MOHAMED v. WIJEYEWARDENE
NLR48V73
1947 Present : Keuneman
and Canekeratne JJ.
MOHAMED, Appellant, and WIJEYEWARDENE, Respondent.
232-D.C.Colombo, 14,579
Building contract-Provision,
for payment of liquidated damages for delay in completion of building-Completion
of building-condition precedent for applicability of such provision.
In a building contract a provision for payment of liquidated damages
for delay in completion of the building
applies, unless otherwise expressly provided for, only when the Contractor has
in fact completed the building, and has no application where he does not
complete the work.
APPEAL
from a judgment of the District Court of
Colombo.
The plaintiff sued the defendant for damages on an alleged breach of a building
contract. He alleged that the defendant, the builder, had without justification
stopped the execution of the works and failed to proceed with and complete the
same.
The defendant has in fact agreed to complete the buildings ready for occupation
by May 21,1942. This was under clause 21. Clause 22 of the agreement ran as
follows:-- "22. If the contractor fails to complete the works by the date named
in clause 21 or within any extended time to which he may become entitled under
these presents and if the architects shall certify in writing on or before the
date of issue of their certificate for the last payment to which the contractor
may become entitled here under that the works could reasonably have been
completed by the said date or within the said extended time, then the contractor
shall pay or allow to the employers the sum of Rs.500 per month as agreed and
liquidated damages and not by way of penalty of every month beyond the said date
or extended time, as the case may be, during which the works shall remain
unfinished, and such damages may be deducted from any moneys due or which may
become due to the contractor."
It was argued on behalf of the appellant that clause 22 could only operate if
the builder or contractor in fact completed the building and had no application
where he did not complete the work.
H. V. Perera, K.C. (with him C. Thiagalingam), for the defendant,
appellant.
N. Nadarajah, K.C. (with him Ivor Misso), for the plaintiff,
respondent.
Cur. adv. vult.
February 26, 1947. KEUNEMAN
J.-
This is action for damages on an alleged breach of building contract. The
plaintiff alleged that the defendant, the builder, has without justification
stopped the execution of the works and failed to proceed with and complete the
same. Plaintiff claimed as damages (1) Rs.4,000 from the date of the alleged
breach until date of action at the rate of Rs.500 per month, and (2) Rs.2,651.25
being the balance due out of an advance of Rs.6,000 with interest at five
percent. Less the sum of Rs.3,723.75 being for work done by the defendant.
The defendant raised various
defences to the plaintiff's claim and counterclaimed on various ground in the
sum of Rs.2,035.76.
The district judge as regards plaintiff's claim (1) awarded him Rs.3,000 and as
regards claim (2) Rs. 1,587.66, making a total of Rs.4,587.66.
The principal matter which was argued before us related to plaintiff's claim
(1). The only issue framed regarding damages was issue 5 as amended, viz., "Has
defendant become liable under clause 22 of the contract to pay plaintiff as
agreed and liquidated damages Rs. 500 per mensem for every month the work remain
unfinished after May 21, 1942?". The defendant in fact agreed to complete the
buildings ready for occupation by May 21,1942. This was under clause 21.
Clause 22 of the agreement P 1 runs as follows:-
"22. If the contractor fails to complete the works by the date named in clause
21 or within any extended time to which he may become entitled under these
presents and if the Architects shall certify in writing on or before the date of
issue of their certificate for the last payment to which the contractor may
become entitled here date or w
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.