HINDUSTAN CONSTRUCTION CO.LTD – Appellant
Versus
UNION OF INDIA – Respondent
REQ. CASE 19/2009
IN THE HIGH COURT OF JUDICATURE AT PATNA
REQ. CASE No.20 of 2009
HINDUSTAN CONSTRUCTION CO.LTD.
Versus
UNION OF INDIA
with
REQ. CASE No.19 of 2009
HINDUSTAN CONSTRUCTION CO.LTD.
Versus
UNION OF INDIA
----------
For the Petitioner: Mr Jayanta Mitre, Senior Advocate
Mr P.K.Dutte, Senior Advocate
Mr. Subhro Sanyal, Advocate
For the Respondent: Mr Mahesh Prasad
Standing Counsel Railways
----------
02/
13.11.2009
Both the matters arise out of the same agreement
between the same parties who are also parties in these two cases.
2. Heard learned counsel for the petitioner and the
respondent.
3. Request case no. 20 of 2009 has been filed on behalf of
the petitioner, which is a construction company, under section 11(6)
of the Arbitration and Conciliation Act,1996 (hereinafter referred to
as >the Act? for the sake of brevity) for appointment of Arbitrator for
determining the disputes and differences which have arisen between
the parties and were covered under the Arbitration Clause contained
in the contract between the parties and which are as follows:
<(i) What is the correct and proper
interpretation of the Price Variation Clause, being Clause
20 of the Special Conditions of the Contract (General)?
(ii) Whether it was the intention of the
parties, which intention can be inferred from the different
clauses of the contract, that in respect of abnormal and
unusual rise in the prices of the said materials, which
could not be covered by the Price Variation Clause, was to
be absorbed by the petitioner?
(iii) In a true and proper interpretation of
the contractual provisions, it could be contended that
whether to supply or not to supply the said materials was
- 2 -
within the absolute discretion of the Respondent-
Railways?
(iv) Is the petitioner right in its contention
that on a correct interpretation of the relevant clauses of
the contract an obligation was cast upon the Respondent-
Railway to supply the said materials, when the same were
available with the Railways?
(v) Whether the petitioner is entitled to
claim a sum of Rs 3.78 crores from the respondent on
account of the escalation of steel as demanded in its letter
dated 8th September, 2005 and further sums till the
completion of the contract?
(vi) To that relief, if any, is the petitioner
entitled against the respondent?=
4. Learned counsel for the petitioner submits that clause 64
of the agreement which is detailed at page 228 of the brief is the
clause with regard to arbitration. Hence when there was abnormal
rise in the steel prices, not forseen at the time of bidding by any
means which has resulted in enormous additional cost to the
petitioner, the petitioner sent a letter dated 08.09.2005 (Annexure 13)
notifying its intention to commence arbitration on the matter of
dispute and requested the respondent to initiate necessary procedures
for constitution of arbitral tribunal.
5. The respondent vide their letter dated 28.02.2007
(annexure 15) sending a panel of four names, out of whom two were
to be selected by the petitioner. It transpires that the petitioner did
not make his choice and instead sent letter dated 30.04.2007
(annexure 14 ) to the respondent stating that since they had given
notice to the railway in that regard, they requested to amicably
resolve the matter under dispute.
6. The Respondent replied vide letter dated 25.09.2007
(annexure 16) stating that since the petitioner had not chosen any
- 3 -
person from the panel sent by the respondent they had appointed a
tribunal of three persons and the petitioner
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.