HIGH COURT OF PUNJAB AND HARYANA
BHARAT SANCHAR NIGAM LTD – Appellant
Versus
BHURUMAL AND ANR – Respondent
CWP 13187/2011
Civil Writ Petition No. 13187 of 2011
-1-
IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH
Civil Writ Petition No. 13187 of 2011
Date of decision:-27.7.2011
Bharat Sanchar Nigam Ltd.
...Petitioner
Versus
Sh. Bhurumal and another
...Respondents
CORAM: HON'BLE MS. JUSTICE RITU BAHRI
Present:-
Mr. Madan Mohan, Advocate
for the petitioner.
RITU BAHRI J.
Challenge is to the Labour Court award dated 11.4.2011 (Annexure
P-6) whereby the petitioner has challenged the Award on the ground that the
respondent No.1 was employed by a contractor and the petitioner was not
directly involved in release of salary in other service commitments.
Respondent No.1 was engaged as daily wage lineman w.e.f.
1.7.1987. His services were terminated on 27.4.2002. Neither any show cause
notice was served upon respondent No.1 nor any inquiry was held. No retrench
compensation was paid. He raised a demand notice to file his claim statement
(Annexure P-2) before the Labour Court. In his claim statement his precise
grievance is that he has worked for 15 years under the respondent-BSNL,
Sonipat (Haryana) w.e.f. July 1987 till April 2002. On 17.11.2001 when the
workman was on duty at 11 AM and repairing the fault of telephone No.65033,
he met with an accident. He was climbing of a phone pole and 11000 volts
electric line was going over the telephone pole and an electric current was
caused to the workman and because of that the workman became unconscious
Civil Writ Petition No. 13187 of 2011
-2-
and his right hip and right little finger were broken. He was shifted to Dr. Sethi
Hospital on 18.11.2001 and on 19.11.2001 he was referred to the Medical
College, Rohtak. Appropriate help was given by Jatinder Kumar, SDO and Manjit
Singh JTO to the workman and he was assured that he will be allowed to re-join
after discharge from the hospital. The workman is claiming salary and treatment
expenses from the Department on account of electric shock while working on the
telephone wire during the duty time. The Management terminated the workman
w.e.f. 28.4.2002.
The respondents filed the reply (Annexure P-4). Vide Award
(Annexure P-6) dated 11.4.2011 the reference was answered in favour of the
workman. Mr. Madan Mohan, counsel for the petitioner has argued that in the
reply a specific stand was taken before the Labour Court while filing the reply
that the work was being got done through a contractor under the duly executed
agreement. There was no direct relation of master and servant with the
respondent No.1-workman. He was never recruited according to recruitment
rules prescribed for the appointment. The documents submitted by the claimant
from C-15 to C-44 are manufactured documents where an attempt is being made
to show that the documents were shown signed by the JTO and by the SDO with
whom he has worked. No evidence has been led to show that the wages were
directly paid by the Department. He has placed reliance of the judgment of the
Supreme Court in International Airport Authority of India versus
International Air Cargo Workers' Union and another (2009) 13 Supreme
Court Cases 374 to contend that there was no relationship of master and servant
with the workman.
After hearing counsel for the petitioner, it is not disputed that the
workman had worked for almost for 15 years as a daily wage workman as
lineman. The documents filed by the workman beyond doubt proved that he had
Civil Writ Petition No. 13187 of 2011
-3-
been working with the petitioner Management as lineman. The diaries, which
have been filed by the workman were prepared in an ordinary course of business
proved that the workman was working directly under the administrative control
of the Management. It is established before the Tribunal that the workman had
met with an accident while working in the office hours of the Management. He
was socially emotionally and financially helped at the time of accident. The
Managem