ABDUL MAJEED v. SILVA
NLR32V161
1930
Present: Maartensz A.J. and
Jayewardene A.J.
ABDUL MAJEED v. SILVA.
162-D. C. Colombo, 26,795.
Liquidated damages-Breach of
contract- Sum recoverable as a fine-Pre-estimate of possible damage.
Where the plaintiff entered into a contract with the defendant to make and
supply certain roofing sheets by a certain date and in default to pay a fine of
Rs. 500, which the defendant was authorized to deduct from the balance sum due
to the plaintiff who had received an advance,-
Held, that the sum provided for was liquidated damages and was recoverable as
being a genuine pre-estimate of the damage which the defendant might sustain
from a breach of the contract.
THE
plaintiff sued the defendant to recover a sum of Rs. 610.65, balance due to
him for supplying certain goods and roofing sheets. The defendant, while
admitting his liability in a sum of Rs. 110,63, claimed to set off a sum of Rs.
500 as damages in terms of an agreement (Dl) dated July 20, 1927. By the
agreement the plaintiff agreed to supply the roofing sheets by August 20, 1927,
and in default to pay a fine of Rs 500, which the defendant was authorized to
deduct from the balance due to the plaintiff, who had received an advance. The
roofing sheets were supplied in consignments, the last of which was delivered on
September 3, 1927. The learned District Judge held that the sum provided for was
a penalty and, as the defendant had not proved damages, entered judgment for the
plaintiff.
De Zoysa, K.C. (with him Rajapakse), for defendant, appellant.-The amount
specified may be deemed " liquidated damages " despite the use of the words "
fine " and " penalty" in the agreement, if such intention can be gathered from a
perusal of the whole instrument. (Wallis v. Smith [(1882) 21 Ch. D. 243.] ; Elphinstone v. Markland
Iron and Coal Co. [ (1886) 11 A. C. 332.] )
If the agreement contains several covenants of varying importance and a large
sum is made payable upon the breach of any of them irrespective of its
importance, or where the sum named is out of proportion to the contract, it is a
penalty in terrorem. (Subbramaniam v. Abeywardene 1; Wickremasuriya v. Appuhamy
2 ; Wijewardene v. Noorbhai. 3)
It is " liquidated damages " if the sum specified is a genuine pre-estimate by
the parties of the loss they contemplated ; or where a particular specified act
had to be performed and, as the extent of the damage is difficult to estimate
exactly, the parties fix upon a certain sum. (Law v. Local Board of Redditch 4 ;
Elphinstone v. Markland Co. (supra); Clydebank Engineering Co. v. Castaneda 5; Pless Poll v.
Soysa. 6 )
Tisseverasinghe, for plaintiff, respondent.-The words used are " penalty " and "
fine ". Defendant himself in his letter refers to it as " the punishment". The
onus, therefore, lies on him to show it is not a " penalty ". He has not
disproved the presumption. (10 Halsbury, p. 329, section 605, rule (1).)
The Roman-Dutch law does not allow the enforcement of agreements where the sum
stipulated is ingens or immanis. If there is an adequate means of ascertaining
the precise damage, only the actual damage suffered (of which here there is no
proof) is awarded. (10 Halsbury, p. 331, section 605, proviso to rule (6).)
The defendant elected to prove the actual damages sustained by him, and the
finding of the Court below is that he had failed. The question whether the
amount is a penalty or liquidated damages therefore does not arise.
A comparison of the two contracts, one for damages at Rs. 10 a day and the other
for a lump sum of Rs. 800, irrespective of the period of delay, shows that the
latter is a penalty.
Foot notes
1 21 N.L.R. 161.
2 6 C. W. R. 57.
3 28 N. L. R. 430.
4
(1892) 1 Q.B. 127.
5 (1905) A. C. 6.
6 15 N. I. R. 57.
Rajapakse, in reply.-The Roman-Dutch law is in our favour ; in any case the
English law is applicable in Ceylon [1 28 N. L. R. 430. ]. If the sum is held to be " liqui