SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(SC) 1286

SUPREME COURT OF INDIA
J. CHELAMESWAR, SANJAY KISHAN KAUL, JJ.
SUTLEJ CONSTRUCTION - Appellant
Versus
UNION TERRITORY OF CHANDIGARH - Respondent
CIVIL APPEAL No. 20885 of 2017
Decided on : 05-12-2017

The court upheld the arbitrator's award, emphasizing that the arbitrator's findings should not be re-appreciated and that the respondent's non-compliance led to the illegal termination of the contract.

Headnote:

Arbitration - Contract Dispute - Arbitration & Conciliation Act, 1996 - Section 34 - Performance of Contractual Obligations - Illegal Termination - Award Upheld

Fact of the Case:

The appellant was awarded a contract for earth excavation work and loading into trucks for road widening. The respondent terminated the contract, leading to arbitration. The arbitrator partly allowed the appellant's claims and rejected the respondent's counterclaims.

Finding of the Court:

The court found that the respondent's breaches caused delays and led to the illegal termination of the contract. The arbitrator's award was reasoned and upheld the appellant's claims.

Issues: Dispute over contract performance, termination, and arbitration process under Section 34 of the Arbitration & Conciliation Act, 1996.

Ratio Decidendi: The court held that the arbitrator's findings were based on evidence and should not be re-appreciated. The respondent's non-compliance with obligations led to the illegal termination of the contract.

Final Decision: The impugned order was set aside, and the enforcement of the award was upheld. The appeal was allowed without imposing costs.

JUDGMENT :

SANJAY KISHAN KAUL, J.

Leave granted.

1. The appellant was awarded a contract by the respondent of earth excavation work and loading into trucks and unloading for purposes of widening of the approach road Sukhna Choe on Chandigarh Kalka Road, Chandigarh vide memo No.201 dated 5.1.1996. The earth was required to be lifted from the first source near the regulator and carried through trucks from Golf side initially. There was a second source of lifting the earth as per permission of the Superintendent Engineer but it is not necessary to go into the details of the contract for the present purposes. Suffice to say that the respondent alleges that the appellant did not fulfil its obligations while the appellant, on the other hand, alleges that what was required to be done by the respondent to facilitate execution of the contract was not so done. This resulted in the respondent terminating the contract on 12.11.1996.

2. The conditions of the contract provided for arbitration and despite the appellant invoking the arbitration clause, the Superintendent Engineer failed to nominate an Arbitrator resulting in the appellant approaching the Court. In the course of the said proceedings Mr. R.N. Singal, retired District & Sessions Judge was appointed as an arbitrator in terms of order dated 31.7.2002 of the learned Civil Judge (Senior Division), Chandigarh.

3. The parties put forth their respective claims before the arbitrator. The appellant laid the claims while the respondent filed the counterclaims. The arbitrator made and published an Award dated 18.12.2013, partly allowing the claim of the appellant while rejecting the counterclaims of the respondent. The claims laid and the extent awarded as well as the counterclaims laid are as under:       

Claims made by the Appellant

Amount awarded by the Arbitrator

S.No.

Particulars

Amount (in INR)

Particulars

Amount (in INR)

1.

Balance payment accruing from the last running bill

2,00,014

Claim No.1 and amount deposited by way of earnes

1,20,299

32,000

2.

Payment due on account of transportation or earth not measured by department

1/11/231

Claim No.3

65,076

3.

Payment due on account of less lead paid

95,400

Claim No.4

7,74,375

4.

Idle hour charges of heavy earth moving machinery and labour deployed on the machinery

31,22,280

Claim No.6

45,435

5.

Payment due on account of earth eroded by heavy rains due to non-compaction of earth and leaking water pipelines

1,69,206

--

--

6.

Payment on account of loss of profit on balance work

90,835

--

--

7.

Loss due to prolongation of work

12,80,000

--

--

8.

Litigation expenses

25,000

--

--

Total

50,93,966

Total

10,37,185

Interest @ 12% per annum was also allowed by the arbitrator in favour of the appellant.       

Counterclaims made by the respondent

1.

Liquidated damages and the expenses incurred by it for completion of work

8,01,808

2.

Loss due to delay in completion of work

20,00,000

Total

28,01,808

4. The respondent aggrieved by the Award filed objections under Section 34 of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as the ‘said Act’), which were, however, rejected by the learned Additional District Judge, Chandigarh vide order dated 23.7.2013. The respondent thereafter preferred an appeal before the Punjab & Haryana High Court and the said appeal succeeded whereby the Award was set aside opining that the contract was rightly terminated and the Department rightly imposed the penalty.

5. We have heard learned counsel for the parties and have perused the record. The Award is a reasone













Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top