and they
approached the appellants with the view of their taking a lease of premises in
the new hotel buildings about to be erected.
After somewhat protracted negotiations the parties signed an agreement dated
March 3, 1913, by which the appellants agreed to accept a lease of the shop
therein described on the terms and for the period therein set forth.
By that agreement the period of the lease (121/2 years) was to commence " from
the date when the new buildings are completed and the shop is occupied " by the
appellants, two events being thus stipulated for as conditions of the
commencement of the lease.
The solution of the controversy between the parties depends on the
interpretation which is to be put on the words " the new buildings."
The respondents resolved to proceed with the re-erection of then-hotel in three
sections, the shop in question being in section No. 2. When that section was
completed, the respondents called upon the appellants to enter into occupation
of the said shop, and ultimately the appellants did so in December, 1913.
The parties are at issue as to the terms upon which such possession was taken.
The respondents maintain that it was because "the new buildings " in the sense
of the agreement had been completed, and when the appellants, therefore, were
bound to take possession, and did take possession, in terms of that agreement.
The appellants, on the other hand, maintain that they took possession before
they were bound to do so in terms of a special arrangement between them and the
respondents.
Thereafter the respondents intimated that they were not going to proceed with
the erection of section No. 3 of the proposed new buildings and the rebuilding
of that section has been definitely abandoned. In the plaint the respondents
sued the appellants for damages in respect of their refusal to enter into a
lease in terms of the said agreement. In their answer the appellants maintained
that they were not bound to enter into such a lease, as the new buildings had
never been completed.
The District Court Judge dismissed the action, with costs. On appeal the Supreme
Court reversed the decision of the District Court Judge, and gave decree against
the appellants for damages and expenses. The present appeal has been taken to
set aside the j