SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Online)(SC) 9830

REPORTABLE

2024 INSC 711 IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS. 3981-3982 OF 2024 (Arising out of SLP (Civil) Nos.21017-21018 of 2021)

OPG POWER GENERATION PRIVATE LIMITED … APPELLANT(S)

Versus ENEXIO POWER COOLING SOLUTIONS INDIA PRIVATE LIMITED & ANR. … RESPONDENT(S)

With CIVIL APPEAL NOS. 3983-3984 OF 2024 (Arising out of SLP (Civil) Nos.21009-21010 of 2021)

J U D G M E N T

MANOJ MISRA, J.

1. These two appeals are directed against a common judgment and order of the High Court1 dated 1 September 2021 passed in OSA (CAD) Nos. 174-175 of 2021, whereby, exercising powers under Section 37 of the Arbitration and Conciliation Act, 19962 read with Section 13(1) of the Commercial Courts Act, 20153 and Clause 15 of Amended Letters Patent, 1865 read with Order XXXVI Signature Not Verified Digitally signed by Sanjay Kumar D 15a :t 1e 1: :2 50 52 I14 S. T0 H9.2 i0 gh Court of Judicature at Madras Reason:

2 1996 Act 3 2015 Act Rule 9 of O.S. Rules, the Division Bench of the High Court allowed the appeals, set aside the judgment and order of the Single Judge dated 23 December 2020 and restored the arbitral award dated 13 July 2020.

THE CONTRACT

2. OPG Power Generation Private Ltd (in short OPG - the appellant in the leading appeal), a subsidiary of Gita Power and Infrastructure Private Limited (in short Gita Power – Respondent No.2 (R-2) in the leading appeal, and appellant in the connected appeal), floated a composite tender for design, manufacture, supply, erection and commissioning of air-cooled condenser unit (ACC Unit) with auxiliaries for 160 MW Coal Based Thermal Power Plant (Project) at Gummidipoondi in the State of Tamil Nadu. Enexio Power Cooling Solutions (in short Enexio - Respondent No.1 (R-1) in the leading appeal) bid for the project. After a series of correspondences /negotiations, on 4 March 2013, R-2 issued two separate orders: (i) for design, engineering and supply of one ACC Unit with auxiliaries for 160 MW Coal Based Power Project at Gummidipoondi (in short, Supply Purchase Order); and (ii) for erection and commissioning of one unit of ACC with auxiliaries for 160 MW Coal Based Power Project at Gummidipoondi (in short, Erection Purchase Order). Interestingly, the tender was floated by OPG but the supply and erection orders were issued by its holding company (Gita Power - R-2) on 4 March 2013. However, later, in the month of July 2013, OPG confirmed those orders by issuing two separate orders with same terms and bearing the same date i.e. 4 March 2013.

3. The supply / erection purchase orders with its enclosures contained an arbitration clause in the following terms:

Clause 21. ARBITRATION

21.1. In the event of any dispute or difference arising under the Order or in connection therewith including any question relating to existence, meaning and interpretation of the Order or any alleged breach thereof that cannot be amicably settled between the Parties, the same shall be referred to the arbitration.

21.2. Arbitration shall be conducted under the Rules of Conciliation and Arbitration of the International Chamber of Commerce by three arbitrators appointed in accordance with said rules. The place of arbitration will be at Chennai. The arbitration proceedings shall be conducted in the English language.

21.3. The arbitrators shall take into consideration the will of the Parties as expressed in the Order, the evidence presented, the principles of equity and good faith. The decision(s) of the arbitrators shall be final and both Parties undertake to fulfil and execute the said decision(s).

21.4. Notwithstanding any dispute between the parties, Parties shall not be entitled to withhold/ delay/defer their obligations under the Order and same shall be carried out strictly in accordance with the terms and conditions of the Order.”

4. Clause 6 of the supply purchase order provided:

6-Tax and duties:

6.1. Taxes, duties and levies payable and charged by the competent authority such as Excise Duty, Sales Tax, Cess will be borne and paid by the Purchaser.

6.2. The Purchaser shall issue Central Sales Tax Form C or any other Form as applicable for interstate sale.”

5. Likewise, clause 6 of the erection purchase order provided:

6-Tax and duties:

6.1. All taxes duties and local levies payable and charged by the Competent Authority for the Services, such as Service Tax, cess, work order tax and other charges whi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top