S.H.KAPADIA, B.SUDERSHAN REDDY
Pundlik Jalam Patil (D) by Lrs. – Appellant
Versus
Exe. Eng. Jalgaon Medium Project – Respondent
Leave granted.
2. These appeals, by Special Leave, are directed against the common judgment
and order dated 22/23.08.2007 of the High Court of Bombay, Bench at Aurangabad allowing the applications filed by the first respondent under Section 5 of the Limitation Act, 1963 (hereinafter referred to as `the said Act) to condone the delay of 1724 days in filing appeals against the award passed by the Civil Judge, Senior Division, Jalgaon in land acquisition cases. The High Court accepted the explanation offered by the respondent no. 1 herein for the apparent inordinate delay in filing the appeals against the award of the Reference Court.
3. Brief facts needed for disposal of these appeals are as under:
4. The lands belonging to the appellants were acquired at the instance of the respondent for a public purpose under the draft Notification published in Maharashtra Government Gazette on 06.03.1997. The Special Land Acquisition Officer, Upper Tapi Project (Hatnur), Jalgaon passed the award dated 31.3.1999. The appellant sought for reference of the said award under Section 18 of the Act seeking enhancement of the compensation. The learned Civil Judge, Senior Division, Jalgaon disposed of the ref
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.