HIGH COURT OF DELHI
CHENNAI ???ENNORE PORT ROAD CO. LTD – Appellant
Versus
RDS PROJECT LTD – Respondent
OMP-213_2013
OMP Nos. 23, 213 and 419/2013 Page 1 of 34
$~
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
O.M.P. 23/2013
CHENNAI –ENNORE PORT ROAD CO. LTD. ..... Petitioner
Through: Mr. Arun Kumar Varma
with Ms. Sahiti Kachroo and Mr.
Mayank Sapra, Advocates.
versus
RDS PROJECT LTD.
..... Respondent
Through: Mr. Jagdeep Dhankar, Senior
Advocate with Ms. Asha Jain Madan and
Mr. Mukesh Jain, Advocates.
WITH
+
O.M.P. 213/2013
CHENNAI –ENNORE PORT ROAD CO. LTD. ..... Petitioner
Through: Mr. Arun Kumar Varma with Ms.
Sahiti Kachroo and Mr. Mayank Sapra,
Advocates.
versus
RDS PROJECT LTD.
..... Respondent
Through: Mr. Jagdeep Dhankar, Senior
Advocate with Ms. Asha Jain Madan and
Mr. Mukesh Jain, Advocates.
AND
O.M.P. 419/2013
CHENNAI –ENNORE PORT ROAD CO. LTD. ..... Petitioner
2015:DHC:3682
OMP Nos. 23, 213 and 419/2013 Page 2 of 34
Through: Mr. Arun Kumar Varma with Ms.
Sahiti Kachroo and Mr. Mayank Sapra,
Advocates.
versus
RDS PROJECT LTD.
..... Respondent
Through: Mr. Jagdeep Dhankar, Senior
Advocate with Ms. Asha Jain Madan and
Mr. Mukesh Jain, Advocates.
CORAM: JUSTICE S. MURALIDHAR
J U D G M E N T
%
23.04.2015
1. These are three petitions by the Chennai-Ennore Port Road
Company Ltd. („CEPRCL‟) under Section 34 of the Arbitration and
Conciliation Act, 1996 („Act‟) challenging three separate Awards
rendered by the Arbitral Tribunal („AT‟) in three references made to it
regarding disputes that arose between the Petitioners and the
Respondent RDS Project Ltd. („RDSPL‟) out of a formal agreement
signed between them on 20th May 2003 for execution of „Sea
Protection work along the Ennore Expressway” in Chennai.
Background
2. The Petitioner is a Special Purpose Vehicle of the National
Highways Authority of India („NHAI‟). Clause 1.1 of the agreement
defines the scope of works. The Petitioner was required to construct
10 Groyne rigid hydraulic wooden/concrete structures built to
2015:DHC:3682
OMP Nos. 23, 213 and 419/2013 Page 3 of 34
interrupt water flow and limit the movement of sediment in sea/ocean
which are found used in tandem with seawalls.
3. Under Clause 1.1 of the agreement, the scope of works was
specified as under:
(i) Identification of quarries for supply of stones of required
specifications.
(ii) Arranging transportation of these stones from the quarries to the
work sites and
(iii) Construction of Groynes according to the specific design,
standards and specifications.
4. There were three separate schedules of quantities for Groyne Fields.
Schedule A1 specified the quantities for Groyne Fields I and II.
Schedule A2, the quantities for construction of 500m long sea wall
north of the northern most Groyne No. 6 in Groyne Field I and
Schedule A3, the quantities for strengthening of sea walls between
groynes in Groyne Field I and Groyne Field II.
5. Since the construction was peculiar as it was to be carried out
underwater, the contract provided for separate bills of quantities
(„BOQs‟) for different layers of the work to be constructed by the
Respondent. The quantities were to be paid in metric tons („MT‟) basis
and this would account for the fact that there was a difference in the
quantities of stones brought on site and those forming part of the
2015:DHC:3682
OMP Nos. 23, 213 and 419/2013 Page 4 of 34
finished work since there could be some amount of stones that would
sink with the waves. The method for measuring the executed
quantities for the purposes of payment under the BOQ was also
provided in the agreement.
6. The layers w